Subject to subsection (c) of this section, each such disposal site shall be specified for each such permit by the Secretary
in any case where such guidelines under clause (1) alone would prohibit the specification of a site, through the application additionally of the economic impact of the site on navigation and anchorage.
The term "Secretary" as used in this section means the Secretary of the Army, acting through the Chief of Engineers.
No general permit issued under this subsection shall be for a period of more than five years after the date of its issuance and such general permit may be revoked or modified by the Secretary if, after opportunity for public hearing, the Secretary determines that the activities authorized by such general permit have an adverse impact on the environment or such activities are more appropriately authorized by individual permits.
Any discharge of dredged or fill material into the navigable waters incidental to any activity having as its purpose bringing an area of the navigable waters into a use to which it was not previously subject, where the flow or circulation of navigable waters may be impaired or the reach of such waters be reduced, shall be required to have a permit under this section.
Not later than the tenth day after the date of the receipt of the program and statement submitted by any State under paragraph (1) of this subsection, the Administrator shall provide copies of such program and statement to the Secretary and the Secretary of the Interior, acting through the Director of the United States Fish and Wildlife Service.
No later than the ninetieth day after the date of the receipt by the Administrator of the program and statement submitted by any State, under paragraph (1) of this subsection, the Secretary and the Secretary of the Interior, acting through the Director of the United States Fish and Wildlife Service, shall submit any comments with respect to such program and statement to the Administrator in writing.
To issue permits which apply, and assure compliance with, all applicable requirements of section 308 of this Act, or to inspect, monitor, enter, and require reports to at least the same extent as required in section 308 of this Act. To assure that the public, and any other State the waters of which may be affected, receive notice of each application for a permit and to provide an opportunity for public hearing before a ruling on each such application. To assure that the Administrator receives notice of each application (including a copy thereof) for a permit. To assure that any State (other than the permitting State), whose waters may be affected by the issuance of a permit may submit written recommendation to the permitting State (and the Administrator) with respect to any permit application and, if any part of such written recommendations are not accepted by the permitting State, that the permitting State will notify such affected State (and the Administrator) in writing of its failure to so accept such recommendations together with its reasons for so doing. To assure that no permit will be issued if, in the judgement of the Secretary, after consultation with the Secretary of the department in which the Coast Guard is operating, anchorage and navigation of any of the navigable waters would be substantially impaired thereby. To abate violations of the permit or the permit program, including civil and criminal penalties and other ways and means of enforcement. To assure continued coordination with Federal and Federal-State water-related planning and review processes.
If, with respect to a State program submitted under subsection (g)(l) of this section, the Administrator determines that such State -
After the Secretary receives notification from the Administrator under paragraph (2) or (3) of this subsection that a State permit program has been approved, the Secretary shall transfer any applications for permits pending before the Secretary for activities with respect to which a permit may be issued pursuant to such State program to such State for appropriate action.
Upon notification from a State with a permit program approved under this subsection that such State intends to administer and enforce the terms and conditions of a general permit issued by the Secretary under subsection (e) of this section with respect to activities in such State to which such general permit applies, the Secretary shall suspend the administration and enforcement of such general permit with respect to such activities.
notify the Secretary that the Secretary shall resume the programs for the issuance of permits under subsection (a) and (e) of this section for activities with respect to which the State was issuing permits and that such authority of the Secretary shall continue in effect until such time as the Administrator makes the determination described in clause (1) of this subsection and such State again has an approved program.
