During the funding lapse, Federalregister.gov is not being supported. If data feeds are not available from GPO, FederalRegister.gov will not be updated, so please use the official edition of the Federal Register on Govinfo (https://www.govinfo.gov/app/collection/fr). If there is a technical issue with the Public Inspection List, you can view the documents on public inspection at our office in Washington, DC or on archives.gov.

Notice

Notice of Anticipated Schedule of Final Order for the Calcasieu Pass Project: Venture Global Calcasieu Pass, LLC; TransCameron Pipeline, LLC

Document Details

Information about this document as published in the Federal Register.

Document Statistics
Document page views are updated periodically throughout the day and are cumulative counts for this document including its time on Public Inspection. Counts are subject to sampling, reprocessing and revision (up or down) throughout the day.
Published Document

This document has been published in the Federal Register. Use the PDF linked in the document sidebar for the official electronic format.

Start Preamble

On September 4, 2015, Venture Global Calcasieu Pass, LLC filed an application in Docket No. CP15-550-000, pursuant to section 3 of the Natural Gas Act (NGA) and Part 153 of the Commission's regulations, for authorization to site, construct, and operate a new liquefied natural gas (LNG) export terminal and associated facilities along the Calcasieu Ship Channel in Cameron Parish, Start Printed Page 45425Louisiana. On the same day, TransCameron Pipeline, LLC filed an application in Docket No. CP15-551-000 requesting a Certificate of Public Convenience and Necessity pursuant to section 7(c) of the NGA to construct, operate, and maintain certain natural gas pipeline facilities. The combined proposed projects, known as the Calcasieu Pass Project (Project), would liquefy and export about 12 million tons per annum of LNG.

In accordance with Title 41 of the Fixing America's Surface Transportation Act, enacted on December 4, 2015, agencies are to publish completion dates for all federal environmental reviews and authorizations. This notice identifies the Commission's anticipated schedule for issuance of the final order for the Project, which is based on the anticipated date of issuance of the final Environmental Impact Statement. Accordingly, we currently anticipate issuing a final order for the Project no later than:

Issuance of Final Order—January 22, 2019

If a schedule change becomes necessary for the final order, an additional notice will be provided so that interested parties and government agencies are kept informed of the Project's progress.

Start Signature

Dated: August 31, 2018.

Nathaniel J. Davis, Sr.,

Deputy Secretary.

End Signature End Preamble

[FR Doc. 2018-19389 Filed 9-6-18; 8:45 am]