BAGHDAD, Iraq, June 2, 2004 — Rehabilitation work on turbine 5 has added 110
megawatts of electricity (105 MW derated) to the Iraqi power grid, according
to U.S. Army Corps of Engineers Gulf Region Division officials. The work was
completed May 31, 2004, at the Haditha Dam in Al Haditha, Iraq.
The $12 million project, administered by CH2M Hill, and overseen by Corps
personnel in support of the Program Management Office and Coalition Provisional
Authority, began Feb. 6, 2004.
The turbine operation had been hindered due to three cracked runner blades.
Additional pumps, controls and motors also had to be replaced. Corps and
contractor personnel living on site have been working side-by-side with Iraqi
plant personnel to accomplish this achievement.
Previous projects at Haditha have included the modification of operation
for turbine 2 as well as restoration of transmission lines to link the hydropower
dam to the Iraqi power grid. In all, an additional 460 MW of capacity has
been added to the overall capacity of the national grid due to the efforts
of this partnering team, according to Robert Goss, project manager for the
Restore Iraqi Electricity Directorate for the Corps.
|