Federal Transit Administration |
|
Federal Transit Administration |
57. |
Rail Fixed Guideway Systems: State Safety Oversight |
Green |
|
Popular Title: State Safety Oversight |
RIN 2132-AA76 |
Stage: NPRM |
Previous Stage:None |
Abstract: In 1995, under RIN 2132-AA39, FTA issued the final rule entitled, Rail Fixed Guideway Systems; State Safety Oversight. On December 23, 1996, under RIN 2132-AA57, FTA issued technical amendments to the final rule. Then in 2002, under RIN 2132-AA69, FTA issued a direct final rule amending the definition of accident. Because FTA received an adverse comment, the direct final rule was withdrawn and the next action was listed as undetermined while the next course of action was determined. FTA now intends to amend the rule, and has closed out RIN 2132-AA69, and opened RIN 2132-AA76, for this action. This rulemaking would add safety standards or guidance and significantly update existing rules in light of the increase in the number of state safety oversight agencies since the original FTA rule was issued. |
Effects:
|
Prompting action: None |
|
Rulemaking Project Initiated: 06/23/2003 |
Dates for NPRM:
Milestone | Originally Scheduled Date | New Projected Date | Actual Date |
To OST |
09/15/2003 |
11/12/2003 |
10/27/2003 |
Publication Approved |
02/15/2004 |
03/12/2004 |
01/22/2004 |
Publication Date |
02/18/2004 |
03/19/2004 |
03/09/2004 |
End of Comment Period |
04/18/2004 |
05/18/2004 |
06/07/2004 |
|
Explanation for any delay: |
N/A
|
|
Federal Register Citation for NPRM: 69 FR 11218 |