Issues
In Focus.
The Renewable Electricity Production Tax Credit
In the late 1970s and early 1980s, environmental
and energy security concerns were addressed at the Federal level
by several key pieces of energy legislation. Among them, the Public
Utility Regulatory Policies Act of 1978 (PURPA), P.L. 95-617, required
regulated power utilities to purchase alternative electricity generation
from qualified generating facilities, including small-scale renewable
generators; and the Investment Tax Credit (ITC), P.L. 95-618, part
of the Energy Tax Act of 1978, provided a 10-percent Federal tax
credit on new investment in capital-intensive wind and solar generation
technologies [85].
The Energy Policy Act of 1992 (EPACT) included a
provision that addresses problems with the ITCspecifically,
the lack of incentives for operation of wind facilities. EPACT introduced
the Renewable Electricity Production Tax Credit (PTC), a credit
based on annual production of electricity from wind and some biomass
resources. The initial tax credit of 1.5 cents per kilowatthour
(1992 dollars) for the first 10 years of output from plants entering
service by December 31, 1999, has been adjusted for inflation and
is currently valued at 1.8 cents per kilowatthour (2002 dollars)
[86, 87].
The original PTC applied to generation from tax-paying
owners of wind plants and biomass power plants using fuel grown
in a closed-loop arrangementcrops grown specifically
for energy production, as opposed to byproducts of agriculture,
forestry, urban landscaping, and other activities. In its early
years, the PTC had little discernable effect on the wind and biomass
industries it was designed to support. By 1999, however, when the
provision was originally set to expire, U.S. wind capacity had begun
growing again, and the PTC supported the development of more than
500 megawatts of new wind capacity in California, Iowa, Minnesota,
and other States. Wind power development was also encouraged by
State-level programs, such as the mandate in Minnesota for 425 megawatts
of wind power by 2003 as part of a settlement with Northern States
Power (now Xcel Energy) to extend on-site storage of nuclear waste
at its nuclear facility [88].
In 1999, the PTC was allowed to expire as scheduled,
but within a few months it was retroactively extended through the
end of 2001 [89], and poultry litter was added to the list
of eligible biomass fuels. Although wind power development slowed
significantly in 2000, 2001 was a record year with as much as 1,700
megawatts installed [90]. Again, State and local programs,
including a significant renewable portfolio standard (RPS) program
in Texas, also supported new wind installations.
The PTC was allowed to expire again on December 31,
2001, while Congress worked on a comprehensive new energy policy
bill. It was retroactively extended a second time to December 31,
2003, as part of an omnibus package of extended tax credits passed
in response to the economic downturn and terrorist attacks of 2001
[91].
Like the 1999 expiration and extension, the extension
of the PTC in 2002 was followed by a lull in wind power development.
And again, a review of confirmed industry announcements indicates
that 2003 will see total new installations of more than 1,600 megawatts
of wind capacity. Significantly, while many 2003 builds still rely
on multiple incentives (for example, the PTC plus a State program)
to achieve economic viability, there are some in Oklahoma and other
States that have been developed with little government support beyond
the PTC [92].
With reductions in capital costs and increases in
capacity factors [93], wind power technology has improved
since the introduction of the ITC and subsequent replacement by
the PTC. It is likely that the installations spurred by these incentives
allowed the industry to learn by doing and thus contributed
to improvement of the technology. There were, however, other factors
that contributed to cost reductions during the period, including
government-funded research and development (both domestic and international)
and large markets for wind power technology that were created by
subsidy programs in other countries, especially, Denmark and Germany.
The AEO2004 reference case, assuming no extension
of the PTC beyond 2003, projects that the levelized cost of electricity
generated by wind plants coming on line in 2006 (over a 20-year
financial project life) would range from approximately 4.5 cents
per kilowatthour at a site with excellent wind resources [94]
to 5.7 cents per kilowatthour at less favorable sites. To incorporate
the effect of the current 1.8-cent tax credit over the 10-year eligibility
period for those plants, the projections account for both the tax
implications and the time value of the subsidy. As a tax credit,
the PTC represents 1.8 cents per kilowatthour of tax-free money
to a project owner. If the owner did not receive the tax credit
and wanted to recoup that 1.8 cents with taxable revenue from electricity
sales, the owner would have to add 2.8 cents to the sales price
of each kilowatthour, assuming a 36-percent marginal tax rate. Applying
the same assumptions used to derive the 4.5-cent total levelized
cost of wind energy over a 20-year project life, the levelized value
of the PTC to the project owner is approximately 2 cents per kilowatthour.
In the reference case, the levelized cost for electricity
from new natural gas combined-cycle plants is 4.7 cents per kilowatthour,
and for new coal-fired plants the projected cost in 2007 is 4.9
cents per kilowatthour [95]. Thus, it is easy to see how
the PTC could make wind plants an attractive investment in the current
electricity market.
