Fees for Service

Fees for Services

Due to fiscal year-end closeout, the Bureau of Safety and Environmental Enforcement (BSEE) will disable the electronic Fees for Services Refund Request Form from 5:00 p.m. Eastern Time, Friday, September 14, 2018, to 9:00 a.m. Monday, October 1, 2018.

In addition, BSEE will disable Pay.Gov forms and payment options for eWell, Disc Media Store, and Public Information Ordering System from 5:00 p.m. Eastern Time, Friday, September 21, 2018, to 9:00 a.m. Monday, October 1, 2018. Accordingly, September 21, 2018 is the final day for accepting payments in Fiscal year 2018.

For more information see

https://www.bsee.gov/sites/bsee.gov/files/notices-to-lessees-ntl//ntl-2018-n04-outage-of-fees-for-services-due-to-fiscal-year-end-closeout.pdf

NOTE:

  •  Effective June 1, 2015 the U.S. Treasury has changed the Credit Card payment limit from $49,999.99 to $24,999.99 for Paygov payments. The ACH (electronic check) remittance is to be used for payments greater than $24,999.99.

Please click on the appropriate section below to locate your specific needs:

Appeals   Exploration & Development Plans Facility & Well Permits   FOIA Bill for Collection Miscellaneous Collections
Pipeline Production & Development   Refund
Request
Structures  

 

Appeals

Service Cost
Appeals $150
Open Access Complaints $7,500

 

Exploration and Development Plans

Service Cost
Deepwater Operations Plan $3,599

 

Facility and Well Permits

Service Cost
Application for permit to drill $2,113
Application for permit to modify $125
New facility production safety system application varies
Modification production safety system application varies

 

Miscellaneous Collections

Service Cost
Includes; Jury Duty, Travel Voucher Repayment, Centrally Billed Repayment, Vendor, etc) varies
Ohmsett Collections varies

 

Pipeline

Service Cost
Pipeline ROW grant application $2,771
Pipeline ROW grant assignment $201
Pipeline application modification - ROW $4,169
Pipeline conversion of lease term to ROW $236
New pipeline application - Lease Term $3,541
Pipeline application modification - Lease Term $2,056
Pipeline repair notification $388
Application to Relinquish a ROW and Decommission Pipeline $2,170
Application to decommission a pipeline - Lease Term $1,142

 

Production and Development

Service Cost
Suspensions of operations/suspensions of production $2,123
500 feet from lease/unit line production request $3,892
Gas cap production request $4,953
Downhole commingling request $5,779
Voluntary unitization proposal or unit expansion $12,619
Unitization revision $896
Surface commingling & measurement application varies
Royalty Relief Application varies

 

Structures (or Platforms)

Service Cost
Platform application installation under platform verification program $22,734
Platform application - fixed structure under the platform approval program $3,256
Platform application - Caisson well protector $1,657
Platform application - Modification $3,884
Application to remove a platform $4,684