Current Projects of the  CIT/Cable Infrastructure Section This page last update October 14, 2004
Project
Project Lead
Remedy
Number
Telephone Infrastructure
Network Infrastructure
Comments/Remarks
Occupancy/Deadline Dates

Bldg 3
Remodel

B McFadden
J Slemp

ST0489944

TBD

B Coates
F Sebera

Jay Jefferies , Project Officer
100% drawings being reviewed
Planning Stages, meetings are starting
NO FUNDING

TBD
Demo Starting 10-02

Bldg 4

R Massagee

ST0759241
E Zebart

TBD

500 sets to convert to ISDN
Some cabling involved
Cabling 50%complete
4 Phases

10-04

Bldg 6

W McFadden

TBD
TBD

TBD/ NIAID

Refurbishment

 


TBD

Bldg 10
1st flr DRD Area

T Lightner

TBD

M Turner

B Coates


Phase 1 starting
Planning stages no firm dates
Getting Qoute to move 200pr Cables

TBD

Bldg 10
Task 17 Central Core

T Lightner

TBD

TBD

B Coates


Starting 06-04
CC Computer Room to be moved
75% drawings received

On Hold

Bldg 10
Revitalization Project

T Lightner
M Trevino

TBD

TBD

W Hill
R Davis


TBD

2020
On Hold

Bldg 10
Router Room Construction

T Lightner
M Trevino
P Hambright

TBD

R Alexander
A Kitsoulis

W Hill
R Davis
T Noonan


99% Complete
Router room under construction completetion date 06/24/04
Build-out on B1 New Router Closet
Waiting on Power

09-04

Bldg 10
Router Room Relocation

T Lightner
M Trevino
P Hambright

TBD

R Alexander
A Kitsoulis

W Hill
R Davis
T Noonan


99% Complete
Router room under construction completetion date 06/24/04
Build-out on B1 New Router Closet
Waiting on Power

08-04

Bldg 10
CRC

T Lightner
M Trevino
P Hambright

TBD

R Alexander
A Kitsoulis

W Hill
R Davis


Occupancy starting
As-built Deliverables starting to arrive
Finals are being completed
Additions are being addressed

07/31/04 Wiring complete

09-2004 Occupancy

Bldg 12
1st & 2nd flrs
Remodel


M Zimmer

TBD

TBD


M Nguyen

Pathway additions
Working on SOW

TBD

Bldg 13
2nd flr
Remodel


M Campbell

TBD

J Lappin


TBD

Complete waiting on as-builts

08/04

Bldg 30
3rd, 4th flr and basement

R Massagee
B Frye

STO641038

R Alexander

P Dang
B Coates


Phase 5 in progress
Waiting on DELPRO
To be completed FY06

Bldg 31
7th floor

W McFadden
J Slemp

ST0749089
J Lappin

TBD/ NIAID

Waiting on as-builts and test results

 


Phase 3 TBD

Bldg 31
B & C Wings

W McFadden
J Slemp

ST0711232
R Jones

M Kerrogin

Construction in Progress
1C14 90% complete
Recieved Drawings

 

10-04

Bldg 33 Complex


T Trang
N Pasquini

TBD

E Zebart
B Dougherty

R Davis
W Hill

Kyung Kim, PO
150,000 GSF
Tony is meeting with PO on responsiblities
Need Network connectivity costs and qoutes

New Walking tunnel under design
Bldg 31 to be reinforced with 1800 pr cable
Received 100% electronic drawings
OSP pathway yet to be completed
Adding Nick to email list
Orders written this week for Garage cabling
Estimates are turned in for Bldg
SOW complete forInside Plant
Waiting on customer response to Outlet Counts

07-2004 Parking Garage

2005 Bldg 33


Bldg 33, 31 & 6
Reinforcement


B Frye
M trevino

TBD

TBD

TBD


Reviewed Tunnel drawings
01-05

Bldg 35
Porter Neuroscience Research Center
Phase 1

T Trang
B Frye
H Marr
M Campbell

TBD
Ronda Jones

M Nguyen
R Davis
A Trang
P Koontz



John Hollingsworth, PO
Doing MAC Work
Waiting on as-builts
Completing Final Inspection and Closeout

Bldg fully occupied 9-2004

Bldg 35
Porter Neuroscience Research Center
Phase 2

T Trang
B Frye
TBD
TBD

M Nguyen
T Nguyen

Conceptual Drawings reviewed

TBD

Bldg 37
1st flr

N Pasquini

TBD

I Robinson

Gregar, NCI

Design review in Progress
Demo started

TBD

Bldg 49
2, 3rd & 5th

N Pasquini

TBD

J Lappin

TBD

NINDS
NIMH

09-04

Bldg 49
5th & 6th flrs

M Campbell

TBD

J Lappin

TBD

NIDDK
Closet Equipment Installed
90% complete
Waiting on Construction

08-04

Off Campus Projects
Go to Top

Project
Project Lead
Remedy
Number
Telephone Infrastructure
Network Infrastructure
Comments/Remarks
Occupancy/Deadline Dates

