United States Department of Agriculture
Research, Education, and Economics
ARS * CSREES * ERS * NASS
Manual
Title: | Major Facilities Construction |
Number: | 242.4-ARS |
Date: | March 4, 1998 |
Originating Office: | Facilities Division, Facilities Contracts Branch, AFM/ARS |
This Replaces: | Directive and Manual 242.4 dated 5/3/89 |
Distribution: | ARS Headquarters, Areas, Locations |
This Manual provides procedures for planning, designing, and constructing Major facilities modernization or construction programs. |
Table of Contents
1. AUTHORITIES
2. INTRODUCTION
3. ABBREVIATIONS
4. ROLES AND RESPONSIBILITIES
5. PHASES AND STEPS
6. GLOSSARY
7. OTHER REFERENCES
8. ARTICLES ON SIGNIFICANT ISSUES
9. EXHIBITS
NOTE: Highlighted words or phrases are defined in the Glossary.
1. AUTHORITIES
2. INTRODUCTION
The purpose of this manual is to define major facilities construction and outline the
process for managing major facilities construction projects. This manual prescribes the
necessary steps and sequence of the responsibilities of key participants in the process.
A major facilities construction project is one which provides for the construction of a new facility or provides for the major renovation (modernization) of a facility.
A major facilities construction project is generally designated by the following:
The objective of major facilities construction project management is to effectively
develop, coordinate, design and construct fully functional and usable facilities to
fulfill the Agency's mission. To meet this objective, it is ARS policy to follow the
procedures in this manual for the following:
Project Team Titles:
A-E - Architect-Engineer
AOE - Area Office Engineer
ASHM - Area Safety and Health ManagerCIC - Construction Inspection Contractor
CO - Contracting Officer
COR - Contracting Officer's Representative
DR - Design Reviewer
EPM - Engineering Project Manager
LM - Location Monitor
NPSR - National Program Staff Representative
RPM - Research Program Manager
RPMB - Real Property Management Branch
RPR - Research Program Representative
SHEMB - Safety, Health and Environmental Management Branch
Other Titles:
AAO - Area Administrative Office
ABFO - Area Budget and Fiscal Office
AD - Area Director
LAO - Location Administrative Office
LC - Location Coordinator
LD - Laboratory Director
RL - Research Leader
RPO - Real Property Office
Organizational Titles:
ADMIN - Administrator
AITD - Administrative Information and Technology Division, AFM
BPMS - Budget and Program Management Staff, ARS
FD - Facilities Division, AFM
FMD - Financial Management Division, AFM
LS - Legislative Staff, ARS
NPS - National Program Staff, ARS
OBPA - Office of Budget and Program Analysis, USDA
OMB - Office of Management and Budget
There are three distinct areas of project management: 1) Program Management is ensuring
that all program requirements are articulated and included in the project; 2) Contract
Management is being responsible for final development of applicable contract terms and
conditions, ensuring all terms and conditions are contractually enforceable and
enforcement of all contract terms and conditions; and 3) Engineering Project Management is
ensuring all technical and program management issues are addressed and incorporated into
the project. Project management is accomplished by the Project Team.
The Project Team is a diverse group of ARS professionals contributing their skills, talent, and knowledge to plan, design, and construct a research facility in support of the Agency's research mission within a specified budget and schedule. The Project Team is generally established at the time the project requirements are determined. The priority of each member of the Project Team is the accomplishment of the group's common goal--to plan, design, and construct the best facility possible within the time and monetary resources available. In this team relationship, individual members 1) perform different tasks and responsibilities as needed by the group, 2) jointly share responsibility for ensuring team results, 3) develop clear strategies and approaches for achieving their team goal, 4) help each other in achieving their common purpose, and 5) recognize individual achievements with team accomplishments. This approach needs to be followed by all team members on a consistent and effective basis through all phases of an ARS major facilities construction project.
Under each phase of this process, specific responsibilities of the Project Team members are discussed. The members of the Project Team are essential for the successful planning and completion of major facilities construction projects. The members of the Project Team are accountable for the successful and timely execution of the project.
The general roles and responsibilities of each Project Team member are as follows:
Research Program Manager (RPM):
The RPM is usually the Area Director. The RPM is responsible for establishing the research program requirements and selecting the RPR. The RPM retains final authority for decisions on program issues of the project, but this authority is frequently delegated to the RPR. The RPM relies upon various Project Team members for technical engineering and contracting support during the design and construction process. The RPM approves the Functional Statement developed by the RPR and is involved in the development of the Action Plan and Fact Sheet. Any deviations from the Action Plan and Fact Sheet must have the approval of the RPM and be communicated to the Project Team for appropriate action that will ensure that such deviations are reflected in the final contract documents. The RPM has final approval authority of the preliminary Program of Requirements (POR) developed by the Research Program Representative (RPR) and Engineering Project Manager (EPM), ensuring that it is consistent with the Action Plan and Fact Sheet approved by the Administrator. The RPM, together with the RPR, ensure that the proposed and constructed facility satisfies program criteria for a complete and usable facility to support research, and satisfies special requirements of any Cooperator.
The RPM and RPR, with the Facilities Division, approve the final POR and the final design, ensuring that they are consistent with the approved Action Plan and Fact Sheet. The RPM is responsible for compliance with the National Policy Act (NEPA) as it relates to the project (Ref. 7 CFR 520 - USDA-ARS and 40 CFR 1508 - Council of Environmental Quality). The RPM is the fund holder for the project and is responsible for AD-700 requisition approval and issuance. The RPM may delegate authority to approve and issue AD-700's. The RPM should be directly involved in the orientation meeting, provide guidance during development of the POR, concept and final design reviews, as well as major issues related to program changes such as project scope, budget, and schedule. The RPM is accountable to the Administrator, and will keep him/her informed on project developments such as program related problems/decisions, budget issues, political issues, Congressional contacts, and cooperator interface problems/issues.Research Program Representative (RPR):
The RPR represents the RPM. The RPR is selected by the RPM and is usually the Location Coordinator, Research Leader, or Laboratory Director. The RPR prepares the Functional Statement for RPM approval, and prepares and coordinates the project's program requirements with the EPM to formulate a specific statement for the preliminary POR's. The RPR serves as the primary source of program criteria information and any special location criteria, and works closely with the Facilities Division in their preparation of the Action Plan and Fact Sheet. The RPR recommends POR approval to the RPM.
During the design phase, the RPR is a member of the Architect-Engineer (A-E) Evaluation Board for selection of the A-E. The EPM, RPR, and Design Reviewer (DR) ensure that the final design prepared by the A-E complies with the POR and confirm this to the Contracting Officer (CO) for final acceptance of the contract. The RPR coordinates the review of designs among the other researchers and any Cooperators involved in the requirements and provides consolidated review comments on the proposed design to the EPM. The RPR, with other Project Team members, is responsible for reviewing and approving all design submissions with primary emphasis on function, program, and special local issues/interest. The RPR will provide written concurrence with the final design documents. Implementation of research program needs is the major objective of the project.
During the construction phase, the RPR participates in regular construction progress meetings, clarifies established program criteria information, is always consulted for concurrence on construction changes that relate to research program requirements, and is informed of all other changes. The RPR serves as a resource to the Project Team and maintains a liaison with the Construction Inspection Contractor (CIC) during the construction process. All written correspondence with the CIC and contractors must be coordinated with the EPM. The RPR is expected to notify the Contracting Officer's Representative (COR) or the CO if he/she becomes aware of unusual or important circumstances pertinent to the construction project. The RPR has no responsibility for construction inspection or supervision, and is not expected to evaluate contractor performance. The RPR may, however, provide observation comments to the appropriate Team Members to assist in maintaining a quality, timely project. As part of the final inspection, closeout, and acceptance procedures of the contract, the RPR, EPM, and CIC will: 1) verify that the construction contractor has provided key personnel with demonstrations and training on operation of new equipment; 2) participate in the final inspection; and 3) recommend acceptance/rejection of the project.
The RPR, with the Area Office, will arrange for maintenance contracts for facility systems and equipment and the establishment of contracts to install telephone systems, moveable equipment, etc. The RPR will coordinate occupancy of the facility and, if applicable, any ceremonial activities. During the warranty period following completion of the project, the team members will provide the RPR with assistance in solving any contractual or construction problem that may arise.
The RPR is responsible for informing the Project Team members of all communications concerning the project.
National Program Staff Representative (NPSR):
The NPSR is assigned to the project team as the Agency's principal representative to provide information regarding the location's current and projected research mission, program and staffing levels. The NPSR, with the RPR, is responsible for developing the Functional Statement and the preliminary POR.
Engineering Project Manager (EPM):
The EPM is an ARS architect or engineer whose primary responsibility, with other Project Team members, is to ensure Agency needs are met within the approved scope, budget, and schedule. The EPM provides technical oversight and direction and is assigned to the project early in its conception during the time of establishing the project scope and budget. The EPM role will continue throughout the planning, design, and construction phases of the project. The EPM will serve as the lead point of contact and shall disseminate information to the appropriate Project Team members for their action or involvement. It is a responsibility of the EPM to see that all Project Team members are kept advised of the actions, plans, and progress of the project. All Project Team members will keep the EPM advised of their needs and concerns. The EPM also is the lead point of contact between the Project Team and contractors for day-to-day business, working within the terms of the contracts.
During the planning phase, the EPM will coordinate the development and review of the Action Plan and Fact Sheet which summarizes the general scope, budget, and schedule for the project for approval by the Administrator. The EPM will work closely with the RPR in the development of the preliminary POR's for the project. After consulting with other Project Team members, the EPM will prepare a design statement of work (SOW) for the project, and a cost estimate for all professional services. The EPM will chair the A-E Evaluation Board to evaluate and recommend the A-E selection for a particular project.
During the predesign and design phases, the EPM will be designated as the COR and will act as the principal liaison with the A-E firm. The EPM will coordinate A-E visits with the members of the Project Team, conduct design progress meetings and design reviews, review all A-E submittals, and make recommendations to the CO for approval of payment. During the development of the POR, the EPM will ensure that the project complies with the approved Action Plan and Fact Sheet. Should POR requirements change during the course of design, the EPM will ensure, after consultation with the Project Team, that the Action Plan and Fact Sheet is revised and resubmitted for approval by the Administrator. The EPM will take the lead to ensure that all Project Team members, including the A-E and the DR, incorporate all project requirements of the POR and that the documents are in compliance with applicable codes and safety standards. The EPM provides evaluations of A-E performance at the end of the design.
During the construction phase, the EPM may act as the COR. If it is necessary to have a COR on site during construction, the COR may be the AOE or Facility Engineer. The EPM is still responsible for general project management and will work closely with the Project Team to provide such information as needed to support the roles of the other team members.
Area Office Engineer (AOE):
The AOE serves as the technical advisor and resource to the Project Team during the planning, design, and construction phases of all projects within his/her Area. It is the responsibility of the AOE to see that the Area and Location personnel are advised of the actions and status of projects during all phases. The AOE is responsible for coordinating the involvement of Area and Location personnel, such as the Area Safety and Health Manager (ASHM), Location Monitor (LM), Location Administrative Officer (LAO), and others as appropriate. The AOE will assist the Project Team by addressing location specific technical questions, and coordinating the review comments from the Area and location personnel.
During the planning phase, the AOE may serve as a member of the A-E Evaluation Board. The AOE is usually involved in the development and review of the POR, Investigative Report, and SOW for A-E services.
During the design phase, the AOE will review the design submittal with particular emphasis on location specific issues such as utility requirements or unique location requirements.
During the construction phase, the AOE will provide assistance to the Project Team, and is invited to participate in progress meetings, equipment testing, and final inspections. He/she will assist the RPR in arranging maintenance contracts for facility systems and equipment and the establishment of contracts to install telephone systems, moveable equipment, etc. The AOE may serve as the COR on some projects.
Contracting Officer (CO):
The CO is an ARS Contract Specialist and the legal government representative to the contractors, authorized to enter, administer, and terminate contracts on behalf of the Government. The CO is the only member of the Project Team with the authority to obligate government funds or change the contract. The CO may delegate certain contractual authority not affecting the contract scope, performance time, or cost.
The CO is assigned to the project early in its conception and will continue with this role through planning, design, construction, and close out of the project. The CO will assist other members of the Project Team in meeting project goals and objectives. The CO is responsible for ensuring that all planned or existing contractual activities or instruments comply with all applicable laws and regulations, and that all activities are conducted in a fair, impartial, and equitable environment. The CO shall ensure that sufficient funds are identified by the fundholder for obligation.
The CO assists/participates with the Project Team in developing the Action Plan and Fact Sheet. The CO officially designates the A-E Evaluation Board and provides regulatory and procedural guidance to ensure appropriate selection activities and reports. The CO makes final selection approval recommendations, and is the liaison between the A-E Evaluation Board and the selection official.
The CO is responsible for guiding the Project Team through the contractual and business management aspects of the project. The CO is responsible for ensuring that contract performance complies with all contractual provisions including, but not limited to, scope, budget, and schedule. The CO is responsible to ensure adequate contract performance and contract management, monitor contract performance and budgetary events, conduct and participate in project meetings, oversee and conduct negotiations, and other actions necessary to assure adequate progression and protection of the Government's interest.
The CO will request and consider the advice of specialists in audit, law, engineering, and other fields as appropriate, and the advice of the Project Team members. This advice will cover technical, legal, budgetary, reporting, and reprogramming activities.
The CO is responsible for informing Project Team members of all communications concerning the project.
Contracting Officer's Representative (COR):
The COR has a separate and distinct role and is usually the EPM. The assignment as COR is made at the beginning of the contract by an official designation letter from the CO, outlining the responsibilities, authority, and limitations. A copy of this designation letter will be provided to both the contractors and the Project Team members.
The COR is responsible for interpreting technical data in the A-E, construction, and CIC contracts. The COR is responsible for the review of progress and pay requests for these contracts and making acceptance/rejection recommendations to the CO. The COR may approve minor changes to the project that do not affect the program requirements, price, scope, or performance time of the contracts. Such changes will be documented and communicated to the Project Team.
