Efficient and Effective Testing of
Multiple COTS-Intensive Systems Dr. Richard Bechtold, Abridge Technology
Testing any complex system is a challenge, but testing multiple commercial off-the-shelf
(COTS)-intensive systems is especially challenging due to a variety of factors. These factors
include (1) systems combining highly diverse technology levels, (2) organizational users spanning
numerous skill levels, (3) incorporating wide varieties of COTS vendors and packages,
and (4) updated systems arriving for testing from projects that already may be substantially
behind schedule and over budget. Regardless of these challenges, it is still essential
to conduct efficient and effective testing in the context of limited time and nominal budgets.
This article explains how to analyze, prioritize, plan, and manage the testing of COTSintensive
systems. Priorities are discussed from the perspective of identifying general types of
transaction dialogues and specific instances of key dialogues. Dialogue value escalation is
explained. Test planning and management are then discussed with the goal of maximizing
the delivered benefit to organizational end-users.
Many organizations depend critically
upon the maintenance and evolution
of multiple in-house commercial off-theshelf
(COTS)-intensive systems. Most
COTS systems are not matched perfectly
to these organizations' specific needs and
hence companies are often adjusting parameters,
creating scripts, developing
macros, writing code, or otherwise changing
or extending functionality. Additionally,
COTS vendors are always developing
new packages, adding additional capability,
and releasing updated versions of their
products. Then, of course, there are the
usual service packs, security patches, and
other bug fixes that vendors want companies
to install. And do not forget ongoing
hardware and network upgrades. All this
translates into a significant challenge for
those responsible for performing testing
to ensure adequate quality within this
complex infrastructure.
For most organizations, testing everything
is simply not an option. Hence,
somehow testing must be biased in a manner
that results in the maximum reduction
of organizational risk, and that helps
ensure the delivery of maximum benefit
to system end-users. Amazingly, approximately
half of all software modules in a
system are defect-free and do not require
any testing at all. Further, 80 percent of
the defects come from 20 percent of the
modules, and 90 percent of system downtime
comes from at most 10 percent of
the defects [1].
The potential exists to substantially
improve upon system uptime and overall
end-user benefit by finding, for example,
just five percent more defects than are
currently found. Ironically, end-user benefit
can even be improved by finding fewer
defects. This might occur if the testing
approach is adjusted to focus on finding
defects that cause the greatest system
downtime. For example, the user experience
will likely be substantially better if
one defect is found that would crash the
system daily versus finding three defects
that would each crash the system annually.
Given the preceding data, a significant
majority of testing efforts should be
focused on 10 percent to 20 percent of
any particular COTS system. The question
is, how do we find that 20 percent? And
since some in-house systems are clearly
more critical than others, how do we
account for that?
This article briefly identifies these and
similar major challenges associated with
performing efficient and effective testing
of multiple in-house COTS-intensive systems.
Then a nine-step process is
explained that can help improve the
approach to performing testing. The steps
are as follows:
- Identify Transaction Dialogues.
- Analyze User Impact.
- Determine Historical Defect Prevalence.
- Prioritize Dialogues.
- Prioritize Test Types.
- Build Test-Dialogue Matrix.
- Analyze Test Resources.
- Establish a Test Plan.
- Conduct Test Management.
Although the above sequence of
actions may, at first, seem a bit daunting,
several of the steps become substantially
simpler after the first planning iteration.
For example, once you have prioritized the
types of tests to perform, you can typically
reuse the same prioritization during
future planning iterations. Additionally,
this method is self-correcting. In earlier
planning iterations, it is likely that you will
have to rely upon a lot of guesswork to
perform some of the steps. However, as
you collect data during subsequent testing
cycles, you can start using that data to
replace, or at least augment, estimates.
Note that the overall testing approach
described in this article can also be applied
to the testing of virtually any complex system,
or for performing testing in environments
where test resources are very scarce
or test urgency is very high. However to
simplify this discussion, the remainder of
this article specifically focuses on discussion
and examples relevant to testing multiple
COTS-intensive systems.
COTS Testing Challenges
Testing of any complex software system
can be challenging, and testing of COTS
systems even more so because they require
testing someone else's software (and hardware)
and also testing your implementation
and/or extension of that system. Deploy a
few dozen COTS-intensive systems into
the organization, and you have created a
full-scale testing nightmare.
When performing testing in this type
of environment, typically you need to
consider and address most or all of the
following issues:
- Different COTS systems may be
based upon significantly different
technologies.
- System end users usually have substantially
different skill and experience
levels.
