United States Department of Agriculture
Research, Education, and Economics

ARS * CSREES * ERS * NASS
Policies and Procedures

 

 

Title: Approval of Ratification Actions within REE
Number: 212.16
Date: July 17, 1997
Originating Office: Procurement and Property Division
This Replaces: Bulletin 960503
Distribution: ARS Area Administrative Officers, ARS Procurement Assistance Officers, PPD, FD, CSREES, ERS, and NASS

 

This P&P provides guidance on processing ratifications of unauthorized commitments within REE.

Change dated 2/16/99:

Removed title of Facilities Div Director when pertaining to delegated procurement authority.

Change dated 12/10/01:

Include title of Chief, Facilities Contract Branch, Facilities Division when pertaining to delegated procurement authority.



1. Delegation of Authority
2. Regulatory Requirements
3. Procedures for Ratification Actions Approved at the Contracting Office Level
4. Report Requirement for Ratification Actions Approved at the Contracting Office Level
5. Review of Ratification Actions Approved at the Contracting Office Level
6. Ratification Actions Requiring HCAD Approval
7. Summary of Responsibilities


1.    Delegation of Authority

The Agriculture Acquisition Regulation (AGAR) 401.602-3 authorizes the Head of the Contracting Activity (HCA) and HCA Designee (HCAD) for REE to delegate ratification authority to qualified individuals at the Chief of the Contracting Office level. Accordingly, the following individuals are hereby delegated the authority to ratify unauthorized actions up to $100,000:


Authority to approve unauthorized contract actions over $100,000 remains at the HCAD level.

2.    Regulatory Requirements

All ratification actions are to be processed in accordance with Federal Acquisition Regulation (FAR) 1.602-3 and AGAR 401.602-3. The authority to ratify an unauthorized commitment may only be exercised when the conditions cited in FAR 1.602-3(c) exist. Procedures cited in AGAR 401.602-3 shall be followed upon learning of an unauthorized commitment. The subject of unauthorized contract awards/ratification actions is included in the Basic and Advanced Field Acquisition Seminars, and the topic is covered in the ARS Field Acquisition Manual 213.2.

3.    Procedures for Ratification Actions Approved at the Contracting Office Level

    
The enclosed form, “Ratifying Official's Determination to Ratify Unauthorized Commitment,” should be completed by the individual in the Contracting Office who is recommending the ratification and signed by the ratifying official for each ratification action processed. This form constitutes the ratification action required by FAR 1.602-3 and does not serve as a substitute for the information AGAR 401.602-3 (c)(3) requires to be submitted by the individual who made the unauthorized commitment. Enclosed are samples of letters which should be forwarded upon approval of the ratification action. It is not necessary that the ratifying official sign the purchase order/contract for the ratification; however, the statement, “This is a ratification of an unauthorized commitment,” should be typed on the face of the AD-838/SF-26 which ratifies theaction. Once the action has been ratified at the appropriate level, any contracting officer with delegated authority for the dollar amount of the action can sign the AD-838/SF-26.

If ratification action is not justifiable, the ratifying official must provide the person who made the unauthorized commitment, the recommending official, and the unauthorized contractor with an explanation of the decision not to ratify. Cases that are not ratifiable under FAR 1.602-3 may be subject to resolution as recommended by the General Accounting Office under its claim procedures, or as authorized by FAR Part 50 as “extraordinary contractual actions.” If the ratifying official for actions under $100,000 or the recommending official for actions over $100,000 has any questions concerning a non-ratifiable action, the HCAD should be contacted.

4.    Report Requirement for Ratification Actions Approved at the Contracting Office Level


An annual report listing all ratifications processed for each ARS Area Office/PPD Branch/FD shall be submitted to the Policy Branch, PPD, by November 1 for the previous fiscal year. This report shall include the item description, the name and location of the person who committed the unauthorized commitment, and the dollar amount.

5.    Review of Ratification Actions Approved at the Contracting Office Level


Ratification actions approved at the contracting office levels will be closely reviewed for compliance with FAR and AGAR requirements during Procurement Management Reviews performed by the Policy Branch, PPD, and the Department.