The COR will provide the CO technical and administrative recommendations and documentation regarding changes to terms and conditions of these contracts.
The COR is responsible for discussing and resolving routine contract performance concerns with the A-E, construction, and CIC contractors. The COR is responsible for immediately notifying the CO of all concerns which may affect contract progress, cost, or scope and providing recommendations to the CO for resolution of these matters.
The COR is responsible for ensuring that all team players are kept advised of the actions and progress of the project. The COR is usually the primary point of contact between the Project Team and A-E, construction, and CIC contractors for day-to-day business, working within the terms of their delegation.
The COR shall recognize that the EPM is still the lead point of contract for the Project Team and shall work closely with the EPM to assure that information is provided, as needed, to support the roles of the other Team Members.
Safety, Health, and Environmental Management Branch: (SHEMB)The SHEMB representative is a Facilities Division staff member and is a resource to the Project Team for safety, health and environmental issues during the planning, design, and construction of projects. Throughout the project, the SHEMB representative may be consulted to provide safety, health, and environmental project requirements during the development of the SOW. The SHEMB representative may also be consulted during construction to address safety, health, and environmental matters. The SHEMB representative will participate, as required, in project meetings, and serve as the primary decision maker concerning waiver requests.
Real Property Management Branch: (RPMB)
The representative of RPMB is a Facilities Division staff member responsible for ensuring that all realty interest associated with the project have been completed, including Federal-ownership of the property or lease agreement sufficient to cover the Federal Government's investment in the property. The RPMB representative is responsible for ensuring that easements, right-of-ways, or other land use agreements for roads and utilities in support of the project have been executed. The RPMB representative will review each project to assure compliance with approved Master Plans, National Historic Preservation Act, and Threatened and Endangered Species Act.
Area Safety and Health Manager (ASHM):
The ASHM serves as the safety, health, and environmental advisor and resource to the Project Team during the planning, design, and construction phases on projects within their Area. The ASHM shall be consulted on safety, health, and environmental issues.
During the planning phase, the ASHM may be consulted to provide input on developing the POR and the SOW for design. The ASHM will assist in the preparation of the variances on safety, health, and environmental issues during the planning and site investigation phases. Also, the ASHM may assist in prioritizing safety, health, and environmental items to be incorporated in the SOW for design.
During the design phase, the ASHM may, as assigned, review the design submittal and develop priority for safety, health, and environmental items to be incorporated into the contract documents.
During the construction phase, the ASHM is to ensure all appropriate safety, health, and environmental management related regulations are in place. The ASHM may participate in final inspection and acceptance of the project.
Location Monitor (LM):The LM is an ARS representative at the construction site (or nearby location) formally designated by the CO, who serves as a point of contact for either the A-E, CIC, or the construction contractor to provide information regarding location rules and regulations. The LM designation, which is approved by the AAO, is normally made to the location Facilities Manager/maintenance engineer, LAO, or Location Coordinator. The LM has no responsibility for construction inspection or supervision, and is not expected to evaluate contractor performance. The LM acts an observer and is expected to notify the COR or the CO if he/she becomes aware of unusual or important circumstances pertinent to the contract. Examples of the situations in which the LM may get involved are: 1) designating parking areas for contractor's employees; 2) coordinating use of Government facilities, restrooms, and utilities; 3) coordinating utility shutdowns and connections; and 4) coordinating authorization for contractor to work beyond normal work hours. The LM may participate in the design review stages and construction progress meetings to provide familiarity with the scope of the project and keep abreast of any changes.
Cooperator:
A Cooperator is a State or Federal agency or private organization having a mutual interest in agricultural research that has entered into a valid and legal Memorandum of Understanding, Cooperative Agreement, long-term lease, or similar document demonstrating that a proposed cooperative effort is of benefit to people of the United States. A Cooperator is not always involved in all major construction projects.
Architect Engineer (A-E):The A-E is a private contractor who provides professional services of an architectural- engineering nature with primary emphasis on the design of research facilities, laboratory support facilities, and administrative facilities. The design is performed under the supervision of a registered or licensed professional architect or engineer as required in the State where the project is located. The A-E also provides investigative studies, assists in quality assurance of the construction project, assists in project management, reviews submittals during construction, and provides consultative services as needed. The A-E will contact the EPM for day-to-day business, working within the terms of the contract. Adjustments to the contract will remain under the authority of the CO.
During the planning phase, the A-E finalizes the POR, prepares the Environmental Assessment (EA) and other investigative reports as may be required.
During the design phase, the A-E develops conceptual drawings and provides a preliminary cost estimate. After approval of the conceptual plans, the A-E is tasked with preparation of the final design and working drawings in a manner which incorporates the various adjustments approved through the design review process. Upon approval, various submittals of plans, specifications, and cost estimates are submitted for program, technical, and budget review through completion of final design. The A-E may formally conduct presentations at the various stages of design development and shall provide complete documentation of all such meetings. The A-E keeps the EPM and the CO advised of the status and progress of the project during design.
During the post-design and construction phase of the project, the A-E may be required to participate in the pre-bid, pre-construction, and other meetings. The A-E may be tasked to review and approve shop drawings, material submittals, review and comment on construction contract modifications, and other related activities as directed by the Government. The Government may confirm construction compliance with design intent through a separate inspection contract, or may contract for these services through the design A-E firm.
Design Reviewer (DR):The DR is an independent contractor who provides professional services to review the design submittals prepared by the design A-E. The design reviewer is required to perform services under the supervision of a registered or licensed professional architect or engineer.
The DR is to provide assurance to the government that the design A-E is proceeding in accordance with the project requirements. The DR will review the major design submittals including cost estimates, referencing project requirements cited in the design A-E contract, (i.e. final POR), geo-technical study, applicable Codes and Industry Standards, and good practices of design. The DR will use the ARS Design Review Check List as part of their review, but will be responsible to see that all project requirements are being satisfied.
The DR will be tasked to perform Value Engineering studies for major construction projects, when required. The DR may be tasked to perform the services of a CIC for major construction contracts.
Construction Inspection Contractor (CIC):
The CIC is an independent contractor, generally an A-E firm, whose primary role is to provide Quality Assurance that the construction project is being constructed as designed, and to provide oversight to the Quality Control Plan of the construction contractor. The CIC will consist of a CIC manager that has access to a technical staff that can report to the project site in a timely manner on an as needed basis. For major construction projects, the CIC responsibility may be assigned as a task order to a construction management firm or an A-E firm separate from the design A-E.
The CIC will monitor the Quality Control Plan of the construction contractor and ensure that special test results, material certifications, etc., are obtained as required. In cases where test results or certifications, etc., are not satisfactory, the CIC will take immediate actions to notify the construction contractor's Superintendent and the COR. Keeping the COR informed of these findings will enable corrective actions to be implemented by the CO if necessary.
The CIC is to report to the COR all findings, observations, and communications with the construction contractor. A daily construction log will be maintained by the CIC, and daily "Quality Assurance" reports will be submitted concurrently to the CO and COR. If it is identified that the construction contractor has made deviations from the plans, the CIC will document these observations and bring them to the attention of the construction contractor's Superintendent, the CO, and the COR. Keeping the CO and COR informed will enable corrective actions to be implemented by the CO or other appropriate Project Team members.
The CIC will assist the CO and COR in analyzing and categorizing construction contract changes.
Construction Contractor:The Construction Contractor is an independent firm, hired under Government contract, to provide those professional construction services defined by Federal Acquisition Regulations, Part 36. The specific work to be performed by the Construction Contractor shall be set forth in writing in the specific contract document. The Construction Contractor's team may consist of the Prime Contractor, who has direct contractual relationship with the Government, and various subcontractors and suppliers. No contract exists between the subcontractors, suppliers and the government. The Construction Contractor shall have full responsibility for the construction Project Team including coordination of work, performance, material delivery and storage, permits, licenses, protection of property and all other elements of construction. The Construction Contractor shall maintain a competent Superintendent at the work site at all times during performance of the contract.
The Contractor shall contact the CO or the COR directly on all matters of the contract affecting changes to the contract provisions, contract scope performance time or cost. The CO is the legal Government representative authorized to enter, administer, and terminate contracts, and is the only member of the Project Team with the authority to obligate Government funds or change the contract. The COR is usually the primary point of contact for the Construction Contractor for day-to-day business, working within the terms of the contract.
In order to most effectively accomplish the construction contract, the Government may form a partnership with the Construction Contractor, in a concept known as Partnering. Partnering would strive to draw on strengths of all parties in an effort to achieve a quality project completed within budget, and on schedule. Partnering would be bilateral in make-up and participation is totally voluntary. Partnering is not a contractual agreement, nor does it create any legally enforceable rights or duties to either party.
The Construction Contractor must prepare and maintain a suitable Quality Control Plan. The Construction Contractor shall develop a progress schedule for approval by the CO and adhere to this schedule throughout the contract. In accordance with OSHA regulations, the Construction Contractor will assure that safety is maintained on the job site at all times. Proposed change orders must be coordinated with the CO, COR, and CIC. The Construction Contractor is responsible for maintaining as built documents on the job site to show the construction of a particular structure or work as actually completed under contract. The Construction Contractor shall submit shop drawings as required by the contract documents. The Construction Contractor must attend all scheduled progress meetings and report the progress of the project as required.
During the close out and warranty phase of the contract, the Construction Contractor will in accordance with the contract, prepare operation and maintenance manuals, ensure systems are fully functioning, provide system demonstration to the RPR, COR, and other individuals as designated by the CO. During the warranty phase, the Construction Contractor is required to respond promptly to requests for warranty service, and shall be responsible to coordinate corrective actions as necessary to mediate government concern.
This flowchart depicts each phase and step in the Major Facilities Construction
Process.
PHASE I - PLANNING PHASE II -
DESIGN PHASE III -CONSTRUCTION
PHASE I - PLANNING
This flowchart depicts the approximate timeframes involved in each step of Phase I.
TOTAL
TIMEFRAME: 180 - 360 DAYS
STEP
STEP 1 - PROJECT CONCEPTION AND SCOPE FORMULATION
AD | Identifies need for project through
Annual Resource Management Plan (ARMP) process or directly to NPS.
|
NPSR | Recommends approval of project and
obtains ADMIN approval. Initiates appropriate Congressional contacts.
|
ADMIN | Approves project.
|
AD | Provides leadership in development
of facility and program needs - program mission - number of scientist years (SY's) - types of space and quantity of space - fixed equipment Selects proposed site. Develops preliminary assessment of environmental feasibility. Develops and evaluates alternatives to accomplish mission goals. The AAO/AOE may participate. Consults NPS and FD for recommendations.
|
FD | Assists AD in the development of
preliminary project data, design alternatives, site selection, budget estimate, schedule,
realty, environmental, safety and health, and other construction management issues.
Develops estimate of total project budget cost (planning, design, and
construction). Reviews need for contract services for studies (i.e. site selection,
environmental, estimating).
|
NPSR | REVIEWS/APPROVES preliminary project
data, site selection, and budget estimate.
|
STEP 2 - APPROPRIATION REQUEST AND ALLOCATION OF FUNDS
|
|
FD | Develops/submits Justification
Statement to NPS.
|
NPSR | Initiates appropriation
request through BPMS.
|
BPMS | Submits project and Justification
Statement to OBPA. Incorporates in ARS budget request. Serves as liaison with OBPA and
Congress.
|
OBPA | Approves project and Justification
Statement. Incorporates project as line item in USDA budget request to OMB.
|
OMB | Approves/incorporates USDA budget
request in Federal budget request.
|
Congress | Appropriates funds.
|
OMB | Provides apportionment of
funds through OBPA.
|
BPMS | Provides written notification of
Congressional appropriations. Provides allocation of funds to AD.
|
AAO/ ABFO/ FMD
|
Establishes accounting code/provides
accounts maintenance services for fundholder. |
STEP 3 - PROJECT INITIATION AND DEVELOPMENT
|
|
FD | Consults with NPSR and AD to
establish project team.
|
RPM | RPM is usually the AD. Selects RPR.
|
FD | Prepares written Action Plan/Fact
Sheet (see EXHIBITS 1 and 2) identifying project team members and defining
responsibilities. Obtains ADMIN approval of AP/FS through NPSR. Begins planning by preparing tentative schedule and preliminary budget for design and construction. Coordinates with AOE and advises NPS and RPM of any schedule or budget concerns.
|
NPSR/ RPM
|
Concurs with Action Plan/Fact Sheet. Recommends ADMIN approval. |
ADMIN | Approves Action Plan/Fact Sheet.
|
RPM/ NPSR/ RPR |
Develops project Functional
Statement (see EXHIBIT 2) preliminary Program of Requirements (POR). Consults AITD for telecommunications advice.
|
EPM | Review/refines preliminary POR to
insure consistency between project scope and project budget and schedule. Finalizes
preliminary POR. Consults with AOE, as appropriate.
|
NPSR/ RPM |
APPROVES final preliminary POR |
PHASE II - DESIGN
This flowchart depicts the approximate timeframes involved in each step of Phase II.
TOTAL TIMEFRAME: 20 - 26 MONTHS
*
Performed simultaneously with preceding activity.