- Your organization may depend upon a
wide variety of COTS vendors.
- The threat levels presented by various
COTS systems relative to core mission
or business processes can differ by
orders of magnitude.
- System test work requests are not
evenly distributed over time, and multiple
parallel systems under test may
rapidly overwhelm available test
resources.
- Systems often become available for
testing substantially later than originally
planned.
- For some system failures, finding the
actual source of the failure - or even
re-creating the failure - can be quite
complex and time-consuming, especially
when the COTS system involves
products from multiple vendors.
- The end-user organization may be
reluctant to provide, or is incapable of
providing (due to security reasons),
actual production data for use in testing.
- Funds or resources originally allocated
for system testing are often used to
cover cost overruns during earlier project
phases.
- System release or go live dates are often
unmovable, or at least quite painful to
move.
- Test organization resources are often
redirected to perform unplanned
emergency testing of systems to investigate
problems reported by end users
working with production systems.
- Calculating return on investment for software
testing can be extremely difficult,
or impossible [2, 3].
In summary, efficient and effective
testing of multiple in-house systems
requires a thorough understanding of the
role those systems play and the value they
provide - and the threat they present to
the organization. It also requires a highly
flexible plan to accommodate potentially
significant organizational dynamics. The
following nine-step process addresses
these issues and is based upon these fundamental
principles: (1) collect intelligence,
(2) prioritize objectives, (3) understand
resources, and (4) go for maximum
impact.
1. Identify Transaction Dialogues
The COTS system value and impact analysis
commences with identifying and documenting
transaction dialogues. A transaction
dialogue is a closely related set of
actions - ideally mapped to one or more
system requirements - that are normally
performed at the same time, and that typically
conclude at the same place they
commenced. For example, adding new
employees to the employee database can
be viewed as a dialogue. It likely starts and
ends on the same menu screen, and the
data entry actions for adding employee
information are closely related.
Another example of a dialogue is
updating electronic timesheets with the
activities performed and hours worked
during a given day. Further examples
include entering sales orders into an
accounts receivable system, entering paycheck
information into a payroll system,
or paying invoices within an accounts
payable system. When creating transaction
dialogues, remember that the ultimate
objective is to structure or design them so
that they directly facilitate testing. (Note:
If you already have a set of use-case scenarios
[4], you can use those in lieu of creating
transaction dialogues. In the absence
of use-case scenarios, defining dialogues
will likely be faster and easier than defining
scenarios).
Figure 1: Identifying and Diagramming Transaction Dialogues
(Click on image above to show full-size version in pop-up window.)
Dialogues can be easily diagrammed as
a directed graph consisting of a set of
nodes and arcs where the nodes represent
specific (and possibly complex) activities
or steps, each with a descriptive label and
possibly a brief description. The arcs,
each of which connects two nodes, indicate
the sequence in which these activities
can occur. As shown in Figure 1, multiple
arcs departing from a node indicate that
any of the destination actions might occur
next. Similarly, multiple arcs arriving at a
node indicate any of the source activities
may have occurred previously. Note that
there are no semantic differences between
two arcs departing (as in Step 2) or in one
arc departing and splitting (as in Step 6).
Likewise there is no difference between
multiple arcs arriving (as in Steps 4B and
5B) or multiple arcs joining and then
arriving as one (as in Steps 6 and 8).
In order to ensure clarity and reduce
misunderstanding, it is important to keep
these drawings, and their associated
semantics or rules, simple (i.e., these diagrams
do not require the formality or
detail of state transition diagrams). The
objective of developing these diagrams is
just to clearly indicate the boundary of the
closely related set of system and user
actions or steps that are covered by the
dialogue.
It may be infeasible or unnecessary to
try to capture all the various dialogues
within a system. Hence, develop dialogues
in a somewhat prioritized order. That is,
what are the most important things a
given system does? Capture that at a high
level. Then, resources permitting, decompose
complex nodes on higher-level dialogues
into their own dialogues. If you are
preparing to perform parallel testing of
multiple COTS systems, then continue
with this strategy by documenting the
most important dialogues in the most
important COTS systems, etc.
Again, resources and time permitting,
steadily extend both coverage and formality
by adding dialogues related to lessimportant
systems and less-important system
interactions, and by adding additional
information to previously developed higher-
priority dialogues. For the most important
dialogues, consider augmenting them
with comprehensive use-case scenarios.
When identifying dialogues within any
given system, the ultimate objective is to
gain a better understanding of where,
how, and why users interact with that system.
This sets the foundation for analyzing
user impact.