a copy of each proposed general permit which such State intends to issue. Not later than the tenth day after the date of the receipt of such permit application or such proposed general permit, the Administrator shall provide copies of such permit application or such proposed general permit to the Secretary and the Secretary of the Interior, acting through the Director of the United States Fish and Wildlife Service. If the Administrator intends to provide written comments to such State with respect to such permit application or such proposed general permit, he shall so notify such State not later than the thirtieth day after the date of the receipt of such application or such proposed general permit and provide such written comments to such State, after consideration of any comments made in writing with respect to such application or such proposed general permit by the Secretary and the Secretary of the Interior, acting through the Director of the United States Fish and Wildlife Service, not later than the ninetieth day after the date of such receipt. If such State is so notified by the Administrator, it shall not issue the proposed permit until after the receipt of such comments from the Administrator, or after such ninetieth day, whichever first occurs. Such State shall not issue such proposed permit after such ninetieth day if it has received such written comments in which the Administrator objects (A) to the issuance of such proposed permit and such proposed permit is one that has been submitted to the Administrator pursuant to subsection (h)(l)(E), or (B) to the issuance of such proposed permit as being outside the requirements of this section, including, but not limited to, the guidelines developed under subsection (b)(l) of this section unless it modified such proposed permit in accordance with such comments. Whenever the Administrator objects to the issuance of a permit under the preceding sentence such written objection shall contain a statement of the reasons for such objection and the conditions which such permit would include if it were issued by the Administrator. In any case where the Administrator objects to the issuance of a permit, on request of the State, a public hearing shall be held by the Administrator on such objection. If the State does not resubmit such permit revised to meet such objection within 30 days after completion of the hearing or, if no hearing is requested within 90 days after the date of such objection, the Secretary may issue the permit pursuant to subsection (a) or (e) of this section, as the cause may be, for such source in accordance with the guidelines and requirements of this Act.
The Administrator shall promulgate regulations establishing categories of discharges which he determines shall not be subject to the requirements of subsection (j) of this section in any State with a program approved pursuant to subsection (h)(2)(A) of this section. The Administrator may distinguish among classes, types, and sizes within any category of discharges.
Not later than the ninetieth day after the date on which the Secretary notifies the Secretary of the Interior, acting through the Director of the United States Fish and Wildlife Service that
the Secretary proposes to issue a general permit under subsection (e) of this section, the Secretary of the Interior, acting through the Director of the United States Fish and Wildlife Service, shall submit any comments with respect to such application or such proposed general permit in writing to the Secretary.
A copy of each permit application and each permit issued under this section shall be available to the public. Such permit application or portion thereof, shall further be available on request for the purpose of reproduction.
Compliance with a permit issued pursuant to this section, including any activity carried out pursuant to a general permit issued under this section, shall be deemed compliance, for purposes of sections 309 and 505, with sections 301, 307, and 403.
Not later than the one-hundred-eightieth day after the date of enactment of this subsection, the Secretary shall enter into agreements with the Administrator, the Secretaries of the Departments of Agriculture, Commerce, Interior, and Transportation, and the heads of other appropriate Federal agencies to minimize, to the maximum extent practicable, duplication, needless paperwork, and delays in the issuance of permits under this section. Such agreements shall be developed to assure that, to the maximum extent practicable, a decision with respect to an application for a permit under subsection (a) of this section will be made not later than the ninetieth day after the date the notice of such application is published under subsection (a) of this section.
The discharge of dredged or fill material as part of the construction of a Federal project specifically authorized by Congress, whether prior to or on or after the date of enactment of his subsection, is not prohibited by or otherwise subject to regulation under this section, or a State program approved under this section, or section 301(a) or 402 of the Act (except for effluent standards or prohibitions under section 307), if information on the effects of such discharge, including consideration of the guidelines developed under subsection (b)(l) of this section, is included in an environmental impact statement for such project pursuant to the National Environmental Policy Act of 1969 and such environmental impact statement has been submitted to Congress before the actual discharge of dredged or fill material in connection with the construction of such project and prior to either authorization of such project or an appropriation of funds for each construction.
A copy of any order issued under this subsection shall be sent immediately by the Secretary to the State in which the violation occurs and other affected States. Any order issued under this subsection shall be by personal service and shall state with reasonable specificity the nature of the violation, specify a time for compliance, not to exceed thirty days, which the Secretary determines is reasonable, taking into account the seriousness of the violation and any good faith efforts to comply with applicable requirements. In any case in which an order under this subsection is issued to a corporation, a copy of such order shall be served on any appropriate corporate officers.
The Secretary is authorized to commence a civil action for appropriate relief, including a permanent or temporary injunction for any violation for which he is authorized to issue a compliance order under paragraph (1) of this subsection. Any action under this paragraph may be brought in the district court of the United States for the district in which the defendant is located or resides or is doing business, and such court shall have jurisdiction to restrain such violation and to require compliance. Notice of the commencement of such action shall be given immediately to the appropriate State.