6001 Executive
2nd & 3rd flrs

R Massagee

TBD
J Lappin
Ted Nguyen

Tracey Harris PO
100 WAO
100 drawings received
Out for bid

TBD

6001 Executive
5th flrs

R Massagee

TBD
D Custis
Ted Nguyen

Demo started
NINDS


Phase2 5th 10-04

6001 Executive
5th flrs

R Massagee

TBD
J Lappin
Ted Nguyen

NIDA
Demo started


Phase2 5th 10-04

6011 Executive
2nd flr

R Massagee

TBD
TBD
Ted Nguyen

Waiting on as-builts

Phase 1 complete
09-04 Phase 3

6116 Executive
1st flrs

R Massagee

ST0714556
D Custis
Ted Nguyen

Computer room renovation
DELPRO Received
B&F signed

John Morris , PO

12-04

5516 Nicholson LN

B Mcfadden
J Slemp

TBD
TBD
M Mason

Tracy Harris, PO
50 tenants
Design Phase
Waiting on drawings

12-04

6707 Democracy
3rd flr

H Ma rr

TBD
D Custis
M Medina

Orders written
Conduit installation due Oct 1

09-04

6130 Executive
3rd Floor

R Massagee

ST0714556
TBD
T Nguyen

NCI
kick off meeting 08-20-04

TBD

Rockledge
6610

N Pasquini

TBD
TBD
M Medina

Move existing Cable Tray
Estimate delivered
waiting on approval

09-04

Rockledge 1
6705 1st flr

H Marr

TBD
I Robinson
M Medina

Refurb
ODOER tenant
POC B Neilsen
Cabling 90% complete
Furniture being installed

09-04

Rockledge 1
6705 2nd flr

H Marr

TBD
I Robinson
M Medina

Complete floor
ODOER tenant
POC B Neilsen
Waiting on construction
Orders written

Phase 1 09-04
Phase 2 10-04

Rockledge 1
6705 6th flr

H Marr

TBD
I Robinson
M Medina

OD Tenant
POC B Neilsen
90% complete
Waiting on Phase 2 furniture installation


Phase 1 complete
Phase 2 09-04

Rockledge 1
6705 6th flr

H Marr

TBD
D Custis
M Medina

NHLBI Tenant
Cabling in Progress
Received Phase 2 as-builts

Phase 3 09-04

Rockledge 2
6701 9th flr

H Ma rr

TBD
TBD
M Medina

NHLBI
On Hold

On Hold

Rockledge 2
6701 6th flr

H Ma rr

TBD
I Robinson
M Medina

15K sq ft renovation

10-04

#5 Reasearch CT

H Ma rr

TBD
TBD
TBD

Completed intial meetings

TBD

Rockledge 2
6701 3rd flr

H Ma rr

TBD
TBD
M Medina

CSR Tenant

TBD

Bldg 102
Poolesville

B Mcfadden
J Slemp

TBD
C Moxley
T DeFeo

Drawings at 30%
Meeting on 03-04 for Drawing review
Maintenance Hole construction problems

12-05

Poolesville
Fire Alarm System

B Mcfadden
J Slemp

TBD
TBD
TBD

Pricing approved by ORF
Working SOW & quote
Forwarded to DOI
PO issued
Started conduit work

12-04

Additional ductbanks
Poolesville

B Mcfadden
J Slemp

TBD
TBD
TBD

Construction to start 07-19-04
50% Complete
All conduits are to tested
Pads & trenching started

12-06

Aerial to Buried
Poolesville

B McFadden
J Slemp

TBD
R Bohr

T DeFeo
M Mason


50% cabled

Restart JUly 19th
On Hold for Construction
Sent cost for conduit testing

12-06


Pending and Misc.


Go to Top
Project
Project Lead
Remedy
Number
Telephone Infrastructure
Network Infrastructure
Comments/Remarks
Occupancy/Deadline Dates
Archibus Project

M Zimmer
B Frye

N/A

TBD

TBD

e
Working on CRC as-builts

TBD
Campus Cable Air

M Trevino

N/A
TBD
TBD

Cable air pressure problems
Writing SOW
Paul Hill reviewing SOW
Requesting qoutes

TBD
Comcast

N Pasquini
R Massagee

N/A
TBD
TBD


Working on CRC
Building 30 estimated completed10/16/04
Quotes received for remaining buildings

On-going
Super Corridor
CATV Trunk Replacement

N Pasquini
R Massagee

N/A
TBD
Ted Nguyen

Estimate received from Comcast
Tony Lightner will deliver quote

12-04
CATV Fisher's Pl

N Pasquini
R Massagee

N/A
TBD
Ted Nguyen

Dave Orchard contact
Survey Complete
Waiting for funds from customers
Problems with Building Management

TBD

Cedar Lane Ductbank

M Trevino
B Frye
J Slemp
N Pasquini

TBD
TBD
M Medina

Fibergate to move cable
Waiting for Starpower and Dark Fiber to be moved.
Evaluating Ductbank impact from fence installation
Drawings delivered to WFT
Dependant on new router room