2.Analyze User Impact
As you build a collection of transaction
dialogues, you can begin to identify specific
user groups within the end-user organization.
Note that the groups you identify
may not align with actual job titles held by
the end-users. This is common and
acceptable because your primary objective
in this step is to improve your understanding
of how closely related sets of
people - regardless of their titles - interact
with the various systems during dayto-
day usage.
Depending upon the complexity of
the end-user organization(s), you may also
find it convenient to define a set of usergroup
types. Type distinction might be
quite simple such as distinguishing
between beginning, intermediate, and advanced
users. For each identified user-group (or
group-type combination), assign a code to
indicate that group's estimated contribution
to core mission or business performance.
For example, use A to indicate a
group that is critical to core performance,
B to indicate a group that is important,
and C to indicate a nonessential support
group.
Next, develop estimates of the number
of users within each group. Typically
the sum of this number across all usergroups
will be much larger than the total
number of users because some people will
belong to multiple groups within one system.
Additionally, numerous people or
organizations may interact with multiple
systems.
The last and possibly most difficult
part of this step is to generally estimate
the number of times an average user
invokes a given dialogue. For example, an
average user within a particular group
might invoke one dialogue an average of
once per month, and another dialogue 20
times per day. Ideally, you can collect feedback
from system end-users to help you
develop these estimates. Alternatively, you
may need to resort to best-guess estimates
developed by you, your test team, and any
available systems analysts.
The final objective of this step is to
have some idea regarding the relative frequency
that various dialogues are occurring.
This data will eventually be used to
help prioritize dialogues, but that prioritization
will also depend upon a dialogue's
historical defect profile, so that step must
be taken next.
3. Determine Historical
Defect Prevalence
For each dialogue, document the average
number of defects normally found during
testing, and add the average number
found after testing (that is, failures reported
by system users). This is a relatively
simple step; you will either have this data
or you will not. Probably, you will not.
Nevertheless, if you have been in the test
group for a while you can likely invent
some reasonably usable numbers.
Alternatively, you may be able to use historical
data from similar dialogues elsewhere
within the system. These numbers
do not need to be either accurate or precise.
All we are trying to determine is
which dialogues tend to contain the most
defects. Whether a given dialogue has
been 10 times more defective than another
or 20 times more defective is not really
important. For the prioritization step, it is
sufficient to know that it is normally much
more defect prone.
4. Prioritize Dialogues
Eventually, we are going to be testing
based upon dialogues (and possibly usecase
scenarios). The question at this point
is which ones and how thoroughly? As
indicated previously, the overall objective
is to perform efficient and effective testing
of multiple in-house COTS-intensive systems
by striving to perform testing in a
manner that reduces organizational risk
and that helps ensure the delivery of maximum
benefit to the end-users. Given this
objective, relative importance can be
established by examining the following for
each dialogue:
. - The size of the user-groups that
invoke the dialogue.
. - The frequency of invocation per unit
time (e.g., 50 users, 20 invocations per
user per day).
. - The relative role of the user-group and
dialogue to the organization's core
mission capabilities.
. - The historical defect prevalence associated
with the dialogue.
Note that this step is an analytical step,
not a calculation. The data developed in
prior steps is used to help make highly
informed decisions regarding how to prioritize
dialogues. However, remember that
much of the data may be gross estimates
at best and some may be outright speculation,
especially during early planning iterations.
Hence, use the underlying numbers
as an aid and combine them with the
experience and judgment of you and your
team.
The ideal output for this step is a
lifeboat ranking (or a fully ordered set) of all
the dialogues that are candidates for the
next phase of testing. Basically, you start
at the top of the list and keep working
downward as far as you can go, resources
permitting. If a fully ordered approach is
infeasible in your environment, then strive
to arrange dialogues into prioritized testing
sets (e.g., critical, highly important, important,
etc.).
5. Prioritize Test Types
This step consists of determining the
types of tests to run relative to the dialogues.
That is, are you only interested in
testing features, or do you also consider
other tests to be important? Examples of
other types of tests include the following:
- Performance (normal load).
- Stress (approaching design limits).
- Overload (substantially beyond design
limits).
- Security.
- Safety.
The purpose of this step is to ensure
that everything that is important regarding
organization risk management and enduser
benefit is considered. For some environments
the prioritization of which types
of tests should be run first is fairly stable.
For example, in life-rated systems, safety is
typically the highest priority. After this
step, you have everything necessary to
build the test dialogue matrix.
