Fish and Wildlife Project Summary

Project 199101900

HUNGRY HORSE FISHERIES MITIGATION


Location: FLATHEAD SUBBASIN basin, including sites listed below.
CRESTON NFH, HUNGRY HORSE DAM, HUNGRY HORSE RESERVOIR.

Summary Description: Coordinates the production program for Kokanee and native trout hatchery production to mitigate losses at Hungry Horse Dam. Focus on kokanee salmon, bull trout, and cutthroat trout.

Background: A fish culture program to mitigate for losses caused by construction and operation of Hungry Horse Dam was needed. Efforts were to be concentrated on kokanee salmon, bull trout and cutthroat trout. Improvements to the Creston NFH were to be identified and funded.

Milestones: Initiated in 1992 after the Draft Hungry Horse Resident fish mitigation plan was adopted by the NPPC. The Implementation Plan was approved in 1993. Mitigates for effects of construction of Hungry Horse Reservoir. This was is an interim program funded annually until negotiation of the Montana Fish Trust was completed. Bull Trout incubation and rearing research underway for two years. Kokanee eggs procured: '92, '93', 94'. Captive kokanee brood produced 3 million eggs in 1994. Kokanee planted in Flathead Lake, '93=200K, '94-800K.. The '95 Kok plant amounted to 502K Five year test started. Mid-way through test. Over 1000 samples for GSI have been collected and analyzed of the Flathead BT genetic profile. Contract 1992AI42887 was completed and closed as of 1997

Results: Lake trout were consuming a large number of planted Kokanee. See M/E rpt.('93-94BY 93 and 408 BY 94. Early (very) results of the cooperative monitoring w/ CSKT indicates that the LKT predation much reduced. Project Ldr. completed a paper titled, " Exper. BT Hatchery Progress Rpt '93-94). Furuc has surfaced in the captive brood.

Publications:
Publication Title Report Type Coverage Years Published Pages DOE/BP Number
Hungry Horse Dam Fisheries Mitigation Kokanee Stocking and Monitoring in Flathead Lake Annual 1995 - 1995 Jun 1996 65903-7
R 115
Kokanee Stocking and Monitoring, Flathead Lake Annual 1993 - 1994 Jul 1995 65903-6
R 099
Hungry Horse Dam Fisheries Mitigation Progress 1992 - 1993 Jun 1994 60559-2
R 093

Project Classification Keys:
Primary: All projects in the Resident Fish Program
Secondary: Focus on producing fish
Tertiary: Implementation of field project work

Work Sites
Site/Subsite Names Site Type Types of Work Performed
CRESTON NFH/Hatchery (acclm ponds, release site, etc)Management / administration
HUNGRY HORSE DAM/Dam (hydro-electric, reclamation, diversion, etc.)Management / administration
HUNGRY HORSE RESERVOIR/Reservoir (incl. lakes, ponds,etc.)Management / administration

Project Budget and Obligation:
Fiscal
Year
Initially
Authorized
Latest
Authorized
Authorized
Change
Obligation
In Process
Bonneville
Overhead
Contracted
Obligation
Contracted
Agent
1992 $300,000 $54,502 $-245,498 $0 $0 $54,502 US FISH AND WILDLIFE SERVICE - DENVER REGION
1993 $76,060 $76,060 $0 $0 $0 $76,060 US FISH AND WILDLIFE SERVICE - DENVER REGION
1994 $600,000 $86,832 $-513,168 $0 $0 $86,832 US FISH AND WILDLIFE SERVICE - DENVER REGION
1995 $84,308 $84,308 $0 $0 $0 $84,308 US FISH AND WILDLIFE SERVICE - DENVER REGION
Totals: $1,060,368 $301,702 $-758,666 $0 $0 $301,702 .