OSM Seal Announcements Navigation graphic Home page Directory Index Search Ask a Question Help
Toolbar3.gif

New Type of Retaining Wall Constructed To Abate Coal Mining Related Landslide in Kentucky A new technique for retention of a landslide in Hazard, Kentucky has been completed which utilizes steel galvanized guardrail and steel rail piling in combination to implement the final phase of this emergency abatement project. Phase I design has been in place for over six months for protection of a house and was provided by in-ground steel rails for temporary stabilization. The final design eliminated the need for a reinforced concrete wall which represents a substantial savings to the Office of Surface Mining. This final project design was a long-term solution for stabilizing a slide which had penetrated under a house affected by mine drainage and spoil from an old abandoned surface and underground mining operation conducted in the 1920's.

The newly developed design utilized a combination of steel rails with galvanized steel guardrail for retention panels. This technique is generally valid for walls less than 10 feet in height with granular backfill and with a footer that can be placed on shallow soils or on bedrock. The landslide below the wall was excavated to prevent any further encroachment on a state highway that had also been affected by the original slide. The combination of guardrail and steel rail piling allowed a savings of 50 percent of the cost of a comparable reinforced concrete retaining wall. These walls are planned as a standard design in the future for similar height structures.



Proposed rule on Excess Spoil, Stream Buffer Zones, and Diversions comment period extended and hearings planned In a Federal Register Notice on February 26, 2004, the Office of Surface Mining extended the comment period on the proposed Excess Spoil, Stream Buffer Zones, and Diversions rule published on January 7, 2004. The comment period on the proposed rule scheduled to close on March 8, 2004, is being extended by 30 days and written comments will be accept on the proposed rule until April 7, 2004 in order to afford the public more time to comment and to allow enough time to hold five public hearings. The five hearings are scheduled as follows:
  • March 30, 2004, 6 p.m. to 9 p.m.
    Charleston Civic Center, Room 206
    200 Civic Center Drive
    Charleston, WV.
  • March 30, 2004, 6 p.m. to 9 p.m.,
    Best Western Parkway Center, 8th Floor in the Horizon Room
    875 Greentree Road
    Greentree, PA.
  • March 30, 2004, 6 p.m. to 9 p.m.
    Hazard Community College, Hazard Campus
    Jolly Center, Room 208
    One Community College Drive
    Hazard, KY
  • March 30, 2004, 6 p.m. to 9 p.m.
    Roane State Community College
    O’Brien Building, Room 101
    276 Patton Lane
    Harriman, TN
  • March 30, 2004, from 2 p.m. to 4 p.m.
    Office of Surface Mining, South Interior Auditorium
    1951 Constitution Avenue NW.
    Washington, DC 20240


Proposed Ownership and Control Settlement Rule comment period extended In a Federal Register notice on February 26, 2004, the Office of Surface Mining extended the comment period on the proposed Ownership and Control Settlement Rule published on December 29, 2003. The comment period on the proposed rule was scheduled to close on February 27, 2004. In response to requests from the public, the comment period is being extended to March 29, 2004.

Proposed regulation on Excess Spoil, Stream Buffer Zones, and Diversions Published The Office of Surface Mining has issued proposed regulations to accomplish two basic goals: Minimizing the adverse environmental effects stemming from the construction of excess spoil fills; and clarifying the circumstances in which mining activities, such as the construction of excess spoil fills, may be allowed within the stream buffer zone, i.e., within 100 feet of a perennial or intermittent stream. These changes will also reduce conflicts and improve consistency between regulation under the Surface Mining Law and the Clean Water Act. Electronic or written comments are requested and must be received by March 8, 2004. An Environmental Analysis on this rulemaking is also available. (Environmental Analysis Appendix).

Office of Surface Mining study finds 3.5 million Americans at risk from nearby abandoned mine hazards To estimate the number of Americans potentially at risk from Abandoned Mine Land hazards, Office of Surface Mining staff compared census information for 2000 with data in the Office of Surface Mining's Abandoned Mine Land Inventory System. Estimates were compiled by determining the approximate number of people living one-half mile and a mile from an abandoned mine land site. Study findings show that nearly 1.2 million Americans live within a half mile of an abandoned mine land site considered a Priority 1 or 2 hazard to health and safety. More than 3.5 million Americans live a mile or less from a hazardous abandoned mine site. At both distances, more people are at risk in the eastern United States, particularly in the Appalachian coal-mining region where there are more abandoned mining sites and denser population patterns. Click here for the People Potentially at Risk From Priority 1 & 2 AML Hazards White Paper.

Find the trees and win a commemorative key chain To help identify the value of planting trees on reclaimed active and abandoned coal mines the Office of Surface Mining is distributing a brochure titled, Market-Based Mine Land Reclamation. To highlight the value of reforestation, a tree hunt is underway on this web site. The first person to find all the trees wins a 25th Anniversary of the Surface Mining Law key chain. One of the trees is just to the right. Click on the tree to begin collecting your trees, or here for more information about the tree hunt.Tree graphic

Navigation graphic

(Home Page)

Office of Surface Mining
1951 Constitution Ave. N.W.
Washington, D.C. 20240
202-208-2719
getinfo@osmre.gov