Location: KOOTENAI SUBBASIN basin, including sites listed below.
KOOTENAI BASIN.
Summary Description: Compile loss/gain statement, Libby fisheries mitigation options and site plans, criteria for selecting and prioritizing mitigation projects, for public scoping and submittal to NPPC.
Background: None provided.
Milestones: Contract1997AD63284 for a microscope ($3,912) was completed and closed 1998.
Results: None identified.
Publications:
Project Classification Keys:
Primary: All projects in the Resident Fish Program
Secondary: Research, evaluation, and studies
Tertiary: Mitigation and recovery planning
Work Sites
Site/Subsite Names |
Site Type |
Types of Work Performed |
KOOTENAI BASIN/ | Unknown | Consult, model / plan devel, gather data, edit |
Project Budget and Obligation:
Fiscal Year | Initially Authorized | Latest Authorized | Authorized Change | Obligation In Process | Bonneville Overhead | Contracted Obligation | Contracted Agent |
1997 |
$162,307 |
$41,112 |
$-121,195 |
$0 |
$0 |
$3,912 |
MERIDAN INSTRUMENT CO INC |
1997 |
|
|
|
$0 |
$0 |
$37,200 |
MONTANA DEPARTMENT OF FISH & WILDLIFE - HELENA |
1998 |
$121,195 |
$121,195 |
$0 |
$0 |
$0 |
$121,195 |
MONTANA DEPARTMENT OF FISH & WILDLIFE - HELENA |
Totals: |
$283,502 |
$162,307 |
$-121,195 |
$0 |
$0 |
$162,307 |
. |
|