STEP 4 - A-E SELECTION PROCESS
Project Team
|
Participates in project Orientation Session. |
RPM | Submits approved preliminary POR to
FD. Submits funded Procurement Request (AD-700) for A-E services to CO.
|
CO | Reviews AD-700. Prepares Procurement
Plan. Appoints A-E Evaluation Board.
|
EPM | Prepares/Submits Statement of Work
(SOW) for A-E services, project Estimated Construction Cost (ECC), and A-E
evaluation criteria to CO.
|
CO | Reviews SOW, ECC, and evaluation
criteria. Publicizes project and evaluation criteria. Advises A-E Evaluation Board of guidelines for integrity and fairness. Receives A-E Qualification Statements (Forms SF-254 and SF-255) from interested A-E firms. Participates in evaluation.
|
Board (EPM, RPR,AOE) |
Evaluates SF-254/SF-255 and submits
preliminary evaluation report of most highly qualified A-E firms (minimum of three) to CO.
|
CO | Reviews preliminary evaluation report
and invites most highly qualified firms for interview process.
|
Board | Interviews A-E firms and evaluates
technical qualifications. Prepares/submits final report with order of preference to CO.
|
CO | Prepares/submits final selection
report.
|
FD | SELECTS A-E.
|
NOTE: | For some Modernization projects, STEP
4 may be eliminated by using FD's pre-established indefinite quantity A-E contractor.
|
STEP 5 - DESIGN
CONTRACT AWARD
|
|
CO | Prepares/issues Request for Proposals
(RFP) for A-E services for predesign and design. Obtains required advice and
reviews (i.e. legal)
|
EPM | Updates SOW for A-E services. Prepares/Submits Government estimate of A-E services fees.
|
RPMB | Finalizes realty acquisition prior to
design award.
|
RPR | Assists in updating SOW, if
necessary.
|
CO | Issues RFP for A-E services and
receives A-E proposal. Obtains EPM, RPM, RPR, AOE, and audit advice on proposal as required. Evaluates proposal and prepares Pre-negotiation Plan.
|
EPM | Provides/coordinates assistance in
technical/cost evaluation of A-E proposal.
|
RPR | May provide program assistance during
evaluation.
|
CO | Conducts negotiations with A-E firm.
|
EPM | Provides and coordinates technical
assistance and price support to CO during negotiations.
|
RPR | May provide program assistance during
negotiations with A-E.
|
RPM | Resolves program discrepancies if
necessary.
|
CO | Notifies LS or others, as required,
prior to award. Notifies/debriefs unsuccessful firms. AWARDS DESIGN CONTRACT
|
STEP 6 - DESIGN REVIEW CONTRACT AWARD
|
|
EPM | Prepares/submits SOW for Design
Review (DR)/Value Engineering (VE).
|
CO | Prepares/issues RFP for DR and VE to
existing Indefinite Quantity A-E Contractor.
|
EPM | Prepares/submits Government Estimate
for DR/VE services to CO.
|
CO | Receives/evaluates DR/VE Proposal.
Obtains EPM, RPM, RPR, AOE, and audit advice.
|
EPM | Provides/coordinates assistance in
technical and cost evaluation of DR/VE proposal.
|
RPR | Provides program guidance if
necessary.
|
CO | Conducts negotiations with DR/VE
firm.
|
EPM | Provides and coordinates technical
assistance and price support to CO during negotiations.
|
RPR | Provides program guidance if
necessary.
|
CO | AWARDS DESIGN REVIEW/VALUE
ENGINEERING CONTRACT.
|
STEP 7 - DESIGN CONTRACT ADMINISTRATION
|
|
CO | Appoints COR (usually EPM). Gives
notice to proceed. Monitors compliance with contract provisions and schedules.
|
A-E | BEGINS PREDESIGN. Finalizes POR.
Completes environmental documentation and other predesign deliverables.
|
EPM/ COR |
Coordinates Project Team and DR A-E
(if necessary) review of predesign submissions. Approves predesign and cost estimate submissions, and design review contractor submissions. Reviews and provides recommendations on proposed changes from a technical and cost standpoint. Coordinates program review of proposed changes. Provides recommendations on contractor payment requests. Provides recommendation to proceed to next phase.
|
RPM | Makes final decision on environmental
documentation. Approves final POR and final predesign. Resolves and approves program
deviations.
|
RPR | Assures final POR complies with
Program. Reviews and comments on predesign submissions. Approves predesign.
|
AAO/ AOE/ ASHM
|
May review and comment on predesign submissions. |
CO | Evaluates and authorizes contract
changes considering technical and program advice. Approves contractor payment requests. Gives notice to proceed to next phase. Monitors compliance with contract provisions and schedules.
|
A-E | BEGINS DESIGN. Makes various stages
of submissions including cost estimates (15%, 35%, 50%, 95%, 100%)
|
DR | BEGINS DESIGN REVIEW. Conducts Value Engineering (VE) Workshop at the 35% design stage.
|
EPM/ COR |
Coordinates Project Team and DR A-E
review of design submissions. Approves A-E design and cost estimate submissions and performance. Approves design review contractor's submissions and performance. Participates in VE Workshop. Coordinates and provides recommendations for incorporation of VE proposals. Reviews and provides recommendations on proposed changes from a technical and cost standpoint. Coordinates program review of proposed changes. Participates in 50% Design Review Board briefing. Provides recommendations on contractor payment requests.
|
RPR | Reviews and comments on design
submissions. Participates in VE Workshop. Reviews and provides recommendations on proposed
changes from a program standpoint. Assures final design complies with POR. Approves final design.
|
RPM | Reviews and comments on design
submissions. May participate in VE Workshop. Resolves and approves program
deviations. Approves final design.
|
AAO/ AOE/ ASHM
|
May review and comment on design
submissions. May participate in VE Workshop. |
CO | Participates in design review and VE
Workshop. Coordinates 50% Design Review Board activities. Evaluates and authorizes contract changes with technical and program advice. Approves contractor payment requests.
|
EPM | Coordinates sign-off and ACCEPTANCE OF FINAL DESIGN documents. |
PHASE III - CONSTRUCTION
This flowchart depicts the approximate timeframes involved in each step of Phase III.
TOTAL
TIMEFRAME: 24 MONTHS
STEP ACTIVITY DAYS
CUMULATIVE (MONTHS)
STEP 8 - CONSTRUCTION
CONTRACT AWARD
|
|
RPM/RPR | Submits funded Procurement Request
(AD-700) for construction services to CO and begins coordination of Ceremonial
Activities.
|
EPM | Forwards approved specifications,
drawings, cost estimate, etc. to CO.
|
CO | Reviews AD-700, specifications,
drawings, and cost estimate. Prepares Procurement Plan. Publicizes project and performs other presolicitation activities. Develops solicitation document and coordinates issuance of solicitation for construction bids.
|
A-E | Issues/distributes solicitation
documents.
|
CO/EPM/ RPR COR/A-E
|
Conducts pre-bid (preproposal)
conference and site visit. AAO/AOE/ASHM may participate. |
CO | Coordinates issuance of solicitation
amendments.
|
EPM | Coordinates and approves technical
aspects of solicitation amendments.
|
RPR | Coordinates and approves program
aspects of solicitation amendments.
|
A-E | Prepares/issues solicitation
amendments. Provides written responses to bidders' questions. Corrects specifications and
drawings as necessary.
|
CO | Receives and evaluates bids.
|
EPM/A-E | Assists in technical aspects of bid
evaluation.
|
RPR | Assists in program aspects of bid
evaluation.
|
CO | Prepares construction contract award
documentation and provides pre-award notifications to LS and others, as required. AWARDS CONSTRUCTION CONTRACT.
|
STEP 9 - CONSTRUCTION PHASE SERVICES CONTRACT AWARDS
|
|
EPM | Prepares/submits SOW for A-E
Construction Management(CM) services and/or Construction Inspection Contractor(CIC)
services to CO.
|
CO | Prepares/issues RFP for A-E CM
services and/or CIC services.
|
EPM | Prepares/submits government estimate
for A-E CM services and/or CIC services to CO.
|
CO | Receives/evaluates A-E CM/CIC
proposal. Obtains EPM, RPM. RPR, AOE, and audit advice, as required.
|
EPM | Provides and coordinates assistance
in technical and cost evaluation of A- E/CM/CIC proposals.
|
RPM/ RPR
|
Provides program guidance if necessary. |
CO | Conducts negotiations with A-E/CIC
firms.
|
EPM | Provides and coordinates technical
assistance and price support to CO during negotiations.
|
RPM/ RPR
|
Provides program guidance if necessary. |
CO | AWARDS A-E CM SERVICES and/or CIC
CONTRACT(S)
|
STEP 10 - CONSTRUCTION CONTRACTS ADMINISTRATION
|
|
CO | Appoints COR (usually EPM) and
Location Monitor(LM). Receives Performance and Payment Bonds from contractor. Gives Notice to Proceed. Participates in Partnering Conference and Quality Coordination Meeting. Conducts Preconstruction Conference. Approves Construction Progress/Payment Schedule.
|
EPM/COR | Participates in Partnering
Conference/Quality Coordination Meeting. Provides technical information at Preconstruction Conference. Coordinates/recommends approval of Construction Progress/Payment Schedule.
|
RPR | Participates in Partnering
Conference and Preconstruction Conference.
|
AAO/ AOE/LM ASHM
|
May participate in Partnering Conference and Preconstruction Conference. |
A-E/ CIC |
Provides recommendations on
Construction Progress/Payment Schedule. Participates in Partnering Conference, Preconstruction Conference, and Quality Coordination Meeting. Acts as quality assurance agent for Government and monitors construction contractor's quality control program. Approves shop drawings, submittals, and schedules. Monitors and coordinates construction progress, reports, meetings, tests, and inspections. Reviews and provides recommendations on proposed changes and costs. Provides recommendations on contractor payment requests.
|
EPM/COR | Monitors construction progress,
quality assurance, and prepares reports. Coordinates review of proposed changes from a technical and cost standpoint and provides recommendations. Coordinates program review of proposed changes. Provides recommendations on contractor(s) payment requests.
|
RPR | Coordinates program changes if
necessary. Concurs in necessity for program change orders. Reviews and provides recommendations on proposed changes from a program standpoint.
|
RPM | Resolves and approves program
deviations if necessary. Obtains ADMIN approval if necessary. |
CO | Monitors compliance with contract
provisions and schedules. Evaluates and authorizes changes with technical and program advice. Negotiates and executes change orders. Approves contractor payments. RESOLVES CONTRACT DISPUTES AND ISSUES FINAL DECISIONS.
|
STEP 11 - FINAL INSPECTIONS
|
|
RPR/ RPM
|
Begins planning and coordination of Ceremonial Activities. |
EPM/COR | Observes commissioning.
Coordinates the conduct of inspections. (Punch-out Inspection, Pre-final Inspection, Final Inspection) AOE/LM may participate.
|
A-E/ CIC |
Participates in all inspections.
Monitors commissioning activities. Reviews and approves contractor's Test and Balance (TAB) reports, Operation and Maintenance (O&M) manuals and training, warranty documentation, and as-built drawings.
|
CO | Obtains written certification from
the construction contractor that project is complete and ready for Final Inspection.
|
EPM/COR A-E/CIC |
Confirms that project is ready for
Final Inspection and coordinates Final Inspection.
|
CO/ EPM/COR A-E/CIC
|
Conducts Final Inspection. |
RPR/LM | Participates in Final Inspection. AAO/AOE/ASHM may participate.
|
A-E/CIC | Records deficiencies during Final
Inspection and provides list of deficiencies to CO as a Punchlist.
|
EPM/COR | Coordinates Punchlist
review and submission to CO.
|
CO | Issues official
Punchlist. Specifies date for completion of Punchlist if different
than contract completion date.
|
CO/ EPM/COR A-E/CIC
|
MONITORS PUNCHLIST COMPLETION |
STEP 12 - ACCEPTANCE, OCCUPANCY, AND FACILITY TURNOVER
|
|
EPM/COR A-E/CIC
|
Notifies CO of Punchlist completion. |
EPM/ COR
|
Coordinates/provides recommendations for acceptance of Facility to CO. |
RPR | Recommends acceptance of Facility.
Coordinates Occupancy of Facility. Arranges for establishment of maintenance contracts for facility systems and equipment. AAO/AOE/ASHM may assist.
|
CO | Upon completion of
Punchlist, officially accepts Facility and authorizes occupancy.
Conducts Post-Acceptance Conference to turnover Facility to RPR in accordance with
established procedures. Provides instructions on Warranty issues to RPR.
|
EPM/COR/ RPR/AOE A-E/CIC
|
Participates in Post-Acceptance Conference. |
RPM/ RPR |
Conducts Ceremonial Activities. OCCUPY FACILITY.
|
STEP 13 - WARRANTY AND CONTRACT CLOSEOUT
|
|
CO | Finalizes outstanding contract
change orders, payments, claims. Monitors warranty performance. Coordinates contract closeout activities in accordance with established procedures.
|
EPM/ COR |
Provides technical recommendations
on final change orders, payments and claims. Coordinates/provides technical advice on
warranty issues. Participates in closeout activities. Prepares Performance Evaluation Reports on contractors.
|
RPR | Provides program recommendations on
final change orders, payments and claims. Notifies EPM of technical problems. Requests
warranty service directly with subcontractors/suppliers in accordance with instructions in
Turnover package. Notifies CO of warranty performance problems.
|
A-E/ CIC |
Provides recommendations on final
change orders, payments and claims. Processes record drawings from contractors as-builts and submits record drawings to the Government.
|
AAO/ AOE
|
Accepts record drawings. |
AAO/ RPO
|
Participates in facilities capitalization in real property records. |
AAO/ ABFO FMD
|
Participates in reconciliation of financial issues. |
CO | Reconciles all contractual and
financial issues. MAKES FINAL PAYMENT.
|
Action Plan/Fact Sheet: A plan developed for major construction projects and approved
by the Administrator. The Action Plan specifies the roles and responsibilities of the
Project Team during the planning, design and construction of the Project. The Action Plan
contains a Fact Sheet which describes the project in terms of scope, budget, and schedule.
See Exhibits 1 and 2.
AD-700, Procurement Request: Form required for requesting procurement of
predesign, design, construction, and related services. Request includes the description of
work, amount of funds, accounting/appropriation information, suggested source of supply,
and signature of fund holder.
A-E Services: Professional services of an architectural or engineering nature
associated with research, development, planning, design, construction, alteration, or
repair of real property. Services are required to be performed by a registered or licensed
architect or engineer as described in the Federal Acquisition Regulation (FAR). See
Article in Section 8.
