Risk Factor: Confronting the Risks That Impact Software Project Success Theron R. Leishman, Software Technology Support Center/Northrop Grumman Dr. David A. Cook, The AEgis Technologies Group, Inc.
Every systems and software project involves risk. Often, how you manage your program
risks is a deciding factor in the eventual success or failure of your program. If you ignore
the risks, your program has a higher chance of failing. On the other hand, if you try to
track and manage all possible risks, you can expend your entire budget managing the risks,
and never produce a deliverable. Risk management, like any other element of systems and
software development, requires forethought and careful planning. This article explains what
risk management is, and then discusses some common developmental risks.
There is a popular television program that
appeals to the brave of heart called
"Fear Factor." During this program, contestants
compete against each other in events
and activities that cause considerable fear for
most people. Although it is considered reality
TV, the things the contestants are required
to eat, drink, touch, dive into, or navigate
through are not considered reality by the
average person. Contestants are eliminated
with each fear-defying competition, until a
single winner remains.
In the reality world of software development
and/or acquisition, there are circumstances,
events, activities, etc. that instill
fear in the hearts of software developers,
acquirers, and managers. Too often these
fear factors are ignored and have devastating
impacts on software projects. The
authors of this article have participated in
the review and assessment of numerous
software-intensive systems from the perspective
of both developing software and
purchasing software. From our experiences,
we have identified several issues that
are common to many software-intensive
programs. These issues, risk factors, are keys
to either the success or failure of any software-
intensive system.
What Is Software Risk
Management?
Risk is defined as, "A possible future event
that, if it occurs, will lead to an undesirable
outcome" [1]. In the context of software
then, software risk management would logically
imply the managing of possible future
events that could have undesirable effects on
software projects. That sounds simple
enough. What future events could possibly
negatively impact my software project? Risk
management is simply defined as a generalized
process for managing risks [2].
However, to be an effective risk management
process, it has to be both accurate and
usable; that is, it must provide results to a
manager in time to allow the manager to
make informed decisions that allow risks to
be minimized or avoided.
Every development project has risks.
The risks can range from the common,
"We might not be able to find a JOVIAL
programming language expert by next
month," to the uncommon, "A hurricane
might destroy all of the prototype aircraft."
How you approach these risks is what is
important. In the rest of this article, risk
refers to software risk.
The Two Extremes of Software
Risk Management
There are two extremes of software risk
management: too little and too much. Each
one can be explained in terms of popular
operating systems.
The first extreme, the too little school,
is much like older versions of UNIX.
While UNIX is a fine operating system, its
roots show a lack of disciplined software
development. For those accustomed to a
single version of an operating system, there
existed numerous versions of UNIX - well
over 1001.
Here is an example of the too little school.
One of the authors used to work on a
Burroughs mini-computer back in the mid-
80s. It ran a version of UNIX referred to as
BNIX, which has an interesting property.
The memory table that kept a list of all currently
running jobs (the process table) had a
limited size, but there was no mechanism to
protect it. The size was somewhere around
1,023 entries. If you tried to run a process
after the table was full, BNIX just bumped the
counter to 1,024 and started entering
process data.
The fact that the process table was full
did not deter it - it just wrote to whatever
memory was at the 1,024th position. Since
the process table was stored in memory, it
was likely (in fact, it was certain) that this
1,024th process just overwrote something
critical in the operating system. Assuming
that the system did not crash immediately,
you could start a 1,025th process. Eventually,
the operating system would crash in some
bizarre fashion.
By not having mechanisms to deal with
the problem, which was a limited size
process table, BNIX used the ostrich-head-in-the-sand method of risk management. This
method means you assume that all will go
correctly, and you just pretend that no risks
exist. Many current software development
projects use this method - the equivalent of
believing in magic, which often occurs
because of a new and untested silver bullet.
For example, "Now that we are using commercial
off-the-shelf software in our program,
we're going to cut the schedule by 25
percent." This is unrealistic, unproven, and
head-in-the-sand thinking.
