NRC Seal/Skip Navigation
Index | Site Map | FAQ | Help | Glossary | Contact Us         Advanced Search

Home Who We Are What We Do Nuclear Reactors Nuclear Materials Radioactive Waste Facility Info Finder Public Involvement Electronic Reading Room
NRC Seal
NRC NEWS
U.S. NUCLEAR REGULATORY COMMISSION

Office of Public Affairs, Region II
61 Forsyth Street SW, Atlanta, GA 30303
www.nrc.gov


No. II-02-041   July 30, 2002
CONTACT: Ken Clark (404) 562-4416
Roger D. Hannah (404) 562-4417
E-mail: opa2@nrc.gov

NRC STAFF TO MEET WITH TVA TO DISCUSS
RESTART OF UNIT 1 AT BROWNS FERRY NUCLEAR PLANT
Printable Version PDF Icon


The U.S. Nuclear Regulatory Commission staff will meet with Tennessee Valley Authority officials on Wednesday, August 7, to discuss the Browns Ferry Unit 1 Restart Project. The meeting will be held at 10:00 a.m. EDT in the NRC Region II office, Sam Nunn Federal Center, 61 Forsyth Street in Atlanta.

The Browns Ferry plant is located near Athens, Alabama, and all three units at the plant were shut down by TVA in 1985. After NRC approval, TVA returned Unit 2 to service in 1991 and Unit 3 in 1996. Unit 1 has remained shut down since 1985 and the NRC will review its readiness to operate again after TVA completes the activities needed for restart.

The August 7th meeting, involving NRC and TVA management, will focus on general TVA plans to complete the work necessary to restart the unit and the NRC role in inspecting those activities. That management meeting will be followed by a working level meeting between TVA and NRC staff to discuss coordination of NRC inspections with the TVA restart activities.

Both meetings are between the NRC and TVA but are open to observation by interested members of the public. NRC officials will also be available prior to the conclusion of both meetings to answer any questions observers may have.