TBD
Dark Fiber

M Zimmer
B McFadden

TBD
TBD


M Everet
T Nguyen

On-going installations as required
Working on Router Room move
Bldg 45 complete
Pending outage for aerial to buried move
Complete 5635 Fishers
5600 to 45 purchase request being processed
12501 Washington Ave to 5635 being processed

On-going as buildings are taken by NIH
Family Lodge

B Frye
M Trevino

ST1150080
R Clark
TBD


cabling due to start 08-04
Scheduling is being definedJob delayed by construction schedule

09-04 Admin Staff
01-05 Residents
NIH COOP

B Frye

TBD
TBD
TBD


Cabling of the new NIH COOP

TBD
HHS COOP

B Frye
M Trevino

TBD
B Dougherty
M Nguyen

Phase 2 nearly complete

Phase 1 complete

GDS Warehouse Industrial Dr

B McFadden
H Marr

TBD

TBD

B Neilsen

New LAN Drops
Sent BAF request
Waiting on Cabling
Conduit work started

11-04

Blue Lights, Loading Docks
and
Courtesy phones

B Frye

TBD
K Waters
B Dougherty
Ted Nguyen - Fishers

MLP 9, MLP10 and Fishers Parking Garage being reviewed for Cameras and Phones
Blood Bank Parking Garage reviewed

on-going as needed
NIH Fence Project

M Trevino
B Frye

TBD
TBD
W Hill

Intial Scope of Work complete addressing modifications
4 mods to base Scope
New Pods added


Phase 2 in Progress
NLM Addition

B Frye
M Trevino

TBD
G Duling
W Hill

Planning Stages
100% drawings are being reviewed, New drawings consist of Parking structure, Tunnel and Bldg
100% drawing comments have been sent
Athanasia Mantzouranis, PO
Reworking estimate to include addtions and utility work

TBD

Off Campus Day care Evaluation

H Marr

TBD
TBD
TBD

TBD

TBD

OSP Updates

M Trevino
B Frye

TBD
TBD
TBD

OSP Updates tenative and completed work discussed
PNRC reinforcement to start

on-going

Outlet Documentation
6701 Rockledge

H Marr

TBD
TBD
M Medina

CSR/SLA
Close out beginning

10-04

SOP drafting

B Frye

TBD
B Harding
S Fosburg
R Davis

SOPs are being developed foe OSP and Insde Plant Outages

10-04

South Campus
Backbone

M Trevino
B Frye

TBD
TBD
R Davis

Need submitted qoutes and SOW to Paul Hill

TBD

AC Installations for LightSpans
6610, 6701 7 6705 Rockledge

H Marr

TBD
TBD
M Medina

Have provided R Farrar necessary paperwork

TBD
Adtran Installations

B McFadden H Marr
Y Brooks

N/A

TBD

T DeFeo

Installations due to begin
Poolesville order issued for install

Problems are starting due to Power requirements
GDC Warehouse pending
Providing cost estimate
PO's signed for Paperwork @ Poolesville

 

11-05


Fishers Place

B Frye

5625
ST0784681

5635
ST0784695

J Clendenning
Ted Nguyen

Marlene Jefferson( 5635 4th flr), Dave Gordon(5625), Bryan Shroye(12735)r Shelley Wiedel(5635)& Dusty Rhodes, PO
Cluster will be fed utilizing copper, feeds are installed in 12735, 5635. 5625 complete


12735
complete

5635
Waiting on qoute Conference Center
Main Closet construction completed
beginning customer adds
Bldg is occupied



5625
Risers complete
1st floor Director's reserve due to start
Wireless to begin10-04
Extras 95% complete

Having problems with Bldg Management on Maintenance Hole access
NHGRI has moved to 5th floor

 

12735 LG: 120
occupied
08/2004 5625 LG: 122
5635 LG: 124
Building occupied
as of 01-15-04

Local OSP Tie cabling to start 09-04

Visitor Center
Gateway Bldg.

B Frye

TBD
TBD
TBD

95% Drawings have been reviewed
Copper and Fiber installed to Temporary Bldg

TBD
Web Page Update

B Frye

TBD
TBD
TBD

Combined CIT effort to redo all CIT webpages has started

TBD

9800 Medical Center Dr

B Mcfadden

TBD
B Dougherty
T Trang

NHGRI
Construction to start 07-19-04
50% Complete
All conduits are to tested
Meeting scheduled for 10-7-04

10-04
Wireless Data Project

M Campbell
R Massagee
H Marr

TBD

N/A

M Medina
T Defeo


6001,
6707 & Democracy 2 locations complete

WAITING SURVEY
Fisher's 5625 starting
Rockledge 1 Pending
Navy Med
Bldg 50

 

on-going

Go to Top

Up one step

Application Development & Support | Corporate Computer Services | Desktop Computer Services
IT Acquisition | Management & Policy | Networking & Telecommunications
Research & Scientific Support | Security | World Wide Web

Home | Search | Index | Disclaimers | Privacy | Accessibility

Email comments or questions to NIH Help Desk or or Visit NIH Support at:http://support.cit.nih.gov/

Center for Information Technology
National Institutes of Health
Bethesda, Maryland 20892

For questions concerning this site and it's associated pages please contact the CIS Webmaster.