The second extreme of software risk
management, the too much school, is more
like Windows 98. Windows has many mechanisms
to ensure you do not overflow
process tables, overwrite system memory, or
use memory that is currently allocated to
other programs. However, Windows 98
sometimes gave a message that said something
like, "Unable to run program - not
enough memory. Try quitting a running program
and try again." Unfortunately, this
error message occurred when only running
a single program, or even no program.What
typically happened was that a previously
running program had used memory incorrectly
(or crashed prior to cleaning up after
itself) and left the system memory corrupted.
Windows 98 was unable to ensure that a
new program would not be overwriting
memory still marked as in use, and would not
let the new program run. It usually required
a reboot to set things right. This method,
being over-cautious of the risks and always
assuming that the worst is going to happen, is
the other extreme.
To effectively manage risks, you have to
take the middle ground. You cannot ignore
risks and pretend that all will go well.
However, you cannot micromanage all possible
risks; you do not have the time and
the resources. To take the middle ground,
you have to be aware of some common
risk factors.
Critical Systems and Software
Risk Factors
To adequately manage risks, it is essential to
evaluate the program's/project's unique situation.
There are, however, certain risks that
tend to impact many programs/projects.
Having evaluated several programs, we have
identified the following critical risk factors as
issues that impact the success of many programs.
By addressing the key risk factors,
programs can make great strides in managing
risks that may impact them.
Inadequate Planning
Recently while assisting in the review of a
large Department of Defense (DoD) software
acquisition program, we asked to
review the program's planning documents.
In response to the request, the program
office produced a Microsoft Project schedule.
This response is common when we ask
about planning documents while performing
program reviews.
There appears to be a lack of desire,
interest, ability, and attention to performing
adequate program/project planning. Not all
programs/projects require the same level of
planning; however, they all should include
enough planning to adequately assess their
issues. Program/project plans should consider
the following:
- Date and status of the plan.
- Scope of the plan.
- Issuing organization.
- References.
- Approval authority.
- Assumptions made in developing the
plan.
- Planned activities and tasks.
- Policies, etc., that dictate the need for this
plan.
- Micro-references - other plans or tasks
referenced by the plan (other plans or
task descriptions that elaborate details of
this plan).
- Schedules.
- Estimates.
- Communication chains.
- Resources and their allocation.
- Responsibilities and authority.
- Risks.
- Quality control measures.
- Cost.
- Stakeholder identification.
- Interfaces among stakeholders.
- Environment/infrastructure, including
safety needs.
- Training.
- Glossary.
- Change procedures and history.
- Schematics, diagrams, and architectures
to further clarify the intent of the plan.
A lack of adequate planning tends to
indicate a lack of forethought and direction.
Inadequate planning at either a program
or project level greatly increases risk
to successful project completion. Elaine M.
Hall [2] has a good explanation of how to
plan for risk.
Unrealistic Schedules
The daughter and son-in-law of one of the
authors of this article recently built a house.
The couple was anxious to have the home
completed so they could move in early
enough in the fall to complete the yard
before winter. To them this seemed a reasonable
request.
As the couple negotiated the deal with
the chosen contractor, they were told the
house would not be completed in the time
schedule desired by the couple. The contractor
showed them the list of tasks to be completed
and the dependency of each task with
other tasks. He further explained to them the
dependency on outside factors such as
weather, availability of special materials that
were part of the couple's design, availability
of subcontractors, whims and schedules of
building inspectors, and the priority of their
house in relationship to other homes the
developer was building. The bottom line: the
couple was not able to eliminate critical steps
in the building process, shortcut the availability
of critical resources, or circumvent
required inspections.
Have you ever been coerced into or
managed a software project that begins with
a predetermined schedule? One that is
unachievable, to start with, that requires
sound processes to be altered or eliminated?
