At our meeting in Menlo Park the first week of February, we agreed to two sets of products we feel can be completed at least in a preliminary form by the end of FY99. The tables that follow document those products, the components, coordinating scientists, and target dates:
May |
Lugo |
10m DEM's |
May |
Yount |
Particle size/soil samples |
June |
Yount, Miller, Calzia |
Surficial geology/Bedrock geology |
June |
Flint |
Lab analyses |
June |
Thomas, Benjamin |
Vegetation |
June |
Hereford |
Climate |
June |
Berry/Benjamin |
Human impacts |
July |
Webb |
Compaction curves |
July |
Berry |
Potential tortoise habitat |
July |
Flint |
Soil moisture model |
July |
Belnap/Phillips |
Crust study and wind effects |
Sept |
Phelps, Bedford |
Statis compaction model |
Sept |
Cruse |
Web and visualization / DSS prototype |
|
Brooks |
Fire perimeters |
|
Flint |
Large area coarse vulnerability to compaction |
|
Hereford |
Climate atlas |
|
Brooks |
Fire ecology handbook |
|
Webb |
Vulnerability and recoverability factors to soil compaction |
|
Brooks |
Exotics handbook |
|
Lovich |
Mojave Science Symposium abstracts |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|