Allocation: The process of BPMS depositing the appropriated and apportioned
funds into a usable account from which obligations can be made.
Apportionment: Approval by the OMB of the total funds available based on an
appropriation. Funds are apportioned on an annual basis for the full amount available. The
amount of funds apportioned sets the limit on the amount available for allocation.
Appropriation: Statutory authority for ARS to incur obligations and make
payments in specific amounts and for specific projects or purposes. The amount of funds
available for each project becomes the legal dollar limitation for fund control under Anti
deficiency Act regulations.
As-built Drawings: Drawings and specifications which have been marked-up by the
construction contractor to indicate actual changes, deviation, and additions to the
original construction contract documents. As-built Drawings are used to prepare Record
Drawings.
Commissioning: A process involving an extra level of inspection for major building
systems (i.e., HVAC, electrical) to verify and document that these systems will operate as
designed. See Article in Section 8.
Construction: Any construction, alteration, or repair (including dredging,
excavating, and painting) of buildings, structures, or other real property. For purposes
of this definition, the terms buildings, structures, or other real property
include, but are not limited to, improvements of all types, such as bridges, dams, power
plants, highways, parkways, streets, subways, tunnels, sewers, mains, power lines,
cemeteries, pumping stations, railways, airport facilities, terminals, docks, piers,
wharves, lighthouses, buoys, jetties, breakwaters, levees, canals, and channels.
Contingency Funds: Funds set aside prior to or upon award of a construction
contract to use for modifications resulting from changes in the drawings, specifications,
site conditions, etc., or for any required special testing. In the construction of special
purpose facilities or renovations, contingency funds may be equivalent to 7-10 percent
of the construction contract cost. In new facilities, contingency funds may be equivalent
to 5 percent of the construction contract cost. Design contingency funds are
usually budgeted to be 1(one) percent. See Article on Project Budget Elements in
Section 8.
Changes/Change Order Request/Change Order Proposal: Verbal or written request to
CO from construction contractor, A-E, EPM, Program Official, or COR, to modify the terms
of the contract. Only the CO has authority to change or modify the contract.
Design: That phase of facility development activity which transforms Program of
Requirements (POR) into architectural and engineering concepts resulting in a set of
construction contract plans/drawings and specifications. These documents will permit
construction bids to be solicited, received, and evaluated.
Drawings/Plans: A two-dimensional graphic representation of the design,
location, elements, and dimensions of a project, normally seen in a horizontal plane
viewed from above. Also contains details, sections, legends for symbols, abbreviations,
and materials, and special tables called Schedules which identify doors,
windows, hardware, mechanical and electrical equipment, and finishes. Drawings are fully
detailed, accurately dimensioned, and cross-referenced.
Environmental Documentation: The findings and determinations of a project's
potential impacts on the environment, as required by the National Environmental Policy Act
(NEPA). Issuance 230.0 includes a detailed discussion of this subject. The Area Director
is responsible for making and documenting NEPA decisions. The following are the possible
reviews/documents:
Estimated Construction Cost (ECC): All labor, material, and fixed equipment costs
associated with actual onsite construction of the facility. This does not include
Contingency Fund costs.
Fixed Equipment: Permanently installed and affixed equipment such as air
conditioning equipment, fume hoods, laboratory casework, water coolers, cage washers, and
similar equipment which is normally capitalized as part of the building or structure.
These items are normally part of the construction contract. (Does not normally include
portable scientific apparatus.) See Article on Appropriate Use of Buildings and Facilities
Funds in Section 8.
Functional Statement: A detailed description of the activities to be performed
at a facility. This includes an organization breakdown, program objectives, summary of
functions and major scientific equipment to be used by each organizational element,
relationships among the various organizational elements, location and siting criteria,
exposure to the public and other groups, logistical needs, staffing, and any other factors
which will influence facility design. See Exhibit 3.
Gross Square Footage (gsf): The total area of a building, including all
operating floors, stairways, corridors, mechanical space, basement space, and covered
outdoor space, used in cost estimating. See Article on Developing the Project Scope in
Section 8.
Inspection: A process in which the Government, an Architect-Engineer firm, CIC,
and/or others inspect work of the construction contractor(s); inspect, test, and approve
construction materials and equipment; and/or perform other designated services for the CO.
See Article on Construction Monitoring, Inspection, and Reporting in Section 8.
Justification Statement: Part of the Budget Explanatory Notes, in support of the
Budget Estimates, sent to the House and Senate Appropriations Committees, describing
requests for construction funds. The amount of funds for each construction project is
identified for land acquisition, planning and design, and construction with a description
of the types of research to be conducted, the reasons the research is essential,
identification of the research objectives to be achieved, gross square footage
requirements, and the nature, condition, and location of any facilities currently used to
perform similar research.
Life Cycle Cost Analysis: The total cost of owning, operating, and maintaining a
building over the length of its useful life, including its fuel and energy costs,
determined on the basis of a systematic evaluation and comparison of alternative building
systems. See Article on Value Engineering in Section 8.
Mission: The broad research goals to be attained as a result of the research
program planned to be performed within the facility.
Orientation: A Project Team meeting held at the beginning of a project to
educate the EPM and CO about the RPR's program and research needs; and, the RPR about the
ARS design and construction contracting process. See Article on Project Team Orientation
in Section 8.
Partnering: A process between the Project Team and the Construction Contractor
Team, structured to establish a mutually-developed strategy of communication and
commitment toward the successful completion of the project. See Article in Section 8.
Planning: General term for the project phase which includes development of the
preliminary Program of Requirements (POR), design criteria, budget estimates, site
selection, and general preliminary project design.
Prebid/Preproposal Conference: A forum prior to bidding in which the Contracting
Officer and other interested Agency personnel explain to potential bidders the nature of
the work and known special conditions. The Design A-E assists in interpreting the plans
and specifications. (This meeting is known as preproposal conference in negotiated
procurement.)
Preconstruction Conference: A forum after contract award, in which the
Contracting Officer, other Project Team members, and the construction contractor meet to
discuss mobilization, construction scheduling, authorities of Government personnel,
progress reports, quality assurance and inspection procedures, payroll submissions,
payment procedures, Equal Employment Opportunity responsibilities, change order
procedures, etc.
Predesign: The phase of planning and design in which required preliminary
activities such as POR finalization, investigative reports, preliminary surveys (i.e.
site, asbestos, environmental) and preliminary cost estimates are developed and approved.
Procurement Plan: A format identifying milestones of the acquisition process and
projected dates.
Procurement Request: See AD-700.
Program of Requirements (POR): A detailed document describing the
characteristics that a proposed facility must contain to meet the needs of the occupying
organization. The POR generally includes: 1) the Functional Statement which provides a
basis for review and justification of the program by the Agency, Department, OMB, and
Congress; and 2), the facility space planning data and budget estimates.
Project Budget Cost: All costs associated with project implementation from
planning, pre-design, design, design review, bid phase, inspection, construction,
construction management. These costs also include environmental/archeological impact
costs, site acquisition and clearance costs, cost for utility and other agreements, other
technical services, contingency fund reserved for unforeseen conditions, and the estimated
cost of construction, all adjusted for inflation and escalated for their respective dates
of obligation. See Article on Project Budget Elements in Section 8.
Punch List: A list of defects and omissions officially developed during
inspections which require completion or correction by the construction contractor.
Quality Assurance (QA): Government Quality Assurance is the review, inspection
and testing of the Contractor's Quality Control Plan and its execution. See Article in
Section 8.
Quality Control (QC): Contractor Quality Control is a formal plan to ensure the
required standards of construction quality are met within the specified time and budget,
through planning and inspecting. See Article in Section 8.
Record Drawings: The construction contractor's marked-up (As-built)
drawings are submitted to the A-E after final inspection for verification and the A-E
transcribes all changes onto reproducible materials and submits the documents to the
Government as the permanent record.
Specifications: Written descriptions of a technical nature of materials,
equipment, construction systems, standards, and workmanship. The Naval Facilities (NAVFAC)
Guide Specification has been adopted for use in ARS construction projects.
Statement of Work (SOW): A translation of the POR into architectural and
engineering technical requirements which serves as the scope of the design contract and
provides sufficient information for an A-E firm to develop a proposed fee for services.
Design criteria may also be referred to as the SOW.
Value Engineering (VE): An engineering analysis of the functions of a program,
project, or system directed at improving quality, performance and costs. A VE workshop is
generally conducted at the 35% design stage or earlier. See Article in Section 8.
Warranty: A legally enforceable guarantee of the assurance of the duration or
quality of a product or the work performed. Warranty periods are usually for a period of 1
(one) year. Specialty items may have a longer warranty period (i.e., roofs, HVAC
components, etc.) See Article on Facility Turnover in Section 8.
Issuance 134.2 - ARS Energy Management Plan
Issuance 230.0 - Safety, Health, and Environmental Management Program
(includes environmental documentation)
Issuance 242.1 - Construction Project Design Manual (includes seismic considerations)
Issuance 242.5 - Economic Analysis and Decision for ARS Facility Modernization
Issuance 242.6 - Metric Conversion
Issuance 242.7 - Value Engineering
36 CFR 1190 - Minimum Guidelines and Requirements For Accessible Design
There are many important requirements, regulations, policies, and procedures applicable
to major facility design and construction projects. The following articles briefly
describe some of these significant issues.
o Project Budget Elements
o Communication of Major Project Budget Estimates
o Appropriate Use of Buildings and Facilities Funds
o Usable Facility
o Realty Interest
o Selection of RPR
o Developing the Project Scope
o Cooperator/Lessor Participation
o Ceremonial Activities and Informing Congress
o Project Team Orientation
o Telecommunications
o A-E Selection
o Review of A-E Design Submittals
o 15% Design Submission (Conceptual Presentation)
o Value Engineering
o Partnering
o Construction Monitoring, Inspection, and Reporting
o Quality Control
o Quality Assurance
o Commissioning
o Use of Facility Prior to Completion
o Facility Turnover
o Contract Closeout
PROJECT BUDGET ELEMENTS
There are various expenditures necessary for the planning, design, and construction of
a major facility construction project. These expenditures include costs for A-E
services, construction of the building, including fixed equipment, and contingency
items (i.e. changes due to unplanned or unforeseen issues or conditions.) The following
table depicts typical project budget elements, percentages, and estimated costs for a new
construction project. Estimated costs for a renovation project are the same, except for
Construction Contingency, which will be 7� percent (rather than
5 percent); and, the ECC reduced accordingly. Estimated costs will vary from project to
project.
$10,000,000 Appropriation for Planning /Design/Construction
Planning & Design Costs | % of ECC |
Amount (+/-10%) |
A-E Services: | ||
--POR Finalization | 2 | $160,000 |
--Design | 6 | 480,000 |
--Design Review | 2 | 160,000 |
--Design Contingency | 1 | 80,000 |
--Miscellaneous (Value Engineering, Environmental Assessment, Renderings, etc.)
|
1 | 80,000 |
TOTAL Planning & Design Costs
|
12% | $ 960,000 |
Construction Costs | ||
--Construction of Facility And Fixed Equipment
|
ECC | $ 8,080,000 |
Other Construction Costs | ||
--A-E Bid Phase Services | 1 | $ 80,000 |
--A-E Inspection Services | 3 | 240,000 |
--A-E Submittal/Documentation | 3 | 240,000 |
--Construction Contingency
|
5 | 400,000 |
Subtotal Other Construction Costs | 12% | 960,000 |
TOTAL Construction Costs
|
$ 9,040,000 | |
TOTAL BUDGET (Appropriation)
|
$ 10,000,000 |
COMMUNICATION OF MAJOR PROJECT BUDGET ESTIMATES
Project Budget Estimates are developed in many different ways. The development can be
(1) a bottom-up estimate that is based on detailed project scope information;
(2) top down (Congressional or Agency sponsored limitation); or, (3) a
projection that is generated on short notice, usually based on square foot only
information, with less than adequate information and analysis. The optimum method of
developing a Project Budget Estimate is by conducting a detailed architectural-engineering
study addressing programmatic, infrastructure, and environmental needs. Whether or not a
project is constructed at one time or in phases impacts the estimate. Project Budget
Estimates, no matter what the source, generally require annual update to reflect inflation
and other industry and economic conditions. Project Budget Estimates are good for one
year.
The following are the Key Communicators:
Administrator National Program Staff Location research personnel Facilities Division |
Associate Administrator Budget Program Management Staff Area Directors Location/Area Administrative Officers |
The following is the Process for Communication of Project Budget Estimates:
Activity | Responsibility |
|
NPS, AD, AAO, LAO, FD FD ADMIN BPMS BPMS FD |
APPROPRIATE USE OF BUILDINGS AND FACILITIES FUNDS
Buildings and Facilities Funds appropriated for Major Facility Construction Projects can
be used to fund all real property and fixed equipment items necessary to make the building
a usable facility.
Buildings and Facilities Funds cannot be used to fund moveable or unaffixed items
that are usually accounted for as personal property, rather than real property.
Unless otherwise specified, the following are examples of items which cannot be funded
from a Buildings and Facilities Account:
ADP equipment filing cabinets and portable safes food service equipment (portable) laboratory equipment (portable) safety equipment (portable) shop equipment (portable) scientific equipment (portable) |
systems furniture furnishings, including rugs furniture (chairs, tables, desks, partitions, clocks) photographic equipment (portable) training equipment (portable) office machines |
USABLE FACILITY
A new or renovated facility must be a stand alone structure which is detached from
buildings not owned by the Agency. The facility must have sufficient usable space to
permit the Agency to conduct the research program defined in the functional statement. The
completed facility should include the construction of the necessary buildings and other
structures needed to support the planned research.
Laboratories, offices, and other buildings and structures must contain, as part of the
design and construction plans, the complete installation of the necessary and fully
operational utilities (i.e., heat, ventilation, air-conditioning, light, power,
telecommunications, safety and health systems). The rooms in such structures must contain
the necessary fixed equipment, cabinets, benches, and other items which are permanently
attached to the building and capitalized as part of the building or structure. Special
purpose space and utility rooms must contain the necessary safety devices, utility
systems, and other fixed equipment necessary for the facility's satisfactory operations.