One that ignores the requirement for critical
resources, eliminates critical reviews, and
allows only minimal time for testing? If so,
then in talk-show host and author Dr. Phil's
words, "What are you thinking?"
Why do we agree to and/or impose software
schedules that require the abandonment
of everything that we have learned
over the past several years as being essential
to the success of software development or
acquisition projects?
The authors have seen numerous software
projects with schedules we consider to
be unreasonable, in our opinion, due to the
following:
- Schedules based on product need rather
than a realistic assessment of engineering
effort. This includes schedules based
on an arbitrarily imposed due date.
- Effort estimates and resulting schedules
based on hallucinations (or unrealistic
hope) rather than on historical basis.
- Schedules based on unrealistic, incorrect,
or unknown requirements.
- Schedules developed without adequate
understanding of sound software engineering
practices.
For these reasons, we have included unrealistic
schedules as one of our software risk
factors.
Unfortunately, managers who attempt to
transform unreasonable schedules into accurate
and reasonable ones run the additional
risk of extreme upper management displeasure.
This (and the risk of losing one's job)
creates great pressure on lower-level managers
to continue to pretend that unreasonable
schedules are, in fact, achievable.
Unconstrained Requirements Growth
There have been volumes written over the
years about the impact of incomplete, inaccurate,
growing, unstable, and on, and on,
and on, software requirements problems. In
the April 2002 CrossTalk, we enumerated
several requirements risks that can drown
software projects [3].
Research conducted by Capers Jones [4]
identified the top five risks that threaten the
success of software projects in various sectors.
Figure 1 summarizes the approximate
percentage of projects that suffer from
creeping user requirements.
Figure 1: Percentage of Three Types of Projects That Suffer From Requirements Creep
(Click on image above to show full-size version in pop-up window.)
As indicated in Figure 1, the majority of
management information systems and military
projects suffer from requirements creep.
We further saw that nearly half of the outsourced
projects included in the study also
suffered from requirements creep.
Our experience shows that nearly all projects
suffer from some form of requirements
risk. The impact is often catastrophic
to the success of the project.We see requirements
issues as a substantial risk to the success
of many software projects.
Dysfunctional Organizational Culture
The following is the parable of the Happy
and Productive Worker:
Once upon a time in a company not
far away, there was a worker. He was a
productive, happy worker, but alas, he was
unsupervised.
The company saw that the worker was
unsupervised and made a supervisor.
The coordinator saw that the worker was
productive and happy and made a lead
worker to make the worker more productive
and happier.
The company saw that the department in
which the productive, happy worker worked
had grown and made a manager to manage
the department in which the productive,
happy worker worked productively and happily.
The manager saw that the worker was
productive and happy and made an assistant
manager to help manage the department
in which the productive, happy worker
worked.
The company saw that the department
where the happy, productive worker worked
had grown and made an administrator to
administer the department in which the productive,
happy worker worked.
The administrator saw that the worker
was productive and happy and made an
assistant administrator to assist in administering
the department in which the productive,
happy worker worked.
More people were added until the director
saw that the department was losing
money. So he consulted a consultant. The
consultant examined the department in
which the productive, happy worker worked
productively and happily and advised there
were too many people in the department in
which the productive, happy worker worked.
And the director paid heed to the counsel
of the consultant and fired the productive,
happy worker.
In the parable of the Happy and
Productive Worker, the organization valued
and rewarded the wrong things. As you think
of the organizations you work in, what is the
culture that exists? Is it a culture plagued
with high turnover? Do you enjoy going to
work each day, or does it take an act of God
to get you out of bed and into the office? Do
you have the training and skills required to
perform the tasks that are expected of you?
Are meetings useful with something actually
being accomplished, or are there too many
long, useless meetings that just distract from
what you are trying to get done?
The organizational culture of many software
companies appears to be that of working
harder to get out of doing work rather
than actually getting things done. This risk
factor ties closely to the management. There
is an inherent risk with over-managing - and
perhaps this risk is greater than under-managing.