6. Build a Test-Dialogue Matrix
This is another potentially simple step
where you build a matrix to help ensure
that all appropriate tests for each of the
designated dialogues are run. For example,
although you may be planning to conduct
testing focused specifically on security,
there may be numerous dialogues where
security is not an issue and security testing
is not required. Within this matrix (dialogues,
in priority order, shown as rows;
and test types, also in priority order,
shown as columns), simply mark any cell
to indicate that you want to perform that
particular test (column) on that particular
dialogue (row).
7. Analyze Test Resources
The last step to perform before building
your test plan is to consider the resources
available for testing. This includes not only
human resources but also any automated
tools you have that can be used to help
with any subset of the testing. The general
approach is to run the most important
tests and to cover the maximum amount
of highest priority dialogues. However,
the overall objective continues to be risk
reduction and user benefit, so it might
make sense to adjust the order of the tests
because you have one or more automated
tools that allow you to rapidly and effectively
test numerous lower priority dialogues.
This would be the preferred
approach when the compound benefit of
testing a large number of lower priority
dialogues exceeds that of the delayed
higher-priority tests.
Integral to this approach is the fact
that it is often difficult, if not impossible,
to know your test resource availability relative
to future demands that may be
placed on your test group. This is why
each of these steps is ultimately about prioritization
and best utilization of available
resources. For example, you may think you
still have a month to finish testing the
dozen COTS systems that are currently
under test, but then again, what if you do
not? Especially when it comes to the highly
dynamic environments typically associated
with testing multiple COTS systems,
it is imperative that whatever is most
important to occur next (whether it is a
single human-intensive test or a highly
automated set of tests) is precisely what
occurs.
8. Establish a Test Plan
Dynamic environment notwithstanding, it
is important to take the time to develop an
actual test plan, or to post your latest
updates and revisions to the existing test
plan. The formality and scope of various
test plans may vary significantly depending
on system criticality (or lack thereof),
your overall test strategy, and resource
availability. For example, there undoubtedly
will be situations where exploratory
testing [5] will give far better coverage
(and test resource utilization) than scripted
testing; additionally, you minimize the
creation of comprehensive test documents
to maximize the performance of
actual test activities. Similarly, you will likely
want to consider some level of combinatorial
testing [6] to reduce the overall
number of required tests by focusing on
two-way and three-way parameter combinations
for effectively finding multi-mode
software faults. Regardless of the overall
strategy, however, in the interests of communication,
consensus, and overall risk
management, some level of documented
test plan is almost always beneficial.
In many environments, test plans (formal
or otherwise) are frequently overtaken
by events and therefore need frequent
revision. For example, you may want to
review your test plan on a weekly or
monthly basis to determine if any revisions
are required. Your test schedule,
however, including revisions to dialogue
prioritization, might need to be updated
on a daily or weekly basis.
When planning, consider the various
development groups within your organization,
and absolutely consider their track
record regarding their commitments to
the test group. Do they normally deliver
system and software enhancements on
time, or do they routinely miss by a few
months? The problem is, although you
have to consider this when preparing your
test schedule, project managers might find
it a tad offensive if your schedule shows,
for example, you are not really expecting
them to deliver until six months after their
claimed completion date. Therefore, consider
keeping both an "official test schedule"
and a "pessimistic test schedule." The
pessimistic schedule is what you use to
remind yourself how you think events are
really going to unfold.
As you are building or revising your
plan and schedule, always consider the
possibility of obtaining additional test
resources. For example, can developers
help with system testing? Absolutely. Can
system designers test? Certainly. Are systems
engineers, requirements analysts, and
end users all potentially effective testers?
Of course they are. Are any of these
resources available to you? They probably
are not. But then again, maybe that
depends on the relative importance of the
items on the upcoming testing schedule
relative to some of the other work currently
occurring within your organization.
Given the steps you have taken to create
the inputs to your multi-system test plan
and schedule, if you think additional
resources are needed, at a minimum you
can support your request with a very compelling
rationale.
9. Conduct Test Management
Effective test management requires a wide
variety of skills and activities, including the
identification, collection, and analysis of a
variety of test-related and quality-related
metrics, and metrics associated with test
status tracking, management, and control;
proper reviews (to varying levels of formality)
of test documentation and support
material; and the determination of clear
criteria for objectively assessing whether or
not a system is ready for piloting, and
when it is ready for operational use.Within
this context, test activities should be prioritized
with the ultimate objective of delivering
maximum benefit to the end-users.
Prioritization is also influenced by the
overall test strategy (such as exploratory
testing and/or combinatorial testing). As
testing activities are performed, there is
normally a wealth of defect data collected.