Support structures and buildings, such as greenhouses, headhouses, repair shops, animal
facilities, and storage facilities must be completed to the extent that requirements are
known during the planning stages (including heating, ventilation, air-conditioning, safety
considerations, provision for appropriate water, gas, and other utility hookups).
The facility must include all necessary sidewalks, roads, vehicle parking spaces,
and landscaping.
REALTY INTEREST
A contract for design of a major facility cannot be awarded until ARS has a sufficient
realty interest in the land upon which the facility will be built. Realty interests are in
the form of fee simple ownership, long-term lease agreements, and easements (for utilities
and road construction).
The Administrator is the Government official delegated the authority to execute the
agreements to acquire realty interests. FD, RPMB, is responsible for determining the type
of estate to be acquired and negotiating and preparing the real estate agreements.
The real estate acquisition process can be a complex and lengthy process involving 9-12
months. Therefore, the AD/RPM/RPR should contact FD/RPMB for their involvement early in
the Planning Phase. Real estate acquisition includes the following activities:
SELECTION OF RPR
The RPR performs a key role in the development and oversight of each major design and
construction project. RPR assignments can require a major portion of a research
scientist's time for a period of several years.
In order to maintain continuity and enhance Project Team communications, it is
recommended that the responsible Research Leader (RL), Laboratory Director (LD), or
Location Coordinator (LC) selected for the RPR assignment be an individual who will be
available throughout the duration of the project; understands that the project will
require a major portion of their time and effort; and, possesses a broad understanding of
the scope of the research program.
DEVELOPING THE PROJECT SCOPE
Past experiences in administering major facility construction programs reveal a general
trend in the relationship between authorized Scientific Year (SY) count and the gross
square footage of floor space in an ARS research facility. Based on this information,
the ADMIN has approved the usage of a general formula for purposes of determining the size
of a research facility. FD applies this formula when developing project scope and budget
estimates during the planning phase and during the development of the Action Plan/Fact
Sheet.
General Formula for Developing the Project Scope:
Number of SY x 3,000 gross square feet (gsf) = Size of Facility
Exemptions: Research Facilities with particularly unique characteristics may be exempt
from this formula. Headhouse (HH) and Greenhouse (GH) space are exempt from this formula.
Historically, the general square footage per SY ranges from 2500 gsf per SY to 3500 gsf
per SY (excluding HH/GH space.) Variables such as project locality, availability of
utilities, diversity of research functions, circulation and support space may
significantly impact this
general square foot estimate; and thus, the overall project scope and budget. Ultimately,
the final project size and scope must be based on the amount of funds available to
construct the facility.
COOPERATOR/LESSOR PARTICIPATION
The Cooperator/Lessor may be interested or involved in the following issues:
CEREMONIAL ACTIVITIES AND INFORMING CONGRESS
Ceremonial activities are often considered appropriate for major projects, especially
when specific Congressional appropriations are involved. The types of activities that have
been conducted are:
- Groundbreaking ceremonies - usually occur at the beginning of the construction
contract.
- Dedications - usually occur upon completion and acceptance of the construction
contract.
The AD, RPM, RPR, and/or Location Leader is responsible for coordinating these
activities with the ADMINISTRATOR and Under Secretary, REE, and the Legislative Staff
(LS). The LS coordinates appropriate Congressional participation. It is imperative that
discussions be initiated with the LS sufficiently in advance of the ceremonial activity to
obtain their recommendations and coordination of Congressional attendance.
The planning time for Ceremonial Activities involving Congressional participation is a minimum of 60 days to assure coordination with the Congressional calendar. Specific dates for events cannot be predetermined by ARS. The availability of Congressional participants is the determining factor in the establishment of the date of the ceremonial activity.
PROJECT TEAM ORIENTATION
The Project Team will meet at the commencement of the project to become familiar with
each others' needs, goals, roles and responsibilities, research program, and the steps in
the planning, design and construction contracting process.
The Project Team orientation meeting was established to promote Team communications and
understandings and share knowledges and concerns about the research program, the Federal
acquisition process, the design and construction industry, and to establish mutual and
common project goals.
TELECOMMUNICATIONS
Identifying the Facility's telecommunication requirements begins early in the Planning
Phase. Coordination among the RPR, AAO, and AITD will ensure that telecommunications needs
are identified for inclusion in the Design contract. Telecommunications costs are part of
the Project Budget. There are two basic options:
Option 1: The Design A-E can design the entire telecommunications system and the
construction contractor can be responsible for the entire installation, from cable trays
to cabling, from purchase to installation of devices. The construction contractor will be
responsible for coordinating the purchase of the complete telecommunication system and
equipment and the installation.
Option 2: The Design A-E can design the distribution system allowing for a variety of
telecommunications systems installations. The construction contractor will install the
distribution system to the extent designed. The AAO will purchase and install the
telecommunications systems and equipment. This can normally be obtained from GSA schedule.
Coordination with the construction contractor will be needed to accommodate the
installation of telecommunication equipment by others and tie-in to the construction
contractor-installed distribution system.
A-E SELECTION
Public Law 92-582, the Brooks Act, is the Federal Government policy for procuring
architectural and engineering services. It allows the Government to evaluate the
qualifications and performance of A-E firms and conduct discussions to select the firm
deemed to be most highly qualified. The Agency is then authorized to negotiate a contract
with the most highly qualified A-E firm for a compensation determined fair and reasonable
by the Government, in accordance with the procedures in the Federal Acquisition
Regulation.
REVIEW OF A-E DESIGN SUBMITTALS
It is critical for the Government to assure that completed A-E designs are
constructable, designed within the project budget, meet all applicable codes
and standards, i.e., Life Safety Codes, Occupational Safety & Health Administration
Standards, result in a usable facility, and contain minimal design
deficiencies. These items are reviewed by the Design Review A-E. In addition, FD conducts
a 50% Design Review Board, in which the Project Team briefs FD management to confirm that
the Design A-E's construction cost estimate at the 50% Design submission conforms to the
specified construction budget and scope.
15 PERCENT DESIGN SUBMITTAL (CONCEPTUAL PRESENTATION)
During this important and interesting step, the Design A-E makes formal presentations
of at least 3 design schemes which successfully integrate interior and exterior design
elements with program function. Each conceptual presentation consists of:
The decision made as a result of the conceptual presentation defines the direction in
which the A-E will proceed to further develop the design within required budgetary,
technical, and programmatic restraints in a functional, aesthetic, and cost effective
manner.
VALUE ENGINEERING
Value Engineering (VE) is a systematic, functional, and creative analysis of a
construction requirement to achieve the best functional combination of cost, reliability,
and performance, over the life-cycle of products, systems, equipment, facilities,
services, and supplies. VE is performed by a team of experienced multi-disciplinary
professionals and subject specialists, whose discipline and expertise match that required
by the construction project. VE is usually performed by the Design Review A-E. The VE
Workshop occurs at the 35% Design Stage or earlier. This process includes the following
five phases:
PARTNERING
Partnering is the creation of a relationship between the Government and its Contractors
that promotes achievement of mutually beneficial goals. While the contract establishes the
legal relationship, Partnering is a process structured to establish working relationships
among the various parties through mutually-developed strategy of commitment and
communication. Partnering creates an environment where trust and teamwork help to resolve
project problems, prevent disputes, foster open communication and cooperation, and
facilitate the successful completion of the project. A Conference is usually conducted at
the commencement of the construction contract to introduce the Project Team and their
relative Roles and Responsibilities and create a cooperative attitude in completing the
project. To create this attitude, each party seeks to understand the roles,
responsibilities, goals, objectives, and needs of the other. This Conference concludes
with a Partnering Agreement or Charter which embodies the commitment to communicate in all
matters affecting the project and resolve conflicts at the lowest level.
CONSTRUCTION MONITORING, INSPECTION, AND REPORTING
The following personnel are involved with the construction activity and provide varying
degrees of coordination as described in the Roles and Responsibilities.
Engineering Project Manager (EPM) - The EPM provides technical oversight and general
project management.
Contracting Officer's Representative (COR) - The COR monitors and reports on the
performance of the construction contractor and/or the A-E contractors. The EPM is often
the COR. The AOE or Facility Engineer may also be the COR.
Construction Inspection Contractor (CIC) - Inspection of ARS construction projects is
usually accomplished by an on-site A-E contractor. Full-time inspection is usually
required for jobs of the size and complexity of major construction. This monitoring and
reporting service can be provided by the Design A-E, Design Review A-E, or a separate A-E
firm.
Construction Management (CM) Services - Construction management services include shop
drawing/submittal review, professional testing services, clarifications of design intent,
change order proposal review, or other professional advice. This service is usually
provided by the Design A-E.
Location Monitor (LM) - The LM serves as a point of contact for either the A-E, CIC, CM, or construction contractor to provide information regarding Location rules and regulations. The LM is normally the location Facilities Manager/maintenance engineer, LAO, or LC.
QUALITY CONTROL
Quality Control (QC) is the Construction Contractor's system for managing, controlling,
and documenting activities to produce construction complying with contract documents.
The quality control system consists of plans, procedures, and organization necessary to
manage all construction operations (onsite and offsite) and is keyed to the proposed
construction sequence. The system covers at least 3 phases for all definable tasks: 1)
Preparatory Phase - planning before construction begins; 2) Initial Phase - as the
construction begins; and 3) Follow-up Phase - daily checks while work is being performed.
Quality Control vs. Inspection: The construction contractor is responsible for
controlling the quality and inspecting the work. Quality Control is a continual system of
planning future activities to prevent deficiencies. Inspection is the process of examining
on-going or completed work to ensure the work complies with the contract and is not
deficient. Inspection is on-going, or after-the fact, while control is
preventive.
QUALITY ASSURANCE
Government Quality Assurance (QA) is the Government's system for protecting its
interests during the construction of the project. Through reviews, inspections, and tests,
he Government assures that the Contractor's Quality Control system is working effectively,
and that the end product complies with the quality established by the contract. The
Government is responsible for establishing and specifying standards of quality in the
contract, confirming the adequacy of contractor's quality control system, performing
specified tests and inspections and reporting deficiencies, determining reported
deficiencies have been corrected, and assuring timely completion. Quality Assurance during
the construction phase is usually performed by the CIC or Design A-E.
COMMISSIONING
Commissioning is a process to assure that the building systems have been constructed
and/or installed in conformance with the contract documents, comply with design intent,
and that location maintenance personnel are trained in the operation and maintenance of
the system. Commissioning is an extra level of inspection, specifically designed to ensure
that sophisticated building systems are properly installed and operating. The primary
emphasis of commissioning is on HVAC systems, but can include electrical and/or special
piping systems. The design A-E develops the commissioning specification and cost estimate.
The construction contractor is responsible for performing the actual commissioning. (test
and balance, system start-up, adjustments, etc.) The commissioning exercise is generally
conducted with the design A-E's commissioning team to verify that the building is properly
commissioned.
USE OF FACILITY PRIOR TO COMPLETION
There is a legal contractual right to occupy and use a facility before all construction
work is completed and before the facility is fully accepted and fully paid for by ARS. The
Contracting Officer (CO) must approve and authorize this activity.
Use and occupancy can occur only if the facility is substantially complete.
Substantially complete means the space can be occupied and utilized for its
intended purpose. Authorization will occur only if the following conditions are met:
FACILITY TURNOVER
During the Post Acceptance Conference the CO informs the RPR of the following:
The CO provides the RPR with a Turnover package containing the following
information:
CONTRACT CLOSEOUT
The purpose of the contract closeout process is to assure accomplishment of the
following in accordance with Federal Acquisition Regulation:
EXHIBIT 1
SUBJECT: Action Plan for the
New ARS Research Center,
Anywhere, USA
TO: Area Director, Appropriate Area
Research Program Manager
FROM: Administrator, ARS
In accordance with Directives 242.4 and 242.5, the Facilities Division has developed,
and I have approved, the enclosed Action Plan and associated Fact Sheet.
The primary members of the project team are:
Research Program Manager (RPM):
Research Program Representative (RPR):
National Program Staff Representative (NPSR):
Engineering Project Manager (EPM):
Contracting Officer (CO):
Contracting Officer Representative (COR):
Area Safety And Health Manager (ASHM):
Area Office Engineer (AOE):
Architect-Engineer (A-E):
Design Reviewer (DR): To Be Determined (TBD)
Construction Inspection Contractor (CIC): TBD
Construction Contractor: TBD
The Facilities Division is responsible for coordinating this effort through the team
approach by interacting with the National Program Staff, Research Program Manager,
Research Program Representative, the Architect-Engineer, and the Contractors.
Should you require additional information concerning the Action Plan or Fact Sheet,
please contact Director, Facilities Division.
2 Enclosures
Action Plan
Fact Sheet
ACTION PLAN
(New ARS Research
Center, Anywhere, USA)
There are three distinct areas of project management. Program Management is to ensure
all program requirements are articulated and included in the project. Contract Management
is responsible for enforcing terms and conditions of the contract. Engineering Project
Management ensures all technical and program management issues are addressed and
incorporated into the project.
The Project Team is a diverse group of ARS professionals contributing their skills,
talent, and knowledge to plan, design, and construct a research facility in support of the
Agency research mission within a specified budget and schedule. The Project Team is
generally established at the time the project requirements are determined. The priority of
each member of the Project Team must be the accomplishment of the group's common goal--to
plan, design, and construct the best facility possible within the time and monetary
resources available. In this team relationship, individual members (1) perform different
tasks and responsibilities as needed by the group,(2) jointly share responsibility for
ensuring team results, (3) develop clear strategies and approaches for achieving their
team goal, (4) help each other in achieving their common purpose, and (5) recognize
individual achievements within team accomplishments. This approach needs to be followed by
all team members on a consistent and effective basis through all phases of an ARS
facilities project.