6.    Ratification Actions Requiring HCAD Approval


Review and approval of previously unauthorized contract actions over $100,000 shall remain at the HCAD level. Such actions must be forwarded to the Director, PPD, for approval and must include evidence of compliance with FAR and AGAR, as cited above. The completed form, “Ratifying Official's Determination to Ratify Unauthorized Commitment,” signed by the appropriate individual at the Chief of the Contracting Office level, as recommending official, must be forwarded to the HCAD for signature, along with the forwarded action.

7.    Summary of Responsibilities


HCAD (Director, PPD)


Branch Chief/PAO


Contract Specialist/Purchasing Agent


Person Who Made the Unauthorized Commitment

JANE L. GILES
Deputy Administrator
Administrative and Financial Management

3 Enclosures

 


 

Enclosure  1


Ratifying Official's Determination to Ratify Unauthorized Commitment

Part 1 - Background Information:

1. Unauthorized Commitment by (name):_________________

2. Location: _______________________________________

3. Supply/Service: __________________________________

_________________________________________________

4. AD-700:    _______  $________  ________________
                        Date          Amount        Accounting Code

5. Contracting Office: ________________________________

6. PO/Contract Amount: $ _____________________________

7. Vendor: _________________________________________

8. Competition Received: _____________________________

9. Performance/Delivery Date: _________________________



Part II - Determination in Accordance with Information Required by
FAR 1.602-3:

1.    Supplies or services have been provided
       to and accepted by the Government, or the
       Government otherwise has obtained or will
       obtain a benefit resulting from performance
       of the unauthorized commitment.               ___ /____
                                                                         Yes     No

2.    Resulting contract would otherwise have
       been proper.                                              ___/____
                                                                         Yes     No

     - If sole source, provide a justification.
    _____________________________________________  

    _____________________________________________

    - If over $100,000 cite FAR Part 6 exemption.
    _____________________________________________    

    _____________________________________________

3.   Price Reasonableness Determination.

     ____________________________________________

     ____________________________________________

    

4.     Payment is recommended.                   ___  /____
                                                                    Yes     No

5.     Funds are available and were available
       at the time the unauthorized commitment
       was made.                                             ___ /___
                                                                     Yes    No

6.   The ratification is in accordance with all
      limitations described under agency procedures.   ___ /___
                                                                                    Yes   No

Based on the information contained herein, ratification of this unauthorized commitment is recommended.

____________________________________              _______  
Recommending Individual in the Procurement Office      Date

Based on the information contained herein, this unauthorized commitment is hereby ratified.

_________________________________                      _____
(PAO/PPD/FD Branch Chief,                                        Date
(HCAD if over $100,000)



 Enclosure 2

SUBJECT:     Ratification of Unauthorized
                       Contract Award

TO:               Person who Committed the
                      Unauthorized Contract Action
        
FROM:        Chief of the Contracting Office
        

I have reviewed the information submitted by _______and have ratified your unauthorized act of purchasing supplies/services to___________ . This ratification is based on the fact that the contractor provided the supplies/services in good faith, and the Government received a benefit.

Your unauthorized act is a violation of the following regulations:

While I have ratified this act (enclosed), you are advised that future procurement and/or contractual actions in which you become involved must be submitted to the procurement office for execution. It is recommended that you review prohibited conduct as covered in the Employee Handbook, Appendix 1 (7 CFR 0.735-11(a)(5), FAR 1.602-3, and
AGAR 401.602-3).

Because of Government publicity on alleged fraud, abuse, and waste of Federal funds, this memorandum is provided to protect your interests and to caution you on future involvement with unauthorized procurement and/or contractual actions.

Enclosures

cc:
Cognizant REE Program Supervisor


Enclosure  3

 

SUBJECT:    Ratification of Unauthorized Act

TO:              _________________________
                    Purchasing Agent, Area/Location
    
FROM:        Chief of the Contracting Office

Enclosed is the signed determination ratifying the unauthorized act committed by
_________________ for the purchase of ________________.

Enclosures