Missouri River Flood and Drought:
Experts Agree the Corps Took Appropriate Action, Given the Circumstances, but Should Examine New Forecasting Techniques
GAO-14-741: Published: Sep 12, 2014. Publicly Released: Sep 12, 2014.
Additional Materials:
- Highlights Page:
- Full Report:
- Accessible Text:
Contact:
(202) 512-3841
fennella@gao.gov
Office of Public Affairs
(202) 512-4800
youngc1@gao.gov
What GAO Found
Experts who participated in a GAO-sponsored meeting agreed that the U.S. Army Corps of Engineers (Corps) made appropriate release decisions during the 2011 flood and 2012 and 2013 drought affecting the Missouri River basin, given the severity of these events. These experts acknowledged that the flood was primarily due to extreme rain in eastern Montana in May and June 2011. The experts agreed that no existing forecasting tools could have accurately predicted these extreme rainstorms more than a week in advance. One of the experts also said that the Corps would have needed several months to release enough water from the reservoirs to have sufficient space for the runoff that occurred in 2011, and predicting an extreme runoff year that far in advance is beyond the current state of science. Moreover, the experts agreed that the Corps appropriately followed the drought conservation procedures in the Missouri River Mainstem Reservoir System Master Water Control Manual (Master Manual), which sets out policies for managing the river. The experts agreed that the Corps does not need to change the Master Manual in response to the 2011 flood or subsequent drought. However, some of the experts noted that if the Corps develops improved forecasting tools, it might be useful to evaluate whether changes to the Master Manual would help the Corps to act on information from the new tools.
The experts suggested that improving data systems and introducing new runoff forecasting techniques could improve the Corps' ability to make release decisions in less extreme events than the 2011 flood. These data systems—such as streamgages, weather radar, precipitation gauges, soil moisture monitoring, and monitoring for snow on the plains—are not managed by the Corps, but by other federal and state agencies, which creates challenges beyond the Corps' control. The experts agreed that probabilistic forecasting techniques—which correct for unknown initial conditions using statistical techniques and provide a range of potential outcomes and their likeliness—could help the Corps manage risks better than their current methods that create one forecast estimate. One of the experts said that probabilistic methods could provide greater benefits, such as higher water supply reliability, increased flood protection and hydropower production, and easier implementation of variable flows to create fish and wildlife habitats. Probabilistic techniques are currently used by New York City to support reservoir releases to manage flood risk and meet water quality goals without adding expensive new filtration equipment. Corps officials said that they have not considered using probabilistic techniques in the Missouri River basin because they are not sure the benefits would outweigh the difficulty of creating the models or explaining the new methods to their stakeholders.
During both the flood and drought, the Corps communicated with Missouri River stakeholders in a variety of ways, which most stakeholders GAO spoke with said were effective. Most stakeholders were generally satisfied with the Corps' communication, saying that the information they received from the Corps was timely and sufficient for their purposes. Most stakeholders had at least one suggestion on how the Corps could improve communication; however, there was little consensus on any one suggestion. A few stakeholders suggested that the Corps hold separate conference calls to discuss sensitive response-related issues. Corps officials said that they would consider this in the future.
Why GAO Did This Study
The Missouri River stretches from western Montana to St. Louis, Missouri. The Corps manages six dams and reservoirs on the river to provide flood control and for other purposes, such as recreation and navigation. The Corps bases reservoir release decisions on the guidance in the Master Manual. In the 2011 flood, the Corps managed the highest runoff volume since 1898, resulting in record reservoir releases. Subsequently, drought occurred in the basin in 2012 and 2013.
GAO was asked to review the Corps' release decisions and communication during the flood and drought. This report examines (1) experts' views on the Corps' release decisions; (2) experts' recommendations to improve the Corps' release decisions; and (3) stakeholders' views on the Corps' communication, as well as any suggested improvements. GAO worked with the National Academy of Sciences to convene a meeting of nine experts to discuss the Corps' data, forecasts, and release decisions. GAO also interviewed 45 Missouri River basin stakeholders, including state and local agencies, among others, to discuss their views on the Corps' communication. The views of stakeholders are not generalizable.
What GAO Recommends
GAO recommends that the Corps evaluate the pros and cons of incorporating new forecasting techniques into its management of the Missouri River reservoirs. The Department of Defense concurred with the recommendation.
For more information, contact Anne-Marie Fennell at (202) 512-3841 or fennella@gao.gov.
Recommendation for Executive Action
Status: Open
Comments: When we confirm what actions the agency has taken in response to this recommendation, we will provide updated information.
Recommendation: To ensure the U.S. Army Corps of Engineers considers a full range of forecasting options to manage the Missouri River mainstem reservoir system, the Secretary of Defense should direct the Secretary of the Army to direct the Chief of Engineers and Commanding General of the U.S. Army Corps of Engineers to evaluate the pros and cons of probabilistic forecasting techniques that could improve the U.S. Army Corps of Engineers' ability to anticipate weather developments, and to evaluate whether forecasting changes are warranted.
Agency Affected: Department of Defense
Explore the full database of GAO's Open Recommendations
»
Oct 31, 2016
-
Oil and Gas Oversight:
Interior Has Taken Steps to Address Staff Hiring, Retention, and Training but Needs a More Evaluative and Collaborative ApproachGAO-16-742: Published: Sep 29, 2016. Publicly Released: Oct 31, 2016.
Oct 24, 2016
-
Superfund Sediment Sites:
EPA Considers Risk Management Principles but Could Clarify Certain ProceduresGAO-16-777: Published: Sep 22, 2016. Publicly Released: Oct 24, 2016.
Oct 17, 2016
-
Water Infrastructure:
Information on Selected Midsize and Large Cities with Declining PopulationsGAO-16-785: Published: Sep 15, 2016. Publicly Released: Oct 17, 2016.
Oct 14, 2016
-
Environmental Protection:
Information on Federal Agencies' Expenditures and Coordination Related to Harmful AlgaeGAO-17-119: Published: Oct 14, 2016. Publicly Released: Oct 14, 2016.
Oct 3, 2016
-
Advanced Technologies:
Strengthened Federal Approach Needed to Help Identify and Mitigate Supply Risks for Critical Raw MaterialsGAO-16-699: Published: Sep 7, 2016. Publicly Released: Oct 3, 2016.
Sep 28, 2016
-
Climate Change:
Information on NOAA's Support for States' Marine Coastal Ecosystem Resilience EffortsGAO-16-834: Published: Sep 28, 2016. Publicly Released: Sep 28, 2016. -
Federal Fisheries Management:
Additional Actions Could Advance Efforts to Incorporate Climate Information into Management DecisionsGAO-16-827: Published: Sep 28, 2016. Publicly Released: Sep 28, 2016.
Aug 15, 2016
-
Grants Management:
EPA Could Improve Certain Monitoring PracticesGAO-16-530: Published: Jul 14, 2016. Publicly Released: Aug 15, 2016.
Jul 26, 2016
-
Army Corps of Engineers:
Additional Steps Needed for Review and Revision of Water Control ManualsGAO-16-685: Published: Jul 26, 2016. Publicly Released: Jul 26, 2016. -
Levee Safety:
Army Corps and FEMA Have Made Little Progress in Carrying Out Required ActivitiesGAO-16-709: Published: Jul 26, 2016. Publicly Released: Jul 26, 2016.
Looking for more? Browse all our products here