Under each phase of this process, specific responsibilities of the Project Team members
are discussed. Their involvement is essential for the successful planning and completion
of major facilities construction projects. They are accountable for the successful and
timely execution of the project. The general roles and responsibilities of each Project
Team members are:
RESEARCH PROGRAM MANAGER (RPM):
The RPM is the Customer and is usually the Area Director. The RPM is
responsible for establishing the research program requirements and selecting the Research
Program Representative (RPR). The RPM retains final authority for decisions on program
issues of the project, but this authority is frequently delegated to the RPR. The RPM
relies upon various Project Team members for technical engineering and contracting support
during the design and construction process. The RPM approves the Functional Statement
developed by the RPR and is involved in the development of the Action Plan and Fact Sheet.
Any deviations from the Action Plan and Fact Sheet must have the approval of the RPM
and be communicated to the Government Project Team for appropriate action that will ensure
that such deviations are reflected in the final contract documents. The RPM has final
approval authority of the preliminary Program of Requirements (POR) developed by the RPR
and Engineering Project Manager (EPM), ensuring that it is consistent with the Action Plan
and Fact Sheet approved by the Administrator. The RPM, together with the RPR, ensure that
the proposed and constructed facility satisfies program criteria for a complete and usable
facility to support research, and satisfies special requirements of any Cooperator.
The RPM and RPR approve the final POR and, with the Facilities Division, the final
design, ensuring that they are consistent with the approved Action Plan and Fact Sheet.
The RPM is responsible for compliance with the National Environmental Policy Act (NEPA) as
it relates to the project (Ref. 7 CFR 520 -USDA-ARS and 40 CFR 1508 -Council of
Environmental Quality). The RPM is the fund holder for the project and is responsible for
AD-700 requisition approval and issuance. The RPM may delegate authority to approve and
issue AD-700's. The RPM should be directly involved in the orientation meeting, provide
guidance during development of the POR, concept and final design reviews, as well as major
issues related to program changes such as project scope, budget, and schedule. The RPM is
accountable to the Administrator, and will keep him/her informed on project developments
such as program-related problems/decisions, budget issues, political issues, congressional
contacts, and cooperator interface problems/issues.
RESEARCH PROGRAM REPRESENTATIVE (RPR):
The RPR represents the RPM. The RPR is selected by the RPM and is usually the
Location Coordinator, Research Leader, or Laboratory Director. The RPR prepares Functional
Statement for RPM approval, and prepares and coordinates the project's program
requirements with the EPM to formulate a specific statement for the preliminary POR's. The
RPR serves as the primary source of program criteria information and any special location
criteria, and works closely with the Facilities Division in their preparation of the
Action Plan and Fact Sheet. The RPR recommends POR approval to the RPM.
During the design phase, the RPR is a member of the Architect-Engineer Evaluation Board
for selection of the Architect-Engineer (A-E). The EPM, RPR, and Design Reviewer (DR)
ensure that the final design prepared by the A-E complies with the POR and confirms this
to the Contracting Officer (CO) for final acceptance of the contract. The RPR coordinates
the review of designs among the other researchers and any Cooperators involved in the
requirements and provides consolidated review comments on the proposed design to the EPM.
The RPR, with other Project Team members, is responsible for reviewing and approving all
design submissions with primary emphasis on function, program, and special local
issues/interest. The RPR will provide written concurrence with the final design documents.
Implementation of research program needs is the major objective of the project.
During the construction phase, the RPR participates in regular construction progress
meetings, clarifies established program criteria information, is always consulted for
concurrence on construction changes that relate to research program requirements, and is
informed of all other changes. The RPR serves as a resource to the Project Team and
maintains a liaison with the Construction Inspection Contractor (CIC) during the
construction process. All written correspondence with the CIC and contractors must
be coordinated with the EPM. The RPR is expected to notify the Contracting Officer's
Representative (COR) or the CO if he/she becomes aware of unusual or important
circumstances pertinent to the construction project. The RPR has no responsibility for
construction inspection or supervision, and is not expected to evaluate contractor
performance. The RPR may, however, provide observation comments to the appropriate Team
Members to assist in maintaining a quality, timely project. As part of the final
inspection, closeout, and acceptance procedures of the contract, the RPR, EPM, and CIC
will: (1) verify that the construction contractor has provided key personnel with
demonstrations and training on operation of new equipment; (2) participate in the final
inspection; and (3) recommend acceptance/rejection of the project. The RPR, with the Area
Office, will arrange for maintenance contracts for facility systems and equipment and the
establishment of contracts to install telephone systems, moveable equipment, etc. The RPR
will coordinate occupancy of the facility and, if applicable, any ceremonial activities.
During the warranty period following completion of the project, the team members will
provide the RPR with assistance in solving any contractual or construction problem that
may arise.
The RPR is responsible for informing the Project Team members of all communications
concerning the project.
NATIONAL PROGRAM STAFF REPRESENTATIVE (NPSR):
The NPSR is assigned to the Project Team as the Agency's principal representative
to provide information regarding the location's current and projected research mission,
program, and staffing levels. The NPSR, with the RPR, is responsible for developing the
Functional Statement and the preliminary POR.
ENGINEERING PROJECT MANAGER (EPM):
The EPM is an ARS Architect or Engineer whose primary responsibility, with other
Project Team members, is to ensure Agency needs are met within the approved scope, budget,
and schedule. The EPM provides technical oversight and direction and is assigned to the
project early in its conception during the time of establishing the project scope and
budget. The EPM role will continue throughout the planning, design, and construction
phases of the project. The EPM will serve as the lead point of contact and shall
disseminate information to the appropriate Project Team members for their action or
involvement. It is the responsibility of the EPM to see that all Project Team members are
kept advised of the actions, plans, and progress of the project. All Project Team members
will keep the EPM advised of their needs and concerns. The EPM also is the lead point of
contact between the Project Team and contractors for day-to-day business, working within
the terms of the contracts.
During the planning phase, the EPM will coordinate the development and review of the
Action Plan and Fact Sheet which summarizes the general scope, budget, and schedule for
the project for approval by the Administrator. The EPM will work closely with
the RPR in the development of the preliminary POR's for the project. After consulting with
other Project Team members, the EPM will prepare a design Statement of Work
(SOW) for the project, and a cost estimate for all professional services. The EPM will
chair the A-E Evaluation Board to evaluate and recommend the A-E selection for a
particular project.
During the predesign and design phases, the EPM will be designated as the COR and will
act as the principal liaison with the A-E firm. The EPM will coordinate A-E visits with
the members of the Project Team, conduct design progress meetings and design reviews,
review all A-E submittals, and make recommendations to the CO for approval of payment.
During the development of the POR, the EPM will ensure that the project complies with the
approved Action Plan and Fact Sheet. Should POR requirements change during the course of
design, the EPM will ensure, after consultation with the Project Team, that the Action
Plan and Fact Sheet is revised and resubmitted for approval by the Administrator. The EPM
will take the lead to ensure that all Project Team members, including the A-E and the DR,
incorporate all project requirements of the POR and that the documents are in compliance
with applicable codes and safety standards. The EPM provides evaluations on the
performance of the A-E at the end of the design, which becomes a permanent part of the
A-E's contract records.
During the construction phase, the EPM may act as the COR. If it is necessary to have a
COR on site during construction, the COR may be the Area Office Engineer or Facility
Engineer. The EPM is still responsible for general project management and will work
closely with the Project Team to provide such information as needed to support the roles
of the other team members.
AREA OFFICE ENGINEER (AOE):
The AOE serves as the technical advisor and resource to the Project Team during the
planning, design, and construction phases of all projects within their Area. It is the
responsibility of the AOE to see that the Area and location personnel are advised of the
actions and status of projects during all phases. The AOE is responsible for coordinating
the involvement of Area and location personnel, such as the Area Safety and Health Manager
(ASHM), Location Monitor (LM), Location Administrative Officer (LAO), and others as
appropriate. The AOE will assist the Project Team by addressing location specific
technical questions, and coordinating the review comments from the Area and location
personnel.
During the planning phase, the AOE may serve as a member of the A-E Evaluation Board.
The AOE is usually involved in development and review of the POR, Investigative Report,
and SOW for A-E services.
During the design phase, the AOE will review the design submittal with particular
emphasis on location specific issues such as utility requirements or unique location
requirements.
During the construction phase, the AOE will provide assistance to the Project Team, and
is invited to participate in progress meetings, equipment testing, and final inspections.
He/she will assist the RPR in arranging maintenance contracts for facility systems and
equipment and the establishment of contracts to install telephone systems, moveable
equipment, etc. The AOE may serve as the COR on some projects.
CONTRACTING OFFICER (CO):
The CO is an ARS Contract Specialist and the legal Government representative to the
contractors. He/she is authorized to enter, administer, and terminate contracts on behalf
of the Government. The CO is the only member of the Project Team with the authority to
obligate Government funds or change the contract. The CO may delegate certain contractual
authority not affecting the contract scope, performance time, or cost.
The CO is assigned to the project early in its conception and will continue with this
role through planning, design, construction, and close out of the project. The CO will
assist other members of the Project Team in meeting project goals and objectives. The CO
is responsible for ensuring that all planned or existing contractual activities or
instruments comply with all applicable laws and regulations, and that all activities are
conducted in a fair, impartial, and equitable environment. The CO shall ensure that
sufficient funds are identified by the fundholder for obligation.
The CO assists/participates with the Project Team in developing the Action Plan and
Fact Sheet. The CO officially designates the A-E Evaluation Board and provides regulatory
and procedural guidance to ensure appropriate selection activities and reports. The CO
makes final selection approval recommendations, and is the liaison between the A-E
Evaluation Board and the selection official.
The CO is responsible for guiding the Project Team through the contractual and business
management aspects of the project. The CO is responsible for ensuring that contract
performance complies with all contractual provisions including, but not limited to, scope,
budget, and schedule. The CO is responsible to ensure adequate contract performance and
contract management, monitor contract performance and budgetary events, conduct and
participate in project meetings, oversee and conduct negotiations, and other actions
necessary to assure adequate progression and protection of the Government's interest.
The CO will request and consider the advice of specialists in audit, law, engineering,
and other fields as appropriate, and the advice of the Project Team members. This advice
covers technical, legal, budgetary, reporting, and reprogramming activities.
The CO is responsible for informing Project Team members of all communications
concerning the project.
CONTRACTING OFFICER'S REPRESENTATIVE (COR):
The COR has a separate and distinct role and is usually the EPM. The assignment as
COR is made at the beginning of the contract by an official designation letter from the
CO, outlining the responsibilities, authority, and limitations. A copy of this designation
letter will be provided to both the contractors and the Project Team members.
COR is responsible for interpreting technical data in the A-E, construction, and CIC
contracts. The COR is responsible for the review of progress and pay requests for these
contracts and making acceptance/rejection recommendations to the CO. The COR may approve
minor changes to the project that do not affect the program requirements, price,
scope, or performance time of the contracts. Such changes will be documented and
communicated to the Project Team. The COR will provide the CO technical and administrative
recommendations and documentation regarding changes to terms and conditions of these
contracts.
The COR is responsible for discussing and resolving routine contract performance
concerns with the A-E, construction, and CIC contractors. The COR is responsible for
immediately notifying the CO of all concerns which may affect contract progress, cost, or
scope, and providing recommendations to the CO for resolution of these matters.
The COR is responsible for ensuring that all Team Members are kept advised of the actions
and progress of the project. The COR is usually the primary point of contact between the
Project Team and A-E, construction, and CIC contractors for day-to-day business, working
within the terms of their delegation.
The COR shall recognize that the EPM is still the lead point of contract for the
Project Team and shall work closely with the EPM to assure that information is provided,
as needed, to support the roles of the other Team Members.
SAFETY, HEALTH, AND ENVIRONMENTAL MANAGEMENT BRANCH: (SHEMB)
The SHEMB representative is a Facilities Division staff member and is a resource to
the Project Team for safety, health and environmental issues during the planning, design,
and construction of projects. Throughout the project, the SHEMB representative may be
consulted to provide safety, health, and environmental project requirements during the
development of the SOW. The SHEMB representative may also be consulted during construction
to address safety, health, and environmental matters. The SHEMB representative will
participate, as required, in project meetings, and serve as the primary decision maker
concerning waiver requests.
REAL PROPERTY MANAGEMENT BRANCH: (RPMB)
The representative of RPMB is a Facilities Division staff member responsible for
ensuring that all reality interest associated with the project have been completed,
including Federal-ownership of the property or lease agreement sufficient to cover the
Federal Government's investment in the property. The RPMB representative is responsible
for ensuring that easements, right-of-ways, or other land-use agreements for roads and
utilities in support of the project have been executed. The RPMB representative will
review each project to assure compliance with approved Master Plans, National Historic
Preservation Act, and Threatened and Endangered Species Act.
AREA SAFETY AND HEALTH MANAGER (ASHM):
The ASHM serves as the safety, health, and environmental advisor and resource to
the Project Team during the planning, design, and construction phases on projects within
their Area. The ASHM shall be consulted on safety, health, and environmental issues.
During the planning phase, the ASHM may be consulted to provide input on developing the
POR and the SOW for design. The ASHM will assist in the preparation of the variances on
safety, health, and environmental issues during the planning and site investigation
phases. Also, the ASHM may assist in prioritizing safety, health, and environmental items
to be incorporated in the SOW for design.
During the design phase, the ASHM may, as assigned, review the design submittal and
develop priority for safety, health, and environmental items to be incorporated into the
contract documents.
During the construction phase, the ASHM is to ensure all appropriate safety, health,
and environmental management related regulations are in place. The ASHM may participate in
final inspection and acceptance of the project.
LOCATION MONITOR (LM):
The LM is an ARS representative at the construction site (or nearby location) formally
designated by the CO, who serves as a point of contact for either the A-E, CIC, or the
construction contractor to provide information regarding location rules and regulations.
