Title: Moratorium on Significant Information Technology Acquisitions
Number: 00-001
Date: 03/15/2000
Originating Office: Information Technology Division, AFM/ARS
Distribution: REE Offices in Headquarters, Areas (ARS - AD's, AAO's, PAO's) and Field Locations
Expires: Remains in effect until further notification

 

 

This Bulletin announces the increase of the moratorium threshold from $25,000 to $250,000. This bulletin describes the Information Technology (IT) Moratorium, explains the process for obtaining a waiver, and the justification needed for approval.

This bulletin replaces Bulletin 98-002, dated March 10, 1998, Bulletin 98-005 dated June 15, 1998, and Bulletin 98-005 dated August 17, 1998.

 

 

 


Background

This Bulletin specifies the current requirements and procedures to be followed for IT acquisitions under the IT moratorium. On November 12, 1996, the Deputy Secretary placed a moratorium on all significant Information Technology (IT) acquisitions. Initially, the USDA Chief Information Officer (OCIO) defined “significant” as those acquisitions over $250,000. On September 19, 1997, the OCIO reduced this threshold to $25,000 to better manage the Department's efforts to fix Year 2000-related computer problems.


Revised Requirements

On March 14, 2000, the OCIO restored the threshold to $250,000 for all significant IT acquisitions. IT items are defined as automated data processing hardware, telecommunications equipment, software, and support services. Components of a significant IT system include, but are not limited to, personal, laptop, and/or hand held computers, ancillary equipment such as printers and software, telecommunications circuits, switches, routers, network servers, hubs, cabling, and telephone systems. Support services include, but are not limited to, systems development contracts and consulting services. This moratorium applies to orders against all existing contracts and General Services Administration schedules.

The following requirements continue as part of the IT acquisition moratorium:

  1. Renewal of existing contracts for maintenance and leases are exempt if the optional enhancements and/or upgrades do not exceed the $250,000.

  2. IT acquisitions for organizations other than USDA agencies are exempt except when funded by USDA grants.



Some special activities require formal waivers:

  1. Telecommunications Network Stabilization and Migration Program requirements must be satisfied before the acquisition of telecommunications equipment. This includes entry of planned telecommunications acquisitions into the Forecast, Inventory and Reporting System.

  2. Software or hardware for major systems within the functional areas of the Department's Corporate Administrative and Financial Systems Portfolio. The purpose is to ensure that agency activities are coordinated with the Secretary's Administrative/Financial Executive Group, while enabling agencies to proceed on priorities that are not part of the corporate portfolio. Specifically, the functional areas include:


New Overall Requirement

Each waiver request must be include an information security plan that identifies system security requirements and the actions that support those requirements.

Application of Policy to REE

Each requisition (AD-700) over $250,000 forwarded to the Contracting Office must have the OCIO's approved waiver attached. Requirements will not be split in order to circumvent the $250,000 threshold, and the spirit of the moratorium will be observed for acquisitions below $250,000.

REE Contracting Officers will not award a contract/order for an IT acquisition costing over $250,000 or if the acquisition does not meet the exceptions previously listed. To support the Office of Management and Budget's requirement of strong enforcement of the moratorium, the OCIO staff will conduct random checks of contract files of USDA agencies.

Obtaining a Waiver

Requests for a waiver from the moratorium must be submitted by the Agency Administrator through the Under Secretary for Research, Education, and Economics to the OCIO. The OCIO will act on waiver requests in writing within 10 working days and expedite waiver requests to meet agency requirements.

The OCIO may request a technical review of waiver by the members of the Information Resources Management Council. For waivers concerning financial and mixed systems, the OCIO consults with the Office of the Chief Financial Officer. For waivers involving administrative systems, the OCIO consults with the Assistant Secretary for Administration.

Specific REE waiver procedures are explained in Exhibit 1. Exhibit 2 is the modified decision memo format for a waiver request.

-/Sd/-

 

KEITH W. ANDERSON
Director
Information Technology Division

Exhibits
1     REE Waiver Procedures
2     IT Moratorium Waiver Request Memorandum
3     REE Information Resource Managers



Exhibit 1



REE WAIVER PROCEDURES

Step Cognizant Office Action
1 Requesting Office Generates the waiver request and cover memo.
2 ARS
- Area Administrative Officers
- Area Directors
- Headquarters - Staff Office
Directors or Deputy
Administrators

NASS - IRM Manager

ERS - IRM Manager

CSREES - IRM Manager

(See Exhibit 3 for listing)

Contact the Director, ITD before submitting the waiver request.

