Power to the People a United
June 26, 2004
“This is a very important project that will contribute electricity to
The Qudas Project consists of six new generators which will ultimately add 422 MW of new generation to the national Iraqi power grid almost a 10 percent increase to the current level. The first of these six generators, Unit #3, is completing commissioning and punch list processes and should be online within a few weeks. The remaining generators are scheduled to be completed before the end of August. The $145 million Qudas project, executed under a contract with Fluor, and using hundreds of local Iraqi workers, is but one example of more than three dozen new generation, rehabilitated generation, transmission, distribution or switching projects managed by the Restore Iraqi Electricity (RIE) Directorate of the Gulf Region Division, U.S. Army Corps of Engineers. Currently the national capacity is near 4800 MW, it reached an all-time peak this past week by surpassing 4900 MW for the first time in a generation for much of
Dr. Aiham Alsammarae, Minister of Electricity, was also on-hand to unveil the new project and touted the continued effort to improve the electrical capacity of
Since last September, the RIE effort has added more than 1300 MW to the national grid and is on track to add 2000 MW total by the end of summer despite attacks on the infrastructure by terrorist groups in theater. The forces of evil in
“I would like to thank the
Maj. Gen. Ronald Johnson, commander of the Gulf Region Division, was on hand at the ceremony to represent the U.S. Army Corps of Engineers in recognition of the country wide effort. --30-- |