The LM designation, which is approved by the Area Administrative Officer, is normally made
to the Location Facilities Manager/Maintenance Engineer, LAO, or Location Coordinator. The
LM has no responsibility for construction inspection or supervision, and is not expected
to evaluate contractor performance. The LM acts an observer and is expected to notify the
COR or the CO if he/she becomes aware of unusual or important circumstances pertinent to
the contract. Examples of the situations in which the LM may get involved are: (1)
designating parking areas for contractor's employees, (2)coordinating use of government
facilities, restrooms, and utilities; (3) coordinating utility shutdowns and connections;
and (4), coordinating authorization for contractor to work beyond normal work hours. The
LM may participate in the design review stages and construction progress meetings to
provide familiarity with the scope of the project and to keep abreast of any changes.
COOPERATOR:
A Cooperator is a State or Federal agency or private organization having a mutual
interest in agricultural research that has entered into a valid and legal Memorandum of
Understanding, Cooperative Agreement, long-term lease, or similar document demonstrating
that a proposed cooperative effort is of benefit to people of the United States. A
Cooperator is not always involved in all major construction projects.
ARCHITECT ENGINEER (A-E):
The A-E is a private contractor who provides professional services of an
architectural engineering nature with primary emphasis on the design of research
facilities, laboratory support facilities, and administrative facilities. The design is
performed under the supervision of a registered or licensed professional architect or
engineer as required in the State where the project is located. The A-E also provides
investigative studies, assists in quality assurance of the construction project, assists
in project management, reviews submittals during construction, and provides consultative
services as needed. The A-E will contact the EPM for day-to-day business, working within
the terms of the contract. Adjustments to the contract will remain the authority of the
CO.
During the planning phase, the A-E finalizes the POR, and prepares the Environmental
Assessment and other investigative reports as may be required.
During the design phase, the A-E develops conceptual drawings and provides a
preliminary cost estimate. After approval of the conceptual plans, the A-E is tasked with
preparation of the final design and working drawings in a manner which incorporates the
various adjustments approved through the design review process. Upon approval, various
submittals of plans, specifications, and cost estimates are submitted for program,
technical, and budget review through completion of final design. The A-E may formally
conduct presentations at the various stages of design development and shall provide
complete documentation of all such meetings. The A-E keeps the EPM and the CO advised of
the status and progress of the project during design.
During the post-design and construction phase of the project, the A-E may be required
to participate in the pre-bid, pre-construction, and other meetings. The A-E may be tasked
to review and approve shop drawings, material submittals, review and comment on
construction contract modifications, and other related activities as directed by the
Government. The Government may confirm construction compliance with design intent through
a separate inspection contract, or may contract for these services through the design A-E
firm.
DESIGN REVIEWER (DR):
The DR is an independent contractor who provides professional services to review
the design submittals prepared by the design A-E. The design reviewer is required to
perform services under the supervision of a registered or licensed professional architect
or engineer.
The DR is to provide assurance to the Government that the design A-E is proceeding in
accordance with the project requirements. The DR will review the major design submittals
including cost estimates, referencing project requirements cited in the design A-E
contract, (i.e., final POR), geo-technical study, applicable Codes and Industry Standards,
and good practices of design. The DR will use the ARS Design Review Check List as part of
their review, but will be responsible to see that all project requirements are being
satisfied.
The DR will be tasked to perform Value Engineering studies for major construction
projects, when required. The DR may be tasked to perform the services of a CIC for major
construction contracts.
CONSTRUCTION INSPECTION CONTRACTOR (CIC):
The CIC is an independent contractor, generally an A-E firm, whose primary role is
to provide quality assurance that the construction project is being constructed as
designed, and to provide oversight to the Quality Control Plan of the construction
contractor. The CIC will consist of a CIC manager that has access to a technical staff
that can report to the project site in a timely manner on an as-needed basis. For major
construction projects, the CIC responsibility may be assigned as a task order to a
construction management firm or an A-E firm separate from the design A-E.
The CIC will monitor the Quality Control Plan of the construction contractor and ensure
that special test results, material certifications, etc., are obtained as required. In
cases where test results or certifications, etc., are not satisfactory, the CIC will take
immediate action to notify the construction contractor's Superintendent and the COR.
Keeping the COR informed of these findings will enable corrective actions to be
implemented by the CO, if necessary.
The CIC is to report to the COR all findings, observations, and communications with the
construction contractor. A daily construction log will be maintained by the CIC, and daily
Quality Assurance reports will be submitted concurrently to the CO and COR. If it is
identified that the construction contractor has made deviations from the plans, the CIC
will document these observations and bring them to the attention of the construction
contractor's Superintendent, the CO, and the COR. Keeping the CO and COR informed of these
findings will enable corrective actions to be implemented by the CO or other appropriate
Project Team members.
The CIC will assist the CO and COR in analyzing and categorizing construction contract
changes.
CONSTRUCTION CONTRACTOR: (CC)
The CC is an independent firm, hired under a Government contract, to provide those
professional construction services defined by Federal Acquisition Regulations, Part 36.
The specific work to be performed by the CC shall be set forth in writing in the specific
contract document. The CC's team may consist of the Prime Contractor, who has direct
contractual relationship with the Government, and various subcontractors and suppliers. No
contract exists between the subcontractors, suppliers and the Government. The CC shall
have full responsibility for the construction Project Team including coordination of work,
performance, material delivery and storage, permits, licenses, protection of property and
all other elements of construction. The CC shall maintain a competent Superintendent at
the work site at all times during performance of the contract.
The Contractor shall contact the CO or the COR directly on all matters of the contract
affecting changes to the contract provisions, contract scope performance time or cost. The
CO is the legal Government representative authorized to enter, administer, and terminate
contracts, and is the only member of the Project Team with the authority to obligate
Government funds or change the contract. The COR is usually the primary point of contact
for CC for day-to-day business, working within the terms of the contract.
In order to most effectively accomplish the construction contract, the Government may
form a partnership with the CC. This partnership would strive to draw on strengths of all
parties in an effort to achieve a quality project completed within budget, and on
schedule. This partnership would be bilateral in make-up and participation is totally
voluntary. The partnership is not a contractual agreement, nor does it create any legally
enforceable rights or duties to either party.
The CC must prepare and maintain a suitable Quality Control Plan. The CC shall develop
a progress schedule for approval by the CO and adhere to this schedule throughout the
contract. In accordance with Occupational Safety and Health Administration (OSHA)
regulations, the CC will assure that safety is maintained on the job site at all times.
Proposed change orders must be coordinated with the CO, COR, and CIC. The CC is
responsible for maintaining as built documents on the job site to show the construction of
a particular structure or work as actually completed under contract. The CC shall submit
shop drawings as required by the contract documents. The CC must attend all scheduled
progress meetings and report the progress of the project as required. During the close out
and warranty phase of the contract, the CC will in accordance with the contract, prepare
operation and maintenance manuals, ensure systems are fully functioning, provide system
demonstration to the RPR, COR, and other individuals designated by the CO. During the
warranty phase, the CC is required to respond promptly to requests for warranty service,
and shall be responsible to coordinate corrective actions as necessary to mediate
Government concern.
EXHIBIT 2
New ARS Research Center
Anywhere, USA
FACT SHEET
1. FTE INFORMATION:
Category | Current Facility | Planned Facility |
ARS Scientists Visiting Scientists Postdoctoral Fellows Graduate Students Admin. Personnel Other Total |
20 6 5 1 10 50 92 |
30 5 10 1 20 54 120 |
2. APPROPRIATION ALLOCATION TO DATE:
Strict adherence to the project budget will be required. The estimated construction
cost will be formulated in accordance with Agency guidelines and will be closely monitored
through all phases of the project to prevent a cost overrun situation.
FY 1997 Planning and Design FY 1998 Planning and Design FY 1999 Construction (Proposed) |
$ 1,400.000 (B&F) $ 1,000,000 (B&F) $23,000,000 (B&F) |
3. FACILITY SCOPE:
The new ARS Research Center is located in Anywhere, USA. The existing laboratory
facilities require extensive modernization to bring them into compliance with current
construction and safety and health codes and standards. There is no remaining space on the
cramped 3.9-acre site for construction of needed additional laboratory and other special
research facilities. A lease agreement has been executed with the University of Anywhere
for a 200-acre site parcel to relocate the new ARS Research Center.
The project scope consists of the construction of a laboratory/office building and
headhouse/greenhouse space at the laboratory complex site, and a farm center and research
field plots at the farm site.
Category | Gross Square Feet Current |
Planned |
Office/Lab Headhouse/ Greenhouse TOTAL |
35,945 46,812 82,757 |
53,740 58,860 112,600 |
4. LAND ACQUISITION COST: N/A
5. STAFF RELOCATION COST: N/A
6. PLANNING AND DESIGN BUDGET:
Predesign/Misc. (3%) Design (6%) Design Review/VE (3%) TOTAL |
$ 600,000 1,200,000 600,000 $2,400,000 |
7. CONSTRUCTION BUDGET:
Type of Space | Sq. Ft. | Total Cost |
Office/Lab Building Headhouse Complex Telecommunications SUBTOTAL - Estimated Construction Cost (ECC)
|
53,740 58,860 LS
|
$ 13,000,000 7,000,000 200,000 $ 20,200,000 $ 200,000 |
8. SCHEDULE: (Construction schedule may be slightly revised when
funds are appropriated.)
Design | Construction (FY-99 Proposed) |
Start - 2nd Qtr., FY-98 Complete - 2nd Qtr., FY-99 |
3rd Qtr., FY-99 1st Qtr., FY-00 |
9. OPERATING COSTS:
FY-96 - Present Facility 82,757 SF FY-00 - New Facility 112,600 SF |
$ 643,000 $ 1,126,000 |
10. ECONOMIC ANALYSIS:
N/A
Exhibit 3
FUNCTIONAL STATEMENT
1.0. INTRODUCTION:
The Conservation Production Systems and Remote Sensing Research Units (CPSRU and RSRU) are housed in the Fruit, Vegetable, Soil and Water Research Laboratory dedicated in 1958 to house Crops Research and Soil and Water Division programs that were greatly expanded at that time. Both units are being served by Group A facilities, presently including buildings 201, 202, 414, and three new greenhouses. Remote sensing techniques were used by Soil and Water Division personnel in the early and mid-sixties to document soil salinity and drainage conditions, and congressional funding that was received in 1967 permitted expansion of effort. It was not until a 1981 reorganization that the research was split into two groups.
The Soil and Water Conservation personnel have pioneered zero grade land leveling, manifold well drain systems, and ethylene glycol method of soil surface area determination; characterized and developed solutions for drainage and soil salinity problems; developed irrigation management practices for cotton, sorghum, citrus and sugarcane, and new lines of cotton; investigated new crops including quayule and kenaf. Because of requirements of the 1990 Farm Bill to control wind erosion and maintain adequate surface plant residue cover, research on the development of conservation tillage systems with crop rotations has greatly expanded. Additional benefits of this research are related to increased water use efficiency, reduced energy consumption, and increased profits. Research on an evaluation of weed and insect control interaction with conservation tillage systems is being conducted. personnel now in Remote Sensing determined the wavelengths for inclusion on satellites; pioneered modeling of light interactions with plant canopies, leaves, and leaf components, the development and application of spectral vegetation indices, and videography as a remote sensing tool. Remote Sensing personnel have also developed a geographic information system (GIS) for the Rio Grande valley. This technology is proving valuable for a wide range of applications.
Emphasis in soil chemistry and engineering has decreased and emphasis on plant science and biotechnology including weed science, pathology, and plant breeding has increased over the years. Periodic fund increases have made it possible to maintain a staff of about 12 professionals since about 1960.
1.1 Existing Programs:
1.1.1 Conservation Production System Research Unit (CPSRU)
The program of the existing Conservation and Production Systems Research Unit includes three primary CRIS projects, integrated production systems, sugarcane physiology, and kenaf breeding. Each of the projects is lead by a research scientist and is supported by 1 or 2 technicians. The unit is directed by a research leader, who administers, coordinates, and participates in the projects.
1.1.1 Integrated Production Systems
1.1.1.1.1 Mission: The objectives of the project are to develop
improved cultural practices for row crops in South Texas to optimize production
efficiency; develop conservation tillage and residue management systems for dryland and
irrigated agriculture; and develop pest management strategies which are compatible with
environmental quality and sustainable agricultural production.
1.1.1.1.2 Research Programs: Under dryland and irrigated
conditions, tillage (conventional, reduced, and no-tillage on ridges) and cropping
sequence (corn, cotton, and sorghum) are being evaluated in terms of productivity and
profitability. Effectiveness of mechanical and chemical methods of controlling weeds are
being assessed by visual evaluations and documentation of weed species and species shifts
over time in the various cropping rotations. Plant growth and crop yield, water use
efficiency, diseases, insects, and soil properties, as affected by tillage and crop
rotation, are being determined.
1.1.1.1.3 Staff: This project involves four of the unit scientists,
with each having primary responsibility in this area. These are a supervisory soil
scientist, agronomist (weed scientist), agricultural engineer, and horticulturist. Six
biological technicians provide support.
1.1.1.2 Sugarcane Physiology
1.1.1.2.1 Mission: This project
determines physiological and biochemical mechanisms limiting sugar accumulation and juice
purity in sugarcane, identifies genes that enhance early- season juice purity, and
determines the effect of soil salinity on sugarcane during development.
1.1.1.2.2 Research Programs: DNA probes, monoclonal antibodies,
and biochemical assays are used to determine the regulation of enzymes of sucrose
metabolism, especially sucrose synthase and invertase, in sugarcane storage tissue during
development and maturation of cultivars that vary in ripening. Sugarcane germplasm with
variable sucrose accumulation patterns, including cultivars, breeding lines and wild
relatives, are evaluated for biochemical pathways associated with high sucrose and early
ripening. Biochemical assays and ion
chromatography are used to evaluate sugar accumulation and metabolism in storage tissue of
sugarcane from salt-affected fields.
1.1.1.2.3 Staff: This program is lead by a plant physiologist.
Support is from two physical science technicians.