Reviews and forwards request to next appropriate reviewing level with cover memo.

3 ARS - Director, Information Technology Division

NASS - Associate Deputy Administrator for Field Operations

ERS - Director, Information Services Division

CSREES - Assistant to the Administrator

Reviews and forwards request to Agency Administrator.
4 Agency Administrator Reviews and forwards the waiver request to the Under Secretary by signing the waiver request.
5 Under Secretary Reviews and forwards the waiver request to the OCIO.
6 OCIO Approves the waiver request.


PROCESS STEPS

Step 1 The requesting office prepares a waiver in the modified decision memo format provided in Exhibit 2. Use the agency administrator's office letterhead for the waiver request.

Provide a detailed explanation of the mission critical need. Address problems that will result if the waiver is disapproved. Follow the format as closely as possible. Exclusion of information will likely delay approval.

The agency IRM manager will add the current Information Technology Investment Portfolio System (I-TIPS) budget information to the package before forwarding it to the agency administrator. The requesting office should mention the inclusion of the I-TIPS Exhibit in the BUDGET INFORMATION section and list it as an enclosure.

Use a cover memo to transmit the request through the normal management levels to the agency administrator.

Step 2 Using a cover memo, forward the waiver request through the usual management levels or IRM manager. (See Exhibit 3 for listing of REE IRM managers).
Step 3 The agency specified management official will forward the waiver request to the agency administrator.
Step 4 The agency administrator will review, sign, and forward the waiver request through the Under Secretary to the OCIO for approval.
Step 5 The Under Secretary submits the waiver request to the OCIO.
Step 6   The OCIO approves the waiver request and returns it to the agency IRM manager.

NOTE: When submitting the AD-700 to the Contracting Office, attach the approved waiver.

 



Exhibit 2


USE AGENCY ADMINISTRATOR'S OFFICE LETTERHEAD


INFORMATION TECHNOLOGY MORATORIUM WAIVER REQUEST FOR THE CHIEF INFORMATION OFFICER

THROUGH:    I. Miley Gonzalez
                          Under Secretary
                           Research, Education, and Economics

FROM:            Agency Administrator

MISSION CRITICAL JUSTIFICATION:
Identify the unit and location needing the acquisition
Briefly describe the unit's mission
Briefly explain the system applications
Describe the existing hardware, software or information system To: AFM Council/ACS

State the consequence if the acquisition is not approved

DESCRIPTION OF ACQUISITION:
For Hardware or Software requests include:
    Technical description of hardware and software
    List of cost, quantity, type, and manufacturer name and model, if available
    Statement that items will conform to USDA architecture

For Support Services or Services requests, attach:
    List of technical and business requirements
    Statement of Work, if available

Project Schedule
    Indicate start timeframe, major milestones, and completion date

BUDGET INFORMATION:
Dollar amount of acquisition broken out by Fiscal Year and Information Technology category: hardware, software, & support services.

Indicate that the current Information Technology Investment Portfolio System (I-TIPS) budget information is enclosed. (The agency IRM manager will add this information to the package before forwarding it to the agency administrator.)

SECURITY REQUIREMENTS
Include reference to enclosed Information Security Plan.

AGENCY CONTACT:
Name, telephone number, and e-mail address of agency point of contact

DECISION BY THE CHIEF INFORMATION OFFICER:
Approve:        ________________________________

Disapprove:        ________________________________

Discuss with me:    ________________________________

Date:        _________________________________

 


 

Exhibit 3

 

REE IRM MANAGERS

 
ARS Keith Anderson
(301) 504-1047
Mail Stop 5119
USDA-ARS-AFM-ITD
5601 Sunnyside Avenue
Beltsville, MD 20705-5119
kanderson@ars.usda.gov
CSREES Curtis Clark
(202) 720-4241
Water Front, Room 4104
800 9th Street, SW
Washington D.C.

USDA-REE-CSREES-PS- CTDE
SOAGRIBG, Rm 3328
P.O. Box 2216
1400 Independence Ave
Washington D.C. 22050-33213
cclark@reeusda.gov

ERS Michael Ahrens
(202) 694-5070
USDA-REE-ERS-ISD-ITSB
S3129
1800 M Street NW
Washington, DC 20036-5831
mahrens@econ.ag.gov
NASS Phillip Zellers
(202) 720-2984
USDA-REE-NASS-ITD-OD
Room 5847
1400 Independence Ave., SW.
Washington, DC 20250
pzellers@nass.usda.gov