In addition to generation cost comparisons, the difference
between an intermittent resource (wind plants) and a dispatched
resource (coal- and gas-fired plants) must also be considered. Dispatched
generation provides value to the grid because it contributes
more to the reliability of the system and is generally available
to meet daily and seasonal load requirements. An intermittent resource
has only limited ability to contribute to grid reliability and does
not necessarily produce energy in a daily or seasonal pattern that
matches daily or seasonal load variations.
Given the uncertainty regarding both the short-term
extension of the PTC and its long-term fate, EIA developed three
alternative PTC cases for AEO2004. The cases are not meant
to indicate a preferred or even likely policy outcome, but rather
to provide a useful range of possible outcomes to provide insight
into the effects of the PTC program on future energy markets relative
to the reference case forecast, which assumes no new PTC subsidy
beyond 2003.
The 3-year PTC case assumes that the PTC is extended
to December 31, 2006, as provided for in the Energy Bill Conference
Report adopted in the House and now before the Senate. The extended
program continues to cover wind and currently eligible biomass fuels,
and coverage is extended to open loop biomass sources
(primarily waste or byproducts from other processes) and landfill
gas generation, as provided for in the Conference agreement. Otherwise,
the structure of the program is assumed to remain the same as under
current law.
The 9-year PTC case assumes extension of the program
to December 31, 2012, as well as the expansion to all biomass and
landfill gas resources. All other assumptions remain the same as
under current law. This case assumes a single 9-year extension,
rather than a series of short-term expirations and reauthorizations
[96]. Because the history of the PTC indicates that such
a cycle can affect the dynamics of industry expansion, and because
the specific tax-liability limitations of project owners are unknown,
this case provides upper-end estimates of capacity additions resulting
from the PTC with a 9-year extension.
The 9-year half PTC case also assumes an extension
of the PTC to 2012 and expansion to biomass and landfill gas resources.
In this case, however, a modified program is assumed, with the value
of the tax credit set at 0.9 cents per kilowatthour (2003 dollars)
for the first 10 years of plant operation, indexed to inflation.
The assumptions for this case do not reflect any expectation or
proposal for the policy but were selected to provide insight into
the limitations of the analysisspecifically, uncertainty about
the ability of industry to capture the full tax credit valueas
well as an indication of program effects if the value of the tax
credit were reduced.
The reference case does not assume the installation
of any planned capacity for which construction is indicated to be
dependent on extension of the PTC. Such planned capacity is included
in the three sensitivity cases through the assumed final extension
date 2006 in the 3-year PTC case and 2012 in the 9-year PTC
case and the 9-year half PTC case. Otherwise, the sensitivity cases
follow the reference case assumptions and are based on a fully integrated
run of the National Energy Modeling System (NEMS), ensuring that
price feedback effects (such as in natural gas markets) are fully
accounted for.
Printer
Friendly Version
Projection |
2003
|
2010 |
2025 |
Reference
|
Reference
|
3-year
PTC |
9-year
PTC |
9-year
half PTC |
Reference
|
3-year
PTC |
9-year
PTC |
9-year
half PTC |
Electric
power sector net summer capacity (gigawatts)
|
Municipal
solid waste and
landfill gas |
3.6
|
3.9
|
4.6
|
4.7
|
4.4
|
4.0
|
4.6
|
4.7
|
4.5
|
Wood and
other biomass |
1.9
|
2.2
|
2.1
|
4.4
|
3.2
|
3.7
|
4.6
|
13.7
|
8.1
|
Wind
|
6.5
|
8.0
|
15.9
|
40.3
|
23.4
|
16.0
|
23.8
|
65.4
|
38.8
|
Total
electric power industry |
936.9
|
931.7
|
937.5
|
958.1
|
943.3
|
1,169.9
|
1,176.7
|
1,221.0
|
1,191.7
|
Electric
power sector generation (billion kilowatthours)
|
Municipal
solid waste and
landfill gas |
25.6
|
28.1
|
33.7
|
34.5
|
32.3
|
28.5
|
33.9
|
34.7
|
32.4
|
Wood and
other biomass |
15.7
|
23.5
|
23.4
|
28.4
|
26.3
|
29.2
|
33.4
|
90.9
|
51.8
|
Dedicated
plants |
10.8
|
13.3
|
13.0
|
22.5
|
17.5
|
22.9
|
28.4
|
90.9
|
51.0
|
Co-firing
|
5.0
|
10.3
|
10.4
|
6.0
|
8.8
|
6.3
|
5.0
|
0.0
|
0.8
|
Wind
|
17.4
|
24.1
|
52.5
|
139.3
|
79.2
|
53.2
|
81.8
|
230.0
|
136.5
|
Total
electricity generation |
3,900.0
|
4,510.0
|
4,511.0
|
4,523.0
|
4,512.0
|
5,787.0
|
5,787.0
|
5,805.0
|
5,790.0
|
|
Table 18 compares the key results of the three PTC
sensitivity cases with the reference case. The 3-year PTC case,
with an expiration date of December 2006, results in an additional
7.9 gigawatts of new wind capacity by 2010 compared to the reference
case. By 2025, however, new wind capacity in the 3-year PTC case
is only 7.8 gigawatts higher than in the reference case. Between
2007 (after the PTC expires) and 2025, 13.5 gigawatts of new wind
capacity is constructed in the 3-year PTC case, compared with 8.6
gigawatts in the reference case for the same period. After 2010,
the 3-year PTC case does not project additional wind capacity builds
beyond those in the reference case. Compared with the reference
case, no additional construction of new biomass facilities by 2010
is projected in the 3-year PTC case. Biomass facilities require
longer construction lead times than the 3-year extension and therefore
are not able to take advantage of the 3-year extension.