1.1.1.3 Improved Cultivars and Cultural Practices of Kenaf
1.1.1.3.1 Mission: The objectives of
this program are to develop improved germplasm and cultivars of kenaf and crotalaria with
increased yield, fiber and pulp characteristics needed by processors, improved seed
quality, and resistance/tolerance to nematodes, pathogens, insects, salinity, and lodging;
and to develop optimal cultural practices for efficient kenaf and crotalaria production
with required fiber quality traits.
1.1.1.3.2 Research Program: Kenaf and crotalaria germplasm will be
evaluated for genetic variability in yield, fiber-pulp quality and resistance to pests,
diseases, and lodging. Optimum cultural practices will be developed for efficient kenaf
and crotalaria production through cooperative studies with Rio Farms, Inc. at Monte Alto,
Texas. Cultural studies will include crop rotations, plant populations, date of planting,
and pest management.
1.1.1.3.3 Staff: The project is lead by a plant geneticist and
supported by two biological technicians.
1.1.2 Remote Sensing Research Unit (RSRU)
The RSRU program consists of two CRIS projects, a larger one that has continued over the
years and a smaller one initiated in late 1993 to grow and spectrally characterize
selected narcotic plant species.
1.1.2.1 Remote sensing technology for resource assessment,
monitoring, and management
1.1.2.1.1 Mission: The unit develops, evaluates, and transfers
remote sensing technology for natural resource management and investigates, characterizes,
and models natural processes using remote sensing.
1.1.2.1.2 Research Programs: Research programs currently deal with
(1) developing and testing state-of-the-art all digital videographic systems (2)
development and use of geographic information systems (GIS) in conjunction with Bureau of
Census Tiger Line Data, SGS topographic elevation and feature maps, and image analysis
procedures to characterize and map natural vegetation, wildlife habitats including that of
Africanized honey bees (AHB), range resources, weed distributors, soil salinity in
cropland, etc. (3) Joint use of ground observations, spectral
observations, and image analysis to determine yield and stress maps of cropped fields and
areas... etc.
1.1.2.1.3 Staff: This project is staffed by two scientists (range
scientist who is the research leader and ecologist) and part of the time of a scientist
(soil scientist) from the other project; 2 category three scientists (remote sensing
specialist and soil scientist); an electronic technician; a biological and an agricultural
research technician; a computer specialist; and, a secretary. Cooperative work is done
with a 1890 Land Grant University (Alabama A&M University) student, The University of
Texas at Edinburgh, The Parks and Wildlife Service, Texas A&M University - Kingsville,
University of Florida, Indiana State University, Sul Ross State University, and numerous
ARS locations.
1.1.2.2 Ecological, phenological, and spectral characteristics of
plants
1.1.2.2.1 Mission: Exploit the ecological, phenological, and
spectral characteristics of plants to aid in their remote detection and identification in
natural and cultural environments.
1.1.2.2.2 Research Programs: First emphasis has been on acquiring
greenhouse, headhouse, and plot area for the work and securing them. Soil will be amended
to vary the pH and root zone physical conditions. The effects on growth of weather
stresses (high ambient temperatures, frosts, water management), day lengtht,
ambient temperature, insects, herbicides, and diseases will be observed, recorded, and
interpreted in terms of growth and production, and measurements will be taken for tuning a
plant growth model.
1.1.2.2.3 A scientist and a technician man the local project.
Collaboration is with several other laboratories on the same general project. Expertise of
personnel of the other CRIS unit will be utilized to make and interpret spectral
observations.
1.2 Facility Requirements:
The mission of the CPSRU is to develop new knowledge and technology through genetic,
biological, physiological, and agronomic studies that will lead to more efficient use of
soil, water, and energy resources in crop production systems. Much of the research is
field- oriented and is conducted at Moore Field, near Mission, and at the North Farm, on
Highway 88 north of Weslaco. There is a need, however, to provide laboratory support for
the field programs related to sugarcane physiology, cotton and kenaf breeding, and
conservation tillage. Of primary importance is expanded greenhouse space and laboratories
to process soil and plant samples.
The mission of RSRU is to develop and transfer remote sensing technology for detecting,
characterizing, and predicting agroecosystem behavior utilizing geographic information
systems interlinked with global positioning systems, including descriptive mathematical
equations.
1.2.1 Scientist (Category I): This facility serves two research
units. Seven Category I scientists in the CPSRU and three Category I scientists in the
RSRU are needed to adequately carry out the research mission. Condensed job descriptions
for each position in each unit are as follows:
1.2.1.1 Conservation and Production Systems Unit
(a) Research Leader: Supervisory Soil Scientist. Coordinates,
assigns, evaluates, and administers research of the unit involving work on conservation
tillage systems, sugarcane physiology, and kenaf and crotalaria.
(b) Research Plant Geneticist: Has primary responsibility for
developing improved germplasm and cultivars on kenaf, crotalaria, and cotton.
(c) Research Agronomist (Weed Science): Has primary responsibility
for development of improved weed control methods, primarily for cotton, sorghum, and corn,
in conservation tillage Systems.
(d) Research Horticulturist: Has primary responsibilities for
improving cultural practices for vegetable crops in South Texas.
(e) Research Plant Physiologist: Proposed position having
responsibilities for determining physiological and environmental barriers to cotton and
corn yields in South Texas.
(f) Research Plant Physiologist: Has primary responsibilities for
determining biochemical limitations to sucrose accumulation in sugarcane.
(g) Agricultural Engineer: Has responsibility for water use
efficiency research for better irrigation water use.
1.2.1.2 Remote Sensing Research Unit
(a) Research Leader: Supervisory Range Scientist. Coordinates,
assigns, evaluates, and administers research of the unit involving the use of remote
sensing techniques for the management of natural resources and the integration of remote
sensing with geographic information system technology.
(b) Soil Scientist: Has primary responsibility for application of
remote sensing for management and yield assessment of crops.
(c) Ecologist: Has primary responsibility for development of
geographic information system technology for agricultural and natural resource assessment.
1.2.2 Support Staff:
1.2.2.1 CPSRU:
(a) Secretary: Provides secretarial support to the Research Leader and scientists of the unit.
(b) Biological Technicians: Because the primary mission of the unit is to conduct field research, each of the six scientists will be supported by one or two technicians.
1.2.2.2 RSRU:
(a) Secretary: Provides secretarial support to the Research Leader and scientists of the unit.
(b) Remote Sensing Specialist: Has primary responsibility to assist in development and assembly of imaging equipment and its application to natural resource management.
(c) Soil Scientist (Category III): Provides expertise in developing a computer-based soil map for the Lower Rio Grande valley.
(d) Electronics Technician: Has primary responsibility for providing expertise on electronics and assembly of imaging equipment.
(e) Computer Specialist: Has primary responsibility for developing computer programs to assist in image analysis.
(f) Biological/Agricultural Technicians: Each of the 3 category 1 scientists is supported by a full-time technician.
(g) President's Stay in School. Teacher Research Fellow, or other part-time Program: One person assists the secretary.
(h) Graduate Students: A Ph.D. candidate
from an 1890 Land Grant college is doing his Ph.D. research at this facility.
2.0 SPACE REQUIREMENTS SUMMARY:
The Group A facilities occupied by CPSRU and RSRU can be divided into three categories:
1) space used by both groups in Building 201 (common area); 2) space used primarily by
CPSRU in Building 201 and Buildings 208, 209, 210, and N03; and 3) space used primarily by
RSRU in Building 201 and Building 202. The summary of space requirements for each building
(Table 2-1) identifies all rooms and net square footage for the function areas of the
proposed facility. Service areas such as utility rooms, corridors, and lobbies are not
included in the net square footage. Space data sheets for each room follow these
summaries.
SPACE REQUIREMENT SUMMARY
Building 201
No. Office/Meeting Space | Sq. Ft. |
1. Common: Conference/Meeting Room | 400 |
2. RSRU: Research Leader's Office - Supervisory Range Scientist | 190 |
3. RSRU: Secretary's Office | 200 |
4. RSRU: Scientist's Office - Research Plant Scientist | 135 |
5. RSRU: Scientist's Office - Remote Sensing Specialist | 135 |
6. RSRU: Scientist's Office - Post Doc | 135 |
7. RSRU: Technician's Office (2 per office) | 150 |
8. RSRU: Technician's Office (2 per office) | 150 |
9. CPSRU: Research Leader's Office - Supervisory Soil Scientist | 190 |
10. CPSRU: Secretary's Office | 150 |
11. CPSRU: Scientist's Office - Research Agronomist | 135 |
12. CPSRU: Scientist's Office - Research Geneticist | 135 |
13. CPSRU: Scientist's Office - Research Plant Physiologist (Sugarcane) | 135 |
14. CPSRU: Scientist's Office - Research Agricultural Engineer | 135 |
15. CPSRU: Scientist's Office - Research Horticulturist | 135 |
16. CPSRU: Scientist's Office - Research Plant Physiologist (Cotton) | 135 |
17. CPSRU: Technician's Office (2 per office) | 150 |
18. CPSRU: Technician's Office (2) | 150 |
19. CPSRU: Technician's Office (2) | 150 |
20. CPSRU: Technician's Office (2) | 150 |
21. Common: Office Supply Storage | 100 |
22. Common: Copier/File/Mail Room | 300 |
23. Common: Bathroom/Shower/Locker Room - Women | 220 |
24. Common: Bathroom/Shower/Locker Room - Men | 220 |
25. Common: Small Meeting Room | 300 |
26. Common: Women's Toilet Room | 100 |
27. Common: Men's Toilet Room | 100 |
|
4,585 |
Building 201
No. | Laboratories | Sq. Ft. |
Ll | RSRU: Laboratory - Plant & Soil Analysis | 600 |
L2 | RSRU: Laboratory - Plant Science | 600 |
L3 | RSRU: Laboratory - Electronics Lab | 300 |
LA | CPSRU: Laboratory - Soil Physics | 600 |
L5 | CPSRU: Laboratory - Horticulture | 800 |
L6 | CPSRU: Laboratory - Kenaf/Cotton Breeding | 400 |
L7 | CPSRU: Laboratory - Weed Science | 600 |
L8 | CPSRU: Laboratory - Sugarcane Physiology | 1,300 |
L9 | CPSRU: Laboratory - Radioisotope | 300 |
L10 | CPSRU: Laboratory - Agricultural Engineering | 600 |
L11 | CPSRU: Laboratory - Cotton Physiologist | 600 |
L12 | CPSRU: Sample Storage | 150 |
L13 | CPSRU: Autoclave/Dishwasher Room | 120 |
Total Laboratories | 6,970 |
Building 201
No. | Storage | Sq. Ft. |
S1 | CPSRU: Freezer/Refrigerator/Incubator Room | 250 |
S2 | CPSRU: Equipment Storage | 240 |
S3 | Common: Janitorial Storage | 80 |
S4 | Common: Audio-visual Storage | 80 |
Total Storage | 650 | |
Total Building 201 | 12,205 |
Building 202 (RSRU)
No. | Office/Meeting Space | Sq. Ft. |
1. | Scientist's Office - Ecologist | 150 |
2. | Scientist's Office - Post Doc | 150 |
3. | Scientist's Office - Remote Sensing Specialist | 150 |
4. | Technician's Office (2 per office) | 150 |
5. | Technician's Office (2 per office) | 150 |
6. | Restroom - Women | 35 |
7. | Restroom - Men | 35 |
8. | Storage Room | 150 |
9. | Storage Room | 140 |
Total Office | 1,110 |
Building 202 (RSRU)
No. | Laboratories | Sq. Ft. |
L1 | Laboratory - Geographic Information System | 300 |
L2 | Laboratory - Electronics and Image Analysis | 300 |
Total Laboratories | 600 | |
Total Building 202 | 1,710 |
Building 414
FM1015 Site (CPSRU)
No. | Headhouse Space | Sq. Ft |
1. | Data Processing Office | 180 |
2. | Soil Storage | 300 |
3. | Soil Preparation/Drying | 360 |
4. | Plant Preparation/Drying | 360 |
5. | Work/Shop Area | 600 |
6. | Seed Storage | 300 |
7. | Growth Chamber Room | 300 |
8. | Chemical Storage | 120 |
9. | Cotton Seed Acid Delinting | 160 |
10. | Hydrology Laboratory | 1,200 |
11. | Bathroom/Shower | 220 |
Total Building 414 | 4,100 |
No. | Greenhouses (N03) | |
G1 | Greenhouse/Sugarcane & Horticulture | 1,600 |
G2 | Greenhouse/Weeds | 1,600 |
G3 | Greenhouse/Kenaf & Cotton | 1,600 |
Total Greenhouses | 4,800 |
Space Data Sheet
BUILDING 201 - COMMON AREA
SPACE DESIGNATION | Conference Room | |
REQUIREMENTS | ||
Number Required: | 1 | |
Number of Occupants: | up to 20 | |
Net Area: | 400 sq ft | |
Hours of Use: | varies | |
Access: | Visitors, General
|
CONSTRUCTION | ||
Floor: | Carpet | |
Base: | Vinyl | |
Walls: | Dry Wall | |
Ceiling: | Acoustic | |
Special Features: | Noise reduction between offices
|
|
ACTIVITY FUNCTION | Unit meetings, small group discussions, presentations to visitors | |
RELATIONSHIPS | Centrally located, accessible to general public |
SYSTEMS | ||
HVAC: | Heating, cooling, and ventilation for personal comfort | |
Plumbing: | None | |
Electrical: | Fluorescent lighting, 120 v outlets; Provide several levels of room darkening; Clock outlet; electronic control of projection screen and projector; | |
Communications: | Telephone | |
EQUIPMENT | ||
Fixed: | White board; Bulletin board; electrically operated projection screen; lockable storage cabinet for audiovisual equipment; conference modular tables and upholstered chairs; podium with audiovisual controls; | |
Movable: | Projection table; slide projector; tv/vcr; overhead projector |