However, much of this strategically valuable
data often is eventually lost. That is,
test results are compiled and sent back to
the development teams and are used for
system and software corrections, but that
data is not otherwise archived and managed
by the test organization.
Note that one of the critical steps previously
described is the determination or
estimation of defect prevalence by dialogue.
Since you are running the tests, you
absolutely can and should retain this information.
Ideally, you have (or can find or
create) one or more failure-related reference
lists so that system failures can be
assigned to failure categories, failure severities,
failure likelihood in the field, etc. This
data can then be stored in a database, or
even in a spreadsheet for use during future
planning iterations.
Possibly even more important, to continue
to enhance this overall process you
must collect relevant data regarding failures
or problems reported from system
beta testing and production usage. These
are the defects that slipped past your testing
process. What are they? Where are
they? When were they discovered? How
were they discovered? For a given defect,
which user group reported it first? Which
user group reported it the most? What was
the impact? This data is absolutely essential
to you in your ongoing efforts to
understand end-user consequences and
organizational risk, and to continually
improve the contributions of your test
organization to overall mission success.
Delivering Maximum Benefit
Delivering maximum benefit to organizational
end-users, and ultimately to the
organization, is everyone's job. Therefore,
related to this discussion are numerous
quality topics such as the value of peer
reviews, the benefits of early inspections,
the greater benefits of perspective-based
reviews [1], etc., which directly impact
overall organizational competence and
mission performance. However, as a manager
or technical specialist within the test
organization, you normally do not influence
such things. The projects build what
they build, the procurement organization
buys what it buys, and the maintenance
teams implement changes however they
feel like. And you are the last line of
defense, literally, for your organizational
system's end-users.
There are many alternative approaches
to testing COTS-intensive systems. You
can, for example, assign functional requirements
to different priority levels, and then
take a priority-driven approach to test performance.
Alternatively, many organizations,
if they have sufficient resources,
plan and perform tests by taking one of
these approaches: try-to-test-everything-once,
top-down, front-to-back, or any of numerous
other techniques.
The premise behind the approach
described in this article is to increase your
efforts relative to test priority analysis and
planning, and to strive to maximize the
test organization's contribution to the
overall delivery of benefits to systems'
end-users, and the overall end-user experience.
Invariably, testing priorities will continue
to be a constantly shifting landscape
due to unexpected events. However, by
regularly following the steps described in
this paper you will steadily improve your
understanding of user-group interactions
with various systems and steadily increase
the amount of data available to you related
to user-discovered defects and consequences.
This combination of strategy,
understanding, and data will directly support
and enhance your overall efforts
toward leveraging your test organization
to deliver maximum benefit to your endusers.
References
- Boehm, B., and V. Basili. "Software
Defect Reduction Top-10 List." NSF
Center for Empirically Based Software
Engineering, Jan. 2001 www.cebase.org/www/home/index.htm.
- Bechtold, R. "Software Quality Valuation:
Return on Investment Versus
Reduction of Risk." International
Conference on Practical Software
Quality Techniques/Practical Software
Testing Techniques. Washington, D.C.,
June 2003.
- Bechtold, R. "Return on Investment for
Software Testing." Software Testing
Forum. Reston, VA., Mar. 2003.
- Satzinger, J., and T. Orvik. The Object
Oriented Approach, Concepts, System
Development, and Modeling with UML.
2nd ed. Course Technology, Thomson
Learning, 2001.
- Bach, J. "What Is Exploratory Testing?"
www.satisfice.com/articles/what_is_et.htm.
- Daich, Gregory T. "No-Cost Combinatorial
Testing Support." Software
Technology Support Center, Hill AFB,
UT., www.stsc.hill.af.mil/consulting/sw_testing/improvement/cst.html.
About the Author
Richard Bechtold,
Ph.D., is president of
Abridge Technology and
is an independent consultant
who assists industry
and government with
organizational change and systematic
process improvement, especially in the
area of implementing effective project
management. Bechtold has more than 25
years of experience in the design, development,
management, and improvement
of complex software systems, architectures,
processes, and environments. This
experience includes all aspects of organizational
change management, process
appraisals, process definition and modeling,
workflow design and implementation,
and managerial and technical training.
Bechtold is an instructor at George
Mason University where he teaches
graduate-level courses in software project
management, systems analysis and
design, principles of computer architectures,
and object-oriented java programming.
The second edition of his latest
book, "Essentials of Software Project
Management," is scheduled for publication
in 2004.