United States Department of Agriculture
Research, Education, and Economics

ARS * CSREES * ERS * NASS
Policies and Procedures

 

 

Title: Economic Analysis and Decision for ARS Facility Modernization
Number: 242.5-ARS
Date: July 9, 1998
Originating Office: Facilities Division, Facilities Engineering Branch, AFM/ARS
This Replaces: ARS 242.5 dated 5/26/92
Distribution: ARS Headquarters, Areas, Locations

 

 

 

This P&P requires performance of analysis to determine the best method of implementing facility modernization. It establishes the Administrator as the decision authority who decides the method of modernization when Gutting and Rebuilding cost is more than 3/4 of New Replacement Facility cost.



Table Of Contents

1. Introduction
2. Policy
3. Alternative Methods of Modernization
     Selective Renovation
     Gutting and Rebuilding
     New Replacement Facility
4. Determining Best Modernization Approach
     General Assumptions and Conditions
     Analysis and Decision Process
5. Summary of Responsibilities
     Administrator
     Area Directors
     National Program Staff
     Area Administrative Offices and Facilities Division


 

1.    Introduction

The ARS research facilities are aging and in need of major repair and improvements to effectively support current agency mission activities. Functional, safety and health, and code-related deficiencies are prevalent. Building components (especially mechanical and electrical systems) are rapidly deteriorating due to normal wear and tear and lack of an aggressive preventive or repair and maintenance program.

To correct these condition deficiencies, ARS implemented an Agencywide facility modernization program involving major facility upgrade (i.e., million dollar packages) at high priority research locations selected by the Administrator and the National Program Staff. These modernization sites are selected and prioritized based on criteria which include high priority programs; safety and health of employees; critical mass of scientists; and established centers of excellence for high priority research programs.

In the FY-90 Senate Appropriation Committee Report, the committee acknowledged the important facility modernization efforts being undertaken by ARS but expects those efforts to be supported by economic analyses and that consideration will be given to complete internal rebuilding of existing facilities (Gutting and Rebuilding) and to demolishing or abandoning of existing structures and building new facilities (New Replacement Facility)--whichever is most feasible.

 

2.    Policy

In implementing modernization of ARS facilities, whenever the total modernization cost is over $1 million, an analysis of alternative methods of modernization shall be performed to determine the best method of correcting building deficiencies. Considering economic and other factors, the analysis shall compare the feasibilities of Selective Renovation, Gutting and Rebuilding, and New Replacement Facility.

This analysis shall be accomplished in conjunction with the planning process for major facilities construction projects outlined in Phase I/Step 1 of the ARS Manual 242.4, Major Facilities Construction.

This policy does not apply to projects involving historic property for which construction activities must comply with national historic preservation laws and regulations.

 

3.    Alternative Methods of Modernization

Selective Renovation

This traditional method of correcting building deficiencies is through the implementation of individual repair and alteration projects. The work may include gutting and rebuilding of the interior spaces of the building on a small-scale basis (i.e., designated laboratories or sections of the building).

Gutting and Rebuilding

This method of modernization is accomplished through complete gutting of the interior space of the existing structure and replacing all interior components (walls, ceilings, etc.), utilities, systems, fixed equipment, and laboratory furniture with new state-of-the-art components. The term gutting refers to a demolition approach back to the structural framework of the building. This modernization approach requires relocation of tenant research operation, personnel, and equipment to a temporary facility.

New Replacement Facility

This method of modernization is accomplished through demolishing or abandoning existing structures and building a replacement facility (at existing or other site). This modernization approach may be considered if the repair and renovation of existing facilities would be impractical. This approach must be supported by the Administrator. Construction of a new replacement facility at an existing building site will require relocation of the tenant research operation, personnel, and equipment to a temporary facility.

 

4.    Determining Best Modernization Approach

General Assumptions and Conditions

To ensure that data and cost estimates for Gutting and Rebuilding and New Replacement Facility are developed and evaluated on the same basis, the following assumptions and conditions must be made.

Analysis and Decision Process

Step 1 - Identify/Evaluate Existing Building Deficiencies

Through performance of a facility condition study performed by an Architect-Engineer (A-E) firm, develop an inventory of existing functional, safety and health, and code-related building deficiencies. Interview pertinent agency/tenant research program personnel to determine their programmatic needs to support current research function as well as any facility enhancements to improve the function. Interview the building manager and building maintenance staff to determine their O&M needs/problems. Identify and evaluate condition deficiencies in terms of:

Step 2 - Determine Building Deficiencies Cost

Estimate the total cost of design and construction to repair/correct all existing building deficiencies. If the total cost is less than $1 million, it shall be deemed practical to correct building deficiencies through Selective Renovation. Otherwise, proceed to Step 3.

Step 3 - Determine Gutting and Rebuilding Cost

Estimate the cost of gutting and rebuilding the existing facility. In addition to design and construction cost, include the cost of temporary facility for tenant research operation that would be displaced by the modernization effort. Include moving cost, lease space, and installation of temporary utilities, etc.

Step 4 - Determine New Replacement Facility Cost

Estimate the cost of building a replacement facility at the existing or new building site. In addition to design and construction cost, include appropriate cost of land (if acquisition of new land is required), geotechnical surveys, additional site work and new site utilities, demolition of old building structure, moving cost, lease space, and installation of temporary utilities, etc.

Step 5 - Compare Costs and Determine Preferred Method of Modernization

Compare building deficiencies cost against gutting and rebuilding cost. Compare gutting and rebuilding cost against new replacement facility cost. Determine preferred method of modernization in accordance with the conditions below:

IF

AND

THEN

Building deficiencies cost is LESS THAN 1/2 of gutting and rebuilding cost Gutting and rebuilding cost is LESS THAN 3/4 of new replacement facility cost The preferred modernization method is Selective Renovation.
Building deficiencies cost is
MORE THAN 1/2 of gutting and rebuilding cost
Gutting and rebuilding cost is
LESS THAN 3/4 of new replacement facility cost
Consider Selective Renovation or Gutting and Rebuilding, whichever is most feasible. (Go to Step 6)
Gutting and rebuilding cost is
MORE THAN 3/4 of new replacement facility cost
Consider Gutting and Rebuilding or New Replacement Facility, whichever is most feasible and supported by the Administrator. (Go to Step 6.)

Step 6 - Analyze Tradeoff Between Alternatives

Identify constraints and other relevant factors which will cause certain alternatives to be infeasible (such as technical, physical, functional, budgetary, and building code requirements). Some of the most important factors to consider are:

Step 7 - Recommendation and Administrator Approval

Obtain necessary approval and direction from the Administrator whether to pursue gutting and rebuilding of the existing facility or to build new replacement facility. Develop recommendation/rationale supporting the preferred method of modernization. Communicate analysis result to the Administrator through the Area Directors (AD) and National Program Staff (NPS).

 

5.    Summary of Responsibilities

Administrator

Area Directors

National Program Staff

Area Administrative Offices and Facilities Division Assist in development of preliminary modernization project data, design alternatives, site selection, budget estimate, schedule, and other modernization issues. Review scope of contract services for facility condition surveys and studies.

Review data, communicate the analysis results, and recommend the course of action to the Administrator through the Area Directors and National Program Staff.

 

 

/s/

W. G. HORNER
Deputy Administrator
Administrative and Financial Management