Over-management forces workers to
spend too much time justifying what they do
(and do not do). Workers need to be allowed
to fail occasionally, and learn from their failure.
If you create an environment of one mistake
and you're out, workers will spend so
much time trying not to fail that they will not
have the time to succeed.
During a recent seminar, we asked the
attendees how many of them had ever been
part of what they considered to be a highperformance
team. Of 30 attendees, five
indicated that they had. Upon discussion
with the group, we identified the following
characteristics of a high-performance team:
- Value for all team members.
- Open communication.
- Common understanding of team goals.
- Recognition for valuable contributions.
- Clear understanding of job expectations.
- Shared desire to meet or exceed expectations.
- Demonstrated commitment to the team
by management.
It is difficult to successfully develop
software in a dysfunctional organization.
Management must look honestly at the
organization to determine if it is dysfunctional.
If your culture is one similar to that
of the Happy Productive Worker, that culture
is a serious risk to your organization's
success in consistently providing quality
software.
Not Having or Following Processes
Having and following a good process is
essential to the consistent development of
quality software systems. It has been said
that a software product is only as good as the
process used to develop and maintain it.
There seems to be common agreement
on the value of having and following sound
processes in the development and maintenance
of software, yet in the authors' experiences,
this continues to be a weakness of
many software development organizations.
We see many organizations that either lack
processes or do not follow their existing
processes. Some have processes in place but
are quick to abandon them when hit with
schedule pressure.
When this happens, the good, smart
things that help ensure quality software fall
by the wayside and programs/projects gradually
spin out of control. Not having or following
processes is on our list of software
risks because this is an area that is often only
given lip service. If processes exist, and are
required to be followed, many other risks
immediately become less critical.
Failure to Actively Manage
Software Risk
Have you ever thought about how much we
depend on software? The world has evolved
to the point where almost everything we do
involves software. Lt. Gen. Jim Fain (U.S. Air
Force retired), during his tenure as F-22 program
director, described software's importance
by saying, "The only thing you can do
with an F-22 that does not require software
is to take a picture of it" [5]. Now in 2004,
there is probably not even a non-disposable
camera in use that is not at least partially
operated by software.
Software has made great technological
advancement possible. This dependence on
software has also brought with it consequences.
Software failures have resulted in
significant financial losses and even the loss
of life. Software has become the very heart
of the new economy, and business risk management
must include software risk management
to survive.
During a recent program review, one of
the authors of this article asked how software
risks were managed on the program.
The program office produced a list from
their risk database of software risks that
included risks at a very high level and were
generic to the point that they could be
applied to any program. When asked how
the list was generated, it was explained that a
tool had generated the risks based on information
provided. We call this risk management
in a can. This was a large DoD program
that included software with potential
life-threatening consequences.
Our dependence on software has pushed
us to the point where a proactive software
risk management process is essential.
Managers must determine whether any
unwanted events may occur during the
development or maintenance of software,
and make appropriate plans to avoid or minimize
the impact of these negative consequences.
Failure to do so may have devastating
consequences. A good software risk
management process should include the following
steps:
- Identification of program-/projectspecific
software-related risks.
- Detailed analysis of each software risk.
- Development of plans to address software
risks.
- Active monitoring and tracking of
software risks.
- Use of metrics to monitor the riskmanagement
process.
By actively managing software-related
risks, the probability of experiencing firsthand
the consequences of a software failure
can be greatly reduced. While failure to
actively manage software risk is the last risk
mentioned, it is critical.
How detailed should your risk management
be? On one recently performed assessment,
the risk list on the project ran more
than 400 pages, and had a complex formula
showing each risk status. Such a complex risk
list is almost useless. It is difficult to see the
overall project risk status, and it takes a huge
amount of time to keep it current.