The 3-year PTC case projects the cumulative cost
to the U.S. Treasury from the 3-year extension to be $1.7 billion
(2002 dollars), using a 7 percent real discount rate [97].
This represents the tax revenue not recovered from the tax-paying
owners of all wind and dedicated biomass facilities placed in service
from the beginning of 2004 to December 31, 2006. It does not include
lost revenue from existing facilities (placed in service before
December 31, 2003) but does include facilities already planned or
committed to be built after 2003.
The 9-year PTC case, with an expiration date of December
2012, results in an additional 32.3 gigawatts of new wind capacity
by 2010 compared to the reference case. By 2015, that has increased
to 54.7 gigawatts over the reference case, but by 2025, the 9-year
PTC case only has an additional 49.4 gigawatts over the reference
case. The cumulative cost to the U.S. Treasury for a 9-year, full
value extension is $33 billion, compared to the reference case with
no extension.
The extension to 2012 also provides an opportunity
for new biomass facilities to be constructed to take advantage of
the tax credit. By 2010, an additional 2.2 gigawatts of operating
biomass capacity is projected in the 9-year PTC case relative to
the reference case, increasing to 8.5 gigawatts over the reference
case in 2015 and 10 gigawatts in 2025. In 2025, the 13.7 gigawatts
of installed biomass capacity in the 9-year PTC case is projected
to generate 91 billion kilowatthours, in addition to 230 billion
kilowatthours of projected generation from 65.4 gigawatts of installed
wind capacity. Although the additional biomass capacity projected
in the 9-year PTC case relative to the reference case is only 21
percent of the wind capacity added by 2025, because of its higher
relative capacity factor, the projected generation from the additional
biomass capacity is almost 40 percent of that from the additional
wind capacity.
Almost 6.3 billion kilowatthours of biomass co-firing
(that is, biomass fuel burned with coal in existing coal-fired plants)
is projected in the reference case by 2025. In the 9-year PTC case,
no co-fired generation is expected by 2025, largely because the
more efficient new dedicated biomass facilities would be able to
pay feedstock suppliers higher fuel premiums than the less efficient
existing coal facilities retrofitted with co-firing equipment.
Total biomass generation (dedicated plus co-firing) in the 9-year
PTC case is more than triple total biomass generation in the reference
case (91 billion kilowatthours and 29 billion kilowatthours, respectively).
In the 9-year half PTC case, substantial projected
increases in wind capacity relative to the reference case projection
reflect wind power costs that are, without subsidy, very close to
being competitive. Although the 9-year half PTC case projects 27
gigawatts less installed wind capacity in 2025 than the 9-year PTC
case, it projects almost 23 gigawatts more than in the reference
case. Like the 9-year PTC case, the 9-year half PTC case projects
significant leveling off of new wind installations after 2012, when
eligibility for the subsidy ends. Between 2015 and 2025, wind capacity
in the 9-year half PTC case increases by only 1.1 gigawatts, compared
with 5.5 gigawatts of capacity growth in the reference case. Although
by 2015 the basic unsubsidized levelized cost [98] of wind
energy is reduced by about 0.5 cents per kilowatthour below the
reference case for the same year, fewer low-cost resources are available
once the subsidy has expired (having already been developed with
the subsidy in place), and fewer attractive resources are available
for development. The cumulative cost of the PTC extension to the
U.S. Treasury in the 9-year half PTC case is projected to be $16
billion.
The projection for dedicated biomass capacity in
2025 in the 9-year half PTC case is 4.3 gigawatts higher than in
the reference case. Although the additional capacity is sufficient
to draw substantial biomass feedstock from the co-firing market,
it does not completely eliminate it. Co-firing in 2025 in the 9-year
half PTC case is only about 0.8 billion kilowatthours below the
reference case projection of 6.3 billion kilowatthours.
Notes and Sources
Released: January 2004
|