The authors recently performed another
assessment, and saw the risks briefed as a
25-item list, each with either a red, yellow, or
green light (standing for high, medium, and
low risk). This method was easy to use, easy
to understand, and reasonably easy to
update. The key point is that the program
manager, using this simple 25-item list, has
the information to understand the risk
exposure of the program and make good
decisions.
Conclusion
This article is not intended to present a complete
list of risk factors for a particular program/
project - it would take much more
space. Likewise, it is not intended to be a
primer on correct risk-management practices.
What this article is intended to do is
heighten your awareness of risk management,
and give you a starting point in creating
an appropriate risk management strategy.
Risk management is usually a task best done
by somebody who has some experience in
the area. Locate an appropriate source of
training or experience, and learn from
other's mistakes. If you proactively manage
risks properly, then you will spend little time
reactively putting out unexpected fires, thus freeing
up more time to build your system based
on current, accurate, and easy-to-understand
risk information.
During a recent "Fear Factor" episode,
contestants were required to leap from one
boat to another while the two boats were
speeding next to each other. This resulted in
some of the contestants experiencing very
traumatic falls into the water.
In this article, we have identified six risk
factors that, based upon our experience, can
have significant impact on the success or
failure of software programs and projects.
By confronting these risks, many inherent
problems can be avoided. We recommend
the following:
- Take program/project planning seriously.
- Do not lie to yourself; develop schedules
based on sound facts and proven
approaches.
- Stringently control requirements growth.
- Establish a success-oriented organizational
culture.
- Develop and follow sound software
development, maintenance, and program/
project management processes.
- Actively identify and manage risks specific
to your program/project.
By doing these, you can reduce the probability
of your program or project having a
traumatic fall into the pit of unsuccessful
software programs and projects. The biggest risk of all is failing to manage your risks! References
1- Leishman, T., and J. VanBuren. "The
Risk of Not Being Risk Conscious:
Software Risk-Management Basics."
STSC Seminar Series, Hill AFB, UT.,
2003.
2- Hall, Elaine M. Managing Risk. Addison-
Wesley, 1998.
3- Leishman, Theron, and Dr. David A.
Cook. "Requirements Risks Can Drown
Software Projects." CrossTalk 15.4
(Apr. 2002): 4-8 www.stsc.hill.af.mil/crosstalk/2002/04/leishman.html.
4- Jones, Capers. Assessment and Control
of Software Risks. Prentice Hall, 1994.
5- Naval Postgraduate School. "Importance
of Software to the Military." U.S. Navy, 4
Mar. 2000 www.nps.navy.mil/wings/acq_topics/AcqTopics.htm.
Note
- See www.scs.org/confernc/astc/astc04/cfp/astc04.htm for a starting
point.
About the Authors
Theron R. Leishman
is a consultant currently
under contract
with the Software
Technology Support
Center at Hill Air
Force Base, Utah. Leishman has 19
years experience in various aspects of
software development. He has successfully
managed software projects
and performed consulting services for
the Department of Defense, aerospace,
manufacturing, health care,
higher education, and other industries.
He is a Level 2 Certified International
Configuration Manager by the
International Society of Configuration
Management, and is employed
by Northrop Grumman. Leishman
has a master's degree in business
administration from the University of
Phoenix.
Software Technology Support Center 6022 Fir AVE, BLDG 1238 Hill AFB, UT 84056
Phone: (801) 775-5738
Fax: (801) 777-8069
E-mail: theron.leishman@hill.af.mil
David A. Cook, Ph.D.,
is a senior research scientist
at AEgis Technologies
Group, Inc.,
working as a verification,
validation, and
accreditation agent in the modelling
and simulations area. He is currently
supporting the Airborne Laser System
Program. Cook has more than 30 years
experience in software development
and management. He was formerly an
associate professor at the U.S. Air Force
Academy, a deputy department head of
the Software Professional Development
Program at the Air Force Institute
of Technology, and a consultant for the
Software Technology Support Center.
Cook has published numerous articles
on software-related topics. He has a
doctorate degree in computer